64
7.2. Erection and alignment of equipment support structures (wherever
required) as per DVC design.
7.3. Erection, alignment and adjustment of all equipments like CB, CT, isolator,
etc.
7.4. Erection and alignment of pipe Bus Support Insulators and 3”/2.5” /1.5”
IPS AL tubes including connection with respective equipment and buses.
7.5. Erection, alignment and stringing of the swing buses including dropper
and jumper connection between ‘A’ frame and gantries, Stringing of earth wires
between gantries.
7.6. Painting of structural steel works, steel cable racks/trays etc including
supply of paints.
7.7. Erection, testing & commissioning of different equipments like
Transformer, circuit breaker, current transformer, isolators, control & relay panels
(for transformer), RTCC panels.
7.8. Laying, dressing, cleating, clamping and termination of all Control and
Power cables including supply of the termination, cleating, crimping, clamping
and dressing materials.
7.9. Supply of all consumables including bolts, nuts, washers etc. as required
for the complete job.
7.10. Erection and alignment of duplex Control & Relay Panels, and other
miscellaneous Panels inside the sub-station Control Room Building/Switchyard.
7.11. Arrangement of insurance coverage for all equipment in stores including
those to be supplied by DVC during transit, storing, erection and commissioning
at site (the amount of insurance charges will be reimbursed by DVC).
7.12. Commissioning in presence of DVC team of representatives and carrying
out of all rectification repair or adjustment work found necessary during
inspection, testing, commissioning and trial run.
7.13. Return of all excess materials to the DVC specified stores at Maithon.
7.14. The contractor shall submit ‘BAR CHART’ showing the commencement
and completion of all activities.
8. Commissioning:
After Completion of all work related to installation, Erection GOMD is called for
Pre-commissioning and in the mean time an application is made to CEA for
inspection. After receipt of observation from GOMD and CEA, compliance report
is sent to GOMD and CEA (with CEA charge). CE A send an approval for
energization. GOMD may again check for the compliance. Then GOMD call CTC
for testing and commissioning. After Testing all equipments Line or Substation
charged.
Before line is energized, visual examination of the line shall be carried out to
check that all nuts and bolts are tight and insulators and accessories are in