STAFF REPORT
2025 SMP PROJECTS
ITEM # 11
MARCH 10, 2025

SUMMARY
Council budgeted $1 million for streets & sidewalk
improvements in 2025 Street Maintenance Program
(SMP)
Agreement with Mendez Engineering,for
engineering design & project management services
2025 SMP proposal of road rehabilitation in 5
project areas
Impacted by water main replacement improvements

BACKGROUND
SMP projects identified in conjunction with the 4x2
/ Water Main Relocation effort
Mendez Engineering proposal for bid and project
management approved in November 2024
Final set of plans reviewed and accepted by staff
in February 2025

SMP PROJECT LOCATIONS
Cloverleaf Ave. between Broadway
& New Braunfels Ave.
Wildrose Ave. between Broadway
& New Braunfels Ave.
Wintergreen Dr. between Blue
Bonnet Blvd & Primrose
Buttercup Dr. between Blue Bonnet
Blvd & Primrose Pl.
*Add Alternate: Rosemary Ave.
between Broadway & New
Braunfels Ave.

TIMELINE & NEXT STEPS
2025 SMP contract advertised for bid March 12th
Projected bid opening April 15
th
Council consideration of most qualified bid April 21st
Projected construction between June & August 2025