Methode Statement OF Bor Pil and HSE For Project Civil.
Size: 1.58 MB
Language: en
Added: Aug 05, 2024
Slides: 14 pages
Slide Content
PEMERIKSAAN TERHADAP : K-3 RAMPAS, FIRE EXTINGUISER, SAFETY LINE, SAFETY NET. APD, P3K INPUT PROSEDUR K 3 Quality Supervisor DIPERBAKI Pelaksana / Ass. Pel. Pengawas K3 P E N A W A S A N RUTIN NO PEMASANGAN : TASK RAMBU-RAMBU K 3 PEMADAM KEBAKARAN PAGAR PENGAMAN PERIKSA : LOKASI KEKUATAN YES DISETUJUI - JARING PENGAMAN - KEAMANAN Pengawas K3 Pengawas K3 Pelaksana / Ass. Pelaksana OUTPUT LAPORAN HARIAN P e n g a wa s K 3 I M P L E M E N T A T I O N P R O C E D U R E K - 3
K 3 TERHADAP SISTEM OIL PIPE INPUT PROSEDUR K 3 OIL PIPE SYSTEM Quality Supervisor DIPERBAKI NO DIPERIKSA YES BERSAMA Pengawas K3 M e c h a ni c a l W o r k TASK RENCANA GAMBAR SISTEM OIL PIPE : DRAIN INSTALLATION PIPE EXISTING & LIFTING INSTALLATION OIL PIPE Mechanical Work INSTALLATION OIL PIPE SESUAI GAMBAR RENCANA Mechanical Work Mechanical Work P E L A K S A NA A N PEKERJAAN OUTPUT INSTALLATION PIPE BAIK - LAPORAN HARIAN Pengawas K3 Mechanical Work P R O S E D U R P E L A K S A N AA N K 3
A. DATA TEKNIS : NAMA PROYEK JUMLAH TITIK PONDASI DIAMETER BORED PILE KEDALAMAN BORE PILE : : : : MUTU BETON MUTU BESI UNTUK SPIRAL MUTU BESI UNTUK TULANGAN POKOK VOLUME BETON PEK. TTK BORED PILE BERAT KERANJANG : : : : : B. PERALATAN YANG DIGUNAKAN : SERVICE CRANE KELLY AUGER MACHINE DIESEL GENSET PIPE CASING DIA. 0.8 M, LENGTH = 16 M CLEANING BUCKET PIPE TREMIE THEODLITE READY MIX (TRUCK MIXER) TREMIE PIPE CONE C. SQUENCE OF WORKS : PEKERJAAN PERSIAPAN UKUR DAN TENTUKAN POSISI TITIK – TITIK BORE PILE DI SITE BUAT PABRIKASI KERANJANG BESI BORE PILE BUAT SHEDULE PENGECORAN BORED PILE DAN TERUS DIKENDALIKAN 4. BUAT FORMAT UNTUK MONITORING REPORT BORE PILE PEKERJAAN BORED PILE SET ALAT PADA POSISI TITIK YANG AKAN DI BOR 2. BILA KONDISI LAPISAN TANAH BAIK - BOR SAMPAI KEDALAMAN 6 m SAJA DAN PASANG CASING 6 m TEMPORARY FULL CASING 5 – 6 M BILA KONDISI LAPISAN TANAH JELEK GUNAKAN FULL CASING UNTUK MENCEGAH KELONGSORAN TANAH PADA SAAT PROSES BORING MASUKKAN FULL CASING KEDALAM LUBANG BOR SEBELUM PROSES PENGEBORAN DIMULAI DENGAN ALAT BANTU VIBRO HAMMER GENSET METHODE KERJA PONDASI BORED PILE
METHODE KERJA PONDASI BORED PILE KEMUDIAN DILANJUTKAN DENGAN PROSES PENGEBORAN SAMPAI KEDALAMAN YANG DIKEHENDAKI CHECK APAKAH KEDALAMAN YANG DIKEHENDAKI SUDAH TERCAPAI ELEV. – 6.00 T E MPO R A RY CASING 6 M BERSIHKAN LUMPUR PADA DASAR LUBANG BOR DENGAN BUCKET CLEANING SELAMA PROSES BERLANGSUNG, CATAT : KEDALAMAN MUKA AIR TANAH JENIS LAPISAN TANAH BERIKUT DEDALAMAN DAN KETEBALAN DARI LAPISAN TANAH 8. BUAT LAPORAN HARIAN BORE PILE ELEV. – 6.00 TEMPORARY FULL CASING (BILA DIPERLUKAN) CLEANING BUCKET
METHODE KERJA PONDASI BORED PILE D. CONCRETE WORK PESAN BETON K - 400., SLUMP 18 +/- 2 CM, KE BATCHING PLAN PASANG KERANJANG BESI ELEV. – 6.00 TEMPORARY FULL CASING DIA. 80 cm L=16 M KERANJANG PEMBESIAN KERANJANG PEMBESIAN PIPA TREMI TEMPORARY FULL CASING DIA. 80 cm L=16 M PASANG PIPA TREMI BILA TERDAPAT MUKA AIR TANAH DALAM LUBANG BOR JIKA TIDAK ADA AIR TANAH PENGGUNAAN PIPATREMIC TIDAK MUTLAK DIPERLUKAN (CUKUP PAKAI CORONG)
METHODE KERJA PONDASI BORED PILE 5. PROSES PENGECORAN PONDASI BORE PILE SELAMA PROSES BERLANGSUNG, CHECK ADAKAH VOLUME TEORITIC PER LUBANG SUDAH SESUAI DENGAN VOLUME BETON YANG DIKIRIM / DICOR KEDALAM LUBANG 6. 7. SEGERA SETELAH PENGECORAN SLESAI, TARIKTEMPORARY CASING DARI LUBANG BOR PEKERJAAN BOR SELESAI TEMPORARY FULL CASING KERANJANG BESI PIPA TREMI TEMPORARY FULL CASING D AS AR EXISTING
METHODE OF BORED PILE FOUNDATION 1.25 M 13 M BORE PILE DIA. 80cm OVER POUR WILL BE CUT OFF SAND FILLING STRUKTUR PONDASI BORED PILE A. METHODE URUTAN BORED PILE AND COR 8. BILA BATAS PENGECORAN AKHIR PONDASI BORE PILE TERLETAK DIKEDALAMAN TERTENTU DARI MUKA TANAH - ISI VOLUME LUBANG TERSEBUT DENGAN PASIR DENGAN DASAR PERTIMBANGAN K 3
FLOW CHART METHOD OF BORED PILE WORK
METHODE PEKERJAAN BORED PILE A. SEBELUM PENGEBORAN DIBUAT TEST-PIT TERLEBIH DAHULU DAN SEGALA SESUATU PEKERJAAN SURVEY PENGEBORAN DIBUAT DALAM 2 (DUA) TAHAPAN YANG BERBEDA YAITU : ZONE A ZONE B MENGGUNAKAN 1 (SATU) UNIT ALAT BOR DAN 1 (SATU) UNIT SERVICE CRANE C. PEMBUATAN (RANJANG) PEMBESIAN DISESUAIKAN LOKASI STOCK PILE D. CAPASITAS PRODUKSI KURANG LEBIH 2 – 3 TITIK/HARI S TA R T UITZET BONGKAR ASPAL/ RIGID. PAV STEL BESI ( R ANJAN G) CASSING + VERTICALITY + MASUK BESI RANJANG PENGEBORAN GALIAN 1.50 – 2.00 M SETTING ALAT TUTUP KEMBALI BEKAS LUBANG FINISH COR
METHODE PEKERJAAN BENTONITE A . D A T A TEK N I S S E B AG A I B E R I KU T : - DIA. 60 cm - L = 11 – 18 m - 1 m 3 = 60 kg S E M U A B EN T O NIT E + 300 kg SEMEN B. PENENTUAN TITIK BOR C. PENGEBORAN SESUAIKAN PEIL KE D ALA M A N Y AN G DIT E NTUK A N D . COR YAITU : T UANG K A N S E M U A S E M EN BENTONITE (SESUAI MIX DESIGN) KEDALAM BUCKET COR / CONCRETE PUMP KEMUDIAN LU A P AN N Y A D IAL I R K A N K E T A N K BENTONITE SETELAH SEMEN BENTONITE MASUKKAN KEDALAM LUBANG SAMPAI MELUAP DAN FRESH S EHIN G G A DID A P A TK A N KA P A S TIA N B A H W A LU B AN G TELA H F UL L S ELA N J U TN Y A S E GE RA P I P A TREMIE DAN CASING DICABUT A R T I N Y A B AH W A P E M B U A T A N BENTONITE PILE TELAH SELESAI
METHODE PEKERJAAN JEMBATAN ( TOP DOWN ) A. BONGKAR ASPAL / RIGIT PAV DAN GALIAN TANAH DAN PEMOTONGAN KEPALA BORED PILE B. PENGUKURAN UNTUK MENENTUKAN PEIL DAN BUAT / PASANG BEKISTING YAITU TERDIRI : PEMADATAN TANAH PAS. LANTAI KERJA PAS. MULTIPLEX 12 mm (BILA TIDAK TERGALI MAKA MENGGUNAKAN BEKISTING BATACO) C . STEL PEMBESIAN SESUAI GBR / BISTAT D . PENGECORAN YAITU SETELAH PEMBERSIHAN DAN PENENTUAN PEIL BORED PILE MULTIPLEX 12 mm LT. KERJA COR CAPPING BEAM COR (PLAT JEMBATAN
METHODE PEMANCANGAN SHEET PILE A. PEMANCANGAN DIBUAT DALAM 2 TAHAP BERSAMAAN YAITU SISI KIRI DAN KANAN (LIHAT GAMBAR) DENGAN MENGGUNKAN 2 ALAT YAITU MASING-MASING 1 UNIT DRIVE PILING DAN 1 UNIT SERVICE CRANE PENGIRIMAN DARI WORK SHOP DISESUAIKAN DENGAN HASIL PEMANCANGAN DILAPANGAN (KARENA STOCK PILE TERBATAS) B. SEBELUM PANCANG LEBIH DAHULU DIBUAT TEST-PIT DAN GUIDE BEAM SEPANJANG RETAINNING WALL SEBAGAI REFERENSI (HARUS KOKOH / KUAT) UNTUK CEK TERHADAP VERTIKAL / HORIZONTAL C . CAPASITAS PRODUKSI KURANG LEBIH 4 – 5 TITIK/HARI D AN H A R U S A D A D A T A K A L E ND E R I N G S TA R T UITZET BONGKAR ASPAL/ RIGID. PAV K E D A L A M AN SHEET PILE SHEET PILE UP PASANG GUIDE BEAM GALIAN 1.50 – 2.00 M SETTING ALAT TUTUP KEMBALI BEKAS LUBANG FINISH PEMANCANGAN
FLOW CHART PEKERJAAN S TA R T PERSIAPAN KOORDINASI DENGAN INSTANSI TERKAIT JARINGAN/PIPA/GAS/DLL / PELEBARAN JALAN PADA TROTOAR / PENEBANGAN PEMINDAHAN POHON CAPPING BEAM PEKERJAAN SHEET PILE GALIAN 1.50 – 2.00 M TRAFIC MANAGEMENT FINISH TRAFIC MANAGEMENT PEKERJAAN BORED PILE PEIR / ABUTMENT JEMBATAN SLAB & OPRIT JEMBATAN Y A / T I D AK Y A T I D AK
FLOW CHART PEKERJAAN S TA R T PERSIAPAN KOORDINASI DENGAN INSTANSI TERKAIT JARINGAN/PIPA/GAS/DLL / PELEBARAN JALAN PADA TROTOAR / PENEBANGAN PEMINDAHAN POHON CAPPING BEAM PEKERJAAN SHEET PILE GALIAN 1.50 – 2.00 M TRAFIC MANAGEMENT FINISH TRAFIC MANAGEMENT PEKERJAAN BORED PILE PEIR / ABUTMENT JEMBATAN SLAB & OPRIT JEMBATAN Y A / T I D AK Y A T I D AK