20 BP AND BCC STATUS PHASE 11 CONTRACTS SL.NO Contract Milestone Name Energization Date Design Consultant Building Permit (BP) and Building Completion Certificate (BCC) DC1 DC2 Building Permit Building Completion Target Dates Remarks Last Presentation Current Date 1 GTC/488B/2012 66 / 11kVGrand Hamad Avenue (New) S/S 16-May-17 AL SADD Received on 16.10.14 Received on 10.03.17 Received on 29.10.2017. 31.03.2023 31.03.2023 NCC is coordinating with the subcontractors for the compliance of MOI-SSD comments. M/s Black arrow submitted the MOI Submission, MOI approval is under progress, Expected TD for MOI Approval by 25-Jan-23 25-Apr-19 2 66/11 kV Montaza 2 S/S 13-Jul-17 AL SADD Received on 21.05.15 Received 14.05.18 Received on 29.01.19 File opened C/2021/0004510-F 30.11.2022 28-Feb-23 File was opened, MME Comments cleared, ASHGHAL Approved, QCDD Inspection is pending for Approval GTC/488G/2012 23-May-18 3 66/11 kV EDC-11& 66/11 kV New Rayyan 28-Dec-17 AL SADD Received 07.06.20 Received on 07.06.2022 Received on 29.7.20 31.01.2023 31-Apr-23 File was opened, MME Comments cleared, MME Inspection Completed, ASHGHAL & QCDD Approval are pending 26-Jun-18 4 66/11 kV Wadi Al Banat South 26-Jun-17 AL SADD Received on 10.12.20 Received on 02.02.2022 Received on 28.12.20 31.12.2022 31-Mar-23 File was opened, MME Comments cleared, ASHGHAL Completed, QCDD Approval is pending 22-Aug-17 5 66/11 kV Wadi Al Banat North 22-Aug-17 AL SADD Received 15.03.15 Received 07.11.18 Received on 27.11.18 File opened C/2021/0004511-F 31.10.2022 31-Mar-23 File was opened, MME Comments cleared, ASHGHAL Completed, QCDD Approval is pending 6 66/11 kV Al Markhiya 29-Mar-18 AL SADD Received 19.08.20 Received 15.07.21 Received 15.11.20 File opened C/2021/0004512-F 30.11.2022 28-Feb-23 File was opened, MME Comments cleared, ASHGHAL Completed, QCDD Approval is pending 7 66/11 kV Al Kheesa East 27-Apr-17 AL SADD Received 19.01.15 Received 07.11.18 Received 10.12.18 File opened C-2021-0004513-F 31.12.2022 28-Mar-23 File was opened, MME Comments cleared, ASHGHAL& QCDD Approval are pending 3-Aug-17 8 66/11 kV Khaldiyah 21-Dec-16 AL SADD 31.03.2023 31.03.2023 Urban Planning has to send the letter to Survey Department to fix the Boundary Points, upon completion they will send the close out letter to KM (TA), 9 66/11 kV Police Training Inst. 15-Jun-16 AL SADD 31.03.2023 31.03.2023 DC2 Approval under progress, Manual submission of DC2 (AVMV, FA & FF) drawing submission under progress, LSP drawing approved 5-Jan-17 10 66 / 11kV PSS-4 Substation. 11-Mar-18 AL SADD Received 23.02.20 Received on 14.02.22 Received on 11.5.2020 31.12.2022 25-Apr-23 File was opened, MME Comments cleared, ASHGHAL& QCDD Approval are under progress 11 66 / 11kV BuFasilah 23-Nov-17 AL SADD As per the BP/BCC obtained document by the developer, Substation was included in the available Bp/BCC 66 / 11kV BuFasilah 23-Nov-17 AL SADD As per the BP/BCC obtained document by the developer, Substation was included in the available Building Permit/BCC 2-Apr-18 12 12 66 / 11kV PSS-6 S/S 30-Nov-17 AL SADD Received 26.04.20 Received on 23.5.2022 Received 12.5.2020 31.01.2023 30-Apr-23 File was opened, MME Comments, ASHGHAL& QCDD Approval are pending 11-Mar-18 13 66 / 11kV Al Mergab Street S/S 1-Aug-17 AL SADD Received 25.01.16 Received 07.11.18 Approved 29.09.18 25.01.2023 30-May-23 Awaiting Revised Property Document from Developer, PIN No was Changed