PUBLIC WORKS
Presented by:
Frank Orta
Public Works Director
2024 STREET MAINTENANCE PROGRAM
ITEM # 10
AUGUST 12, 2024
FY 2024 STREET SUMMARY–PUBLIC WORKS
Seek Council authorization to award contract for
2024 Street Maintenance Program (SMP)
Clark Construction submitted the lowest, qualified
bid
Total of contract is not to exceed $888,251.96,
of $1,000,000 budgeted for FY 2024 SMP
2
BACKGROUND INFORMATION
February 26, 2024, Council authorized engineering
contract with Freese and Nichols for the 2024 SMP
program
Amended contract on May 28
th
Advertised in SA Express-News –June21
st
& June
26
th
, 2024
Pre-bid meeting –June 28
th
Bids opened & reviewed –July 24
th
3
2024 STREET MAINTENANCE PROGRAM
2024 SMP includes following project areas
Broadway Pedestrian Crossing, north of College
Broadway –Blue Bonnet to Primrose
Broadway –Primrose to Claywell (striping only)
Estes Ave –Patterson to Cambridge Oval
Townsend –north of Cambridge Oval to north of midblock crossing (road
reprofiling)
Arcadia –Cleveland Ct to Broadway (Add-Alternate)
Broadway intersection, N of Austin Hwy*
Ellwood, Cleveland Ct to Austin Hwy*
Kampmann, Ellwood to Austin Hwy*
Marcia, Cleveland Ct to N New Braunfels*
* To be negotiated with contractor under change order allowance
BACKGROUND CON’T
Three bids received:
Clark Construction in the amount of $710,601.57
Lone Star Paving $732,284.90
J&P Paving $993,030.39
5
POLICY ANALYSIS
Local Government Code Sec. 252.048 provides
City ability to submit change order requests to
increase original contract amount by up to 25
percent, with Council authorization
Freese and Nichols recommends awarding 2024
qualified low bid contract to Clark Construction
6
COORDINATION
Freese and Nichols
Public Works
City Attorney
City Manager
7
FISCAL IMPACT
Authorization results in fiscal expenditures:
$710,601.57 for bid contract (Clark Construction)
The City has an option to add 25% for favorable
contract in the amount of $177,651.00
Total contract is not to exceed $888,251.96, of which
$1,000,000 is currently budgeted in FY 2024 Budget
8