Site Report: Measurement 1
Building Materials
Construction Technology
Jake Sia Chyi Sern 0314396
2
Contents
Objectives of site visit ................................................... 3
Details of the project ................................................... 4
Observations .................................................... 5
Conclusion .................................................... 21
3
Objective of site visit
To observe the different activities and techniques carried out on site.
To explore the various types of building materials and machinery used on site.
Aware of the items measurable for sub-structure and reinforced concrete frame works.
To have a feel of how the condition of the site really is and how safety is a priority.
To have an up-close view of the entire building structure as opposed to seeing it in the
drawings.
4
Details of the project
-25 storeys
-2 basement floors of carpark, levels 1-2 will be the shopping areas, levels 3-6 will be
another carpark area, levels 7-24 will be the apartments.
-Approximate cost of RM100million for the entire project
-AIKBEE TIMBERS (employer), LT LEONG SEKUTU (architect), PERUNDING MAJUJAYA
(civil & structural engineer), KEW & ASSOCIATES (mechanical & electrical engineer), PCM
COST PERUDING (quantity surveyor), ENCORP CONSTRUCT (main contractor).
5
Observations
Ground floor
The overall view of construction
Construction netting & scaffolding can be seen on the exterior of the building
6
Mesh fabric reinforcement bars & timber stored on site
Security room right in front of the entrance
7
The safety & health officer, in charge of the safety and well-being of those on site
Parts of scaffolding & cement stored on site
8
Scaffolding in the centre of the building possibly used for installing the formworks and
pouring the concrete
Pipes, timber and other resources stored on site
9
Basement
The basement level where the workers temporarily stay for the night
Basement carpark
10
More scaffolding used for various tasks namely the piping
Air conditioning ducts stored waiting to be installed
11
Wall piles to support the base of the building and for extra anchorage
Ground floor-basement staircase
12
Ramp to the first floor carpark
The old building on site waiting to be demolished or continued upon
13
Reinforcement bars & stirrups for the ramps
Floors above ground level
The frame of the lifts
14
Scaffolding in the middle of the building from the ground floor
Starter bars for the continuation of the next section of concrete works
15
Workers positioning the reinforcement bars in place
Aerial view of part of the site
16
Back to ground floor
Scaffolding on the exterior of the building to gain easy excess to the upper floors
Wires to be installed along the inside of the orange pipe
17
Formwork for sides and soffits of staircase
Production of spacers used to determine concrete cover
18
Site office from the outside
Site office for the consultants to hold meetings and various other functions
19
The drawings for the whole project
Tower crane at the front of the building used to carry heavy loads onto the upper floors
20
Fresh fabric reinforcement bars just being delivered to the site
21
Conclusion
From this site visit, I have experienced for the first time what it feels like to be in a
construction site and I can say it is pretty exciting. Apart from the experience, this site
visit also helps me to visualise the items that needs to be measured and how it is
properly placed in real time. I also see that safety is very important in the site especially
for us newbies. It also seems like a good place to talk to some of the people involved to
get more insight on this field. Teamwork is also important at a site that’s where
different professions come together to work on the project. For it to work, the team
must rely on each other and must constantly interact with one another.