danieljacksoni2000
43 views
102 slides
Jun 04, 2024
Slide 1 of 102
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
About This Presentation
Inasemekana kwamba george Müller alisoma Biblia zaidi ya mara mia mbili, nyingi kati ya hizo akiwa amepiga magoti. Kabla ya kifo chake, aliulizwa na mwandishi wa habari nini bado angependa kufanya, yeye, kwa magoti yake, alijibu, "Kusoma zaidi Biblia kwa sababu najua kidogo sana juu ya uwezo w...
Inasemekana kwamba george Müller alisoma Biblia zaidi ya mara mia mbili, nyingi kati ya hizo akiwa amepiga magoti. Kabla ya kifo chake, aliulizwa na mwandishi wa habari nini bado angependa kufanya, yeye, kwa magoti yake, alijibu, "Kusoma zaidi Biblia kwa sababu najua kidogo sana juu ya uwezo wa Kristo." "
Huyu alikuwa ni Mkristo wa Kiinjilisti, mkurugenzi wa kituo cha watoto yatima cha Ashley Down huko Bristol, Uingereza, ambako alikuwa anatunza watoto yatima 10,024 katika maisha yake yote kutokana na ahadi ya Mungu inayopatikana katika Zaburi 68:5 “Mungu ni Baba wa yatima hao”
Alijulikana kama mtu aliyehusika kikamilifu katika elimu ya watoto aliowalea, hata alishutumiwa kwa kutoa elimu zaidi ya kawaida kwa nyakati hizo. Alianzisha shule 117 zilizotoa elimu ya Kikristo kwa watoto 120,000, wengi wao wakiwa yatima.
Alisema, “Ikiwa mimi, mtu maskini, naweza kujenga na kusimamia kituo cha watoto yatima bila kumwomba mtu yeyote pesa au msaada, kwa njia ya maombi na imani tu, hii, pamoja na baraka ya Bwana, inaweza kuwatia moyo watoto wa Mungu katika imani, kuwa pia ushuhuda wenye nguvu kwa makafiri juu yake uwepo wa Mungu."
Mwandishi mashuhuri Charles Dickens mwenyewe alitembelea makazi ya George Müller ili kujionea huduma zinazotolewa kwa watoto. Dickens alifurahishwa sana hivi kwamba aliandika nakala za magazeti kadhaa, pesa za tangazo haziwezi kununuliwa.
Hivyo, hata baada ya umri wa miaka 70, Müller alisafiri sana, akifikia nchi 42, akiongea hata na wenye mamlaka wa Ikulu ya Marekani, akishiriki na wengine uzoefu wake mzuri Kwa Mungu.
Siku ya mazishi ya Müller, viwanda vya Bristol vilifungwa. maelfu ya watu walikuja kutoa heshima zao za mwisho kwa mtu aliyebadilishwa na Mungu kutoka kuwa mwizi aliyewasaliti rafiki zake wa karibu, hadi mtu ambaye alijiweka chini ya Mungu na kukusanya kiasi cha dola milioni 180 kwa njia ya sala na imani katika Yesu Kristo.
Müller aliandika hivi kuhusu kuongoka kwake: “Nilipojisalimisha kabisa kwa Mungu, upendo wa pesa ulitoweka, upendo wa nyumba ulitoweka, upendo wa mali ulitoweka, Kupenda vitu vya kilimwengu kulitoweka. Mungu amekuwa kila kitu kwangu. Nilipata kila kitu ndani yake, hakuna kitu kingine nilichotaka nikakosa. Na nilikaa Naye, mtu mwenye furaha, mtu mwenye raha sana, akitafuta tu kutimiza mambo ya Mungu. "
Maisha mengi zaidi yamebadilishwa kwa sababu ya imani na ujasiri wa Müller. Hata ikiwa hayuko tena miongoni mwetu, kazi aliyoianzisha ingali ipo, na ujumbe wa Müller unatujulisha leo: "Mungu ni halisi, Yeye ni Mungu ambaye unaweza kumtumaini!"
Inatosha kumtegemea Mungu aliye hai, Müller alisema, na tusiwe na wasiwasi juu ya mambo ya duniani, kwani mwanzo wa wasiwasi ni mwisho wa imani; na mwanzo wa imani ni mwisho wa wasiwasi.*Uongo huu na namna hii ya upotoshaji unadhidi kuenea, kama mkristo hauta tia bidii kujifunza zaidi Neno la Mungu kupitia vyuo vya Biblia na taasisi mbalimbali za mafunzo ya Neno la Mungu mfano TAASISI YA EfaN, n.k utaishia kudanganyika na wewe utaanza kusamba
Size: 2.24 MB
Language: en
Added: Jun 04, 2024
Slides: 102 pages
Slide Content
Quantity Takeoff
Dr. Ahmed Elyamany
1
Outline
•Importance of Quantity Takeoff
•Preparation of Quantity Takeoff
•Measurement Units
•Measuring excavation, P.C footings, Beams,
Columns, slabs, and stairs.
•Solved Example
2
Quantity Takeoff
•Quantity takeoff is an activity performed by
General Contractors, Subcontractors, Cost
Consultants, and Quantity Surveyors as part
of the construction process.
•It involvescounting the number of items
associated with a particular construction
project
3
Quantity Takeoff
•Quantity Takeoff is performed by:
•General Contractors,
•Subcontractors,
•Cost Consultants,
•Quantity Surveyors
5
Quantity Takeoff
•Counting the number of items associated
with a particular construction project
•Determining the associated materials and
labor costs
•Preparing an estimate as part of the bidding
process.
•Applied to the pricing process.
6
Quantity take-off: Why?
•Owner perspective:
•Initial estimate of the project costs at the
different stages of the project.
•Preparing the BOQ as a requirement of the
contract documents.
•Estimating the work done for issuing the
contractor payments.
7
Quantity take-off: Why?
•Contractor perspective:
•Pricing different work items.
•Identifying the needed resources (Labor,
Equipment, etc.).
•Project schedule.
•Preparing invoices for work done.
•Subcontractors’ payments.
•Review and control of crews’ production rates.
8
Quantity Takeoff
•The quantity takeoff process is typicallydone
manually using a printout, a pen, and a
calculator.
9
Quantity Takeoff
•New Trend is Building Information Modeling
(BIM)
•Provide a solution thatgenerates a set of
takeoff elements(counts, measurements,
conditions that affect cost) enables
estimators to more quickly and more
accurately perform takeoff for bidding or
pricing.
10
Quantity Takeoff
•Important to specify the type of ;
•Imported materials
•Suppliers
•Equipment
•Labors
•Work in project
•Important to know project budget
•Important to know activities logic
11
Quantity Takeoff Criteria
•It must be as accurate as possible
•Should be based on all available engineering
and design data.
•Use of appropriate automation tools is highly
recommended.
•The Quantity Takeoff is an important part of
the cost estimate.
12
Quantity Takeoff Input Documents
•Input from the client (task description).
•Conditions (general, special, supplementary).
•Drawing and specifications.
•Addenda.
•Agreement form.
•Modifications.
13
Quantity Development Guidelines
•Coordinate the quantity takeoff process and plan with
the estimator.
•Include a list of materials in quantity takeoffs.
•Utilize a process that easily records the quantity
•Check scales and dimensions on each drawing sheet.
•Highlight drawing areas where quantities have been
determined to ensure all elements is captured but not
double counted.
14
Quantity Development Guidelines
•Consider items that have no material but still
require cost, e.g., job office overhead, task
setup, training and certifications.
•Add a certain amount of waste, loss, drop off,
or length related to the material purchases
for a bulk order.
•Coordinate with designers if the design
appears in error..
15
Takeoff Sheet & Bill Of Quantities
•Quantity Takeoff Sheet
•تايمك تاسياقم
•Estimated Quantities
•ةيريدقت لامعأ تاسياقم
•Actual Quantities •ةيلعف لامعأ تاسياقم
•Bill Of Quantities (BOQ)
•ةينيمثت تاسياقم
16
Bill Of Quantities
18
NotesPrice
QuantityUnitItemItem
TotalUnit
1
2
3
Bill of Quantities classification
•The Bill of Quantities is classified into the
following work groups:
•Civil works
•Sanitary works
•Electrical works
•Mechanical works
19
Bill of Quantities classification
•Civil works:
•Earth works:
•leveling,
•excavation,
•backfilling,
•transportation of excavated soil)
•Foundation works:
•plain concrete
•reinforced concrete
•piling foundations
20
Bill of Quantities classification
•Civil works:
•Skelton reinforce concrete:
•Columns,
•Beans,
•Slabs
•Stairs
•Brick works:
•Internal brick work
•External brick work
21
Bill of Quantities classification
•Civil works:
•Finishing:
•Water proofing
•Staircases
•Plastering
•Flooring
•Painting
•Metal works:
•Windows
•Doors
•Accessories
22
Bill of Quantities classification
•Sanitary works:
•Water feeding systems
•Internal and external plumbing works
•Finishes of plumbing works
•Electrical works:
•Electrical cables
•Wiring; Accessories
•Internal connections
•Mechanical works:
•Air conditioning systems
•Elevators
23
Work order
•Items in takeoff sheets are organized in the
same construction sequence.
•Order of items in the same chapter:
•Items estimated in (m3)
•Items estimated in (m2)
•Items estimated in (m)
•Items estimated in (unit)
•Items estimated in (ton)
•Items estimated in (L.S.)
24
Measuring Units
•The units of measurements for civil
engineering worksare mainly categorized for
their:
•Nature
•Shape
•Size and
•Payments to the contractor.
•There are a number of standard codes and
methods of measurement that are available.
25
Measuring Units
Cubic meter (m
3
)
•Used for items such as:
•Excavation
•Backfilling
•Concrete
•Brick walls (≥25 cm thick)
Square meter (m2)
•Used for items such as:
•Brick walls (<25 cm thick)
•Plastering
•Flooring
•Painting
26
Measuring Units
Linear meter (m)
•Used for items such as:
•Pipe lines
•Canals
•Stair steps
•Windows sills
Number (unit)
•Used for items such as:
•Electric outlets
•Doors and windows
•Sanitary fixtures
•Precast concrete
27
Measuring Units
Lump sum(L.S.)
•Item is subcontracted when the contractor
does not have enough experience to
construct it or there is an item which has a
small quantities of many work items such as:
•Manholes
•Lifts
•Some electrical and plumbing works
•Weight (Ton):
•Metallic works
•Reinforcement steel
28
Preparation of Quantity Takeoff
•Check the availability of drawings
•Check the axis and dimensions
•Check building levelsand link it to structural
drawings.
•Check doors and windows modelnumbers
•Check ground waterlevels
29
Preparation of Quantity Takeoff
•Check architecturalagainst structural
drawings
•Check foundation design and foundation
levels
•Check construction members dimensionand
reinforcement.
•Review the contract conditions and
specifications
30
Formulas
32
Triangles
Regular Polygons
Circle
Parabola
Ellipse
Formulas
33
Formulas
34
Formulas
35
Formulas
36
Formulas
37
Formulas
38
TakingoffItems
39
Earth works
Excavation
•Quantities are calculated based on the
dimensions of the foundation in plans from the
owner perspective.
•Contractors should consider the excess of
material excavated to all for safe operations.
•Prices differ based on the soil type, deep of
excavation, ground water level, site location,
shoring system, Equipment used, etc.
•Unit of measurement m3 (volume).
40
Earth works
Excavation: Example
•Calculate the volume of Excavation for each
of the following cases:
41
1.80
1.20
1.40
Earth works
Excavation: Example
42
1.80
0.75 1.20
1.40
0.75
1.0
1.0
Earth works
Excavation: Example
43
1.80
0.75 1.20
1.40
0.75
1.0
1.0
Earth works
Excavation: Example
44
1.80
1.20
20 m
10 m
Earth works
Excavation: Example
45
20 m
1.80
1.20
Earth works
Excavation: Example
46
Earth works
Excavation: Example
•The length of excavation = 5.4 ×2 + (4.4 –2) ×2 = 15.6 m
•Depth of excavation = 1.8 m
•Width of excavation = width of plain concrete footing = 1.0 m
•Volume = 15.6 ×1.8 ×1.0 = 18.8 m3
47
Earth works
Backfilling
•Unit of measurement is m3 (volume)
•Volume of backfilling = excavation –concrete –brick
48
Earth works
Backfilling: Example
•Consider the previous example, the volume
of backfilling could be calculated as follow:
•Volume of concrete = 15.6 ×1 ×0.4 = 6.24m3
•Volume of brick = 15.6 ×0.4 ×1.4 = 8.736m3
•Volume of backfilling = 18.8 –(6.24 + 8.736) =
3.824m3
49
Earth works
Site leveling
•Top soil cannot be used for backfilling as it
would, over time, cause damage to the
substructure.
•The usual default depth for topsoil is 15 cm
•Measured in m2 (area) if thickness < 30cm.
•Measured in m3 (volume) if thickness >
30cm.
50
Earth works
Site leveling: Example 1
•Figure below is a 5 m grid of a survey of levels
taken on a site.
•The site is required to be reduced to a level of
35.62 and in order to calculate the volume of
excavation required the average level of the
site must be determined.
51
Earth works
Site leveling: Example 1
•This can be easily done by weighting the
levels as follows starting at the top left-hand
corner of the site (35.90) and working from
left to right.
52
Earth works
Site leveling: Example 1
Level Total Level
35.90 35.90
35.86 ×2 71.72
35.89 ×2 71.78
35.92 ×2 71.84
35.90 ×2 71.80
35.89 35.89
35 86 ×2 71.72
35.84 ×4 143.36
35.88 ×4 143.52
35.90 ×4 143.60
35.90 ×4 143.60
35.86 ×2 71.72
35.84 35.84
35.85 ×2 71.70
35.87 ×2 71.74
35.90 ×2 71.80
35.88 ×2 71.76
35.78 35.78
Total 1435.07
53
Number of Points = 40
Average site level =
1435.07 / 40 = 35.87
Reduced level = 35.62
Average Excavation
depth= 35.87 -35.62 =
0.25
Earth works
Soil transportation
•Transported soil = Vol. of exc. –Vol. of
backfilling + additional soil at site
•Add swelling factor based on the soil type:
•5% sandy soil.
•15% clayey soil and
•25% for demolition material. (owner or
contractor)
54
Concrete works
Plain concrete (PC)
•Measured in m2(area) if thickness < 20 cm.
•Measured in m3(volume) if thickness ≥ 20
cm.
•Average thickness should be mentioned
when measurement is done by area.
55
Concrete works
Reinforced concrete (RC)
•All RC elements measured by volume (m3)
excepthollow block slabs and Domes,
cylindrical roofs and shells.
•Hollow blockslabs measured by area (m2).
•Domes, cylindrical roofs and shells measured
by area in the horizontal projection (m2).
56
Concrete works
Plain Concrete Footing
•Quantity of P.C footing = No. of footings for a
specific model * length * width * depth
•Total quantity of P.C footings = summation of
P.C footing models
57
PC Footing
RC Footing
Concrete works
Ground Beams
•Quantity of ground beam = No. of ground
beams for a specific model * length * width *
depth
•Total quantity of ground beams = summation
of ground beam models
58
PC Footing
RC Footing
Ground Beam
Concrete works
Columns
•Quantity of columns = No. of columns for a
specific model * length * width * height
•Total quantity of columns = summation of
columns models
59
PC Footing
RC Footing
Columns
Concrete works
Slabs
•Solid slabs:
•Quantity of slab = length * width * thickness
•Flat slab:
•Quantity of slab = length * width * thickness
•Beams:
•Quantity of beam = length * width * height
60
Concrete works
Stairs
•Quantity of stairs = (thickness + riser/2 )*
tread * width * No. of stairs
61
tread
riser
thickness
thickness
Solved Example
62
Example
(Unit price Contract)
63
15cm
7ɸ10/m
7ɸ12/m4.8m
5.6m
ك1
ك2
ك2
ك1
ع1
ع1 ع1
ع1
AA
Example
(Unit price Contract)
64
تﻼمسلا عاطق0.3m x 0.5m
ع دومعلا عاطق1 0.3m x 0.3m
ع دومعلا عافترا1 3.0m
ةحلسملا دعاوقلا1m x 1m x 0.4m
ةيداعلا دعاوقلا1.6m x 1.6m x 0.15m
ك تارمكلا عاطق1,ك2 0.3m x 0.5m
2ɸ16 يولع+4ɸ16 تاناكلا و لدع يلفس6ɸ8/m يناسرخلا ءاطغلا
2.5 مس
ةيعيبطلا ضرﻷا بوسنم
1.05 m
Section A-A
Example
(Unit price Contract)
•It is required to make an engineering
estimate to the quantities of the following
items:
•Excavation (as isolated footing)
•Plain Concrete Footings
•Reinforced Concrete Ground Beams
•Filling
•Columns concrete
•Slab and beams Concrete
•Slab and beams Reinforcement
65
Example
(Unit price Contract)
66
.15 m
.15 m5.6 m
5.3
1.6 m
0.8 m
3.7 m
1.6 m
1.6 m
1.05 m
4.8 m
Example
(Unit price Contract)
68
No.Item UnitNumberLengthWidthDepthTotal
2PC Concrete m2 41.61.6 10.24
1.6 m
1.6 m
0.15 m
Example
(Unit price Contract)
69
No.Item UnitNumberLengthWidthDepthTotal
3RC Concrete m3 4110.41.6
1.0 m
1.0 m
0.4 m
Example
(Unit price Contract)
70
No.Item UnitNumberLengthWidthDepthTotal
4Ground Beamsm3 25.30.30.51.59
24.50.30.51.35
0.15 m
5.6 m
5.3
0.3 m
تﻼمسلا
0.5 m
4.8 m
4.5 m
0.3 m
0.15 m
Example
(Unit price Contract)
72
No.Item UnitNumberLengthWidthDepthTotal
2PC Slab on Grade m215.04.2 21
5.6 m4.8 m
5.0 m
4.2 m
Example
(Unit price Contract)
73
No.Item UnitNumberLengthWidthDepthTotal
6Columns Concretem3 40.30.331.08
ةدمعﻻا
3.0 m
3.0 m
3.0 m
Example
(Unit price Contract)
74
No.Item UnitNumberLengthWidthDepthTotal
7Slab & Beamsm3 25.30.30.51.59
24.50.30.51.35
154.20.153.15
0.15 m
5.6 m
5.3
4.8 m
4.5 m
0.15 m
0.5 m
0.3 m
5.0 m
4.2 m
0.15 m
15
cm
Example
(Unit price Contract)
76
No.Item UnitQuantityUnit priceTotal priceNotes
1Excavation m3
13.0
2Filling m3
7.0
3PC Concrete footingm2
10.0
4RC Concrete footing
and Ground Beams
m3
5.0
5Columns Concretem3
1.0
6PCSlab-on-gradem2
21.0
7Slab & Beamsm3
6.0
Bill of Quantities
Example
(Lump Sum Contract)
•It is required to make a contractor estimate to the
quantities of the following items:
•Excavation (excavated as raft, soil swelling factor =1.2,
earth slop 1:1.5 and are increased by 1 m from all sides,
excavated soil is to be transported outside site)
•Plain Concrete Footings
•Reinforced Concrete Footings
•Ground Beams concrete
•Filling (shrinkage factor =0.85, new fill soil to be brought
from outside site)
•Columns concrete
•Slab and beams Concrete
•Slab and beams Reinforcement
77
Example
(Lump Sum Contract)
78
8.9
8.1
0.15 0.155.6 m
5.30.8
4.8
0.81.01.0
8.9
1
1.5
8.91.575
1.05
1.575
12.05
8.1
1
1.5
8.11.575
1.05
1.575
11.25
Example
(Lump Sum Contract)
79
8.9
1
1.5
8.91.575
1.05
1.575
12.05
8.1
1
1.5
8.11.575
1.05
1.575
11.25
Base 2 =12.05 x 11.25 = 135.5625
Base 1=8.9x8.1= 72.09
Excavation Vol. = 1.05 *(135.563+72.09)/2 = 109
Transported Soil Volume = 109 x 1.2 = 130.8 m3
#ItemUnitNumberLengthWidthDepthTotal
1Excavationm31 109
Example
(Lump Sum Contract)
80
No.Item UnitNumberLengthWidthDepthTotal
2PC Concrete foundationm3 41.61.60.151.536
1.6 m
1.6 m
0.15 m
Quantity of concrete needed = 1.536 x 1.05 = 1.6 m3
Example
(Lump Sum Contract)
81
No.Item UnitNumberLengthWidthDepthTotal
3RC Concrete m3 4110.41.6
1.0 m
1.0 m
0.4 m
Quantity of concrete needed = 1. 6 x 1.05 = 1.68 m3
Example
(Lump Sum Contract)
82
No.Item UnitNumberLengthWidthDepthTotal
4Ground Beamsm3 25.30.30.51.59
24.50.30.51.35
تﻼمسلا
0.5 m
0.3 m
Quantity of concrete needed = 2.94 x 1.05 = 3.1 m3
Example
(Lump Sum Contract)
84
No.Item UnitNumberLengthWidthDepthTotal
2PC Slab on Grade m315.04.20.153.15
Quantity of concrete needed = 3.15 x 1.05 = 3.3 m3
5.6 m4.8 m
5.0 m
4.2 m
Example
(Lump Sum Contract)
85
No.Item UnitNumberLengthWidthDepthTotal
6Columns Concretem3 40.30.331.08
ةدمعﻻا
3.0 m
3.0 m
3.0 m
Example
(Lump Sum Contract)
86
No.Item UnitNumberLengthWidthDepthTotal
7Slab & Beamsm3 25.30.30.51.59
24.50.30.51.35
154.20.153.15
0.15 m
5.6 m
5.3
4.8 m
4.5 m
0.15 m
0.5 m
0.3 m
5.0 m
4.2 m
0.15 m
15
cm
Example
(Lump Sum Contract)
88
ك تارمكلا عاطق1,ك2 0.3m x 0.5m
2ɸ16 يولع+4ɸ16 تاناكلا و لدع يلفس6ɸ8/m يناسرخلا ءاطغلا2.5 مس
7ɸ10/m
7ɸ12/m
2.5cm
30cm
25cm
2.5cm
50cm
Reinforcement Takeoff
4.8m
5.6m
Example
(Lump Sum Contract)
89
Unit
(kg)
No. of
bars
LengthTotal
length
Unit
Weight
Total
Weight
16 upper (beams) 44.819.21.6331.296
45.622.41.6336.512
16 lower (beams) 84.838.41.6362.592
85.644.81.6373.024
10 long (Slab) 345.6190.40.63119.952
12 short (Slab) 404.81920.92176.640
8 stirrup (beams) 601.55930.4138.130
511.5579.050.4132.411
TotalSteel 570.557
Reinforcement Takeoff
Taking off Finishing Items
90
Brick works
•Measured in m2(by area) if thickness <25 cm.
•Measured in m3(by volume) if thickness ≥25cm.
•Deduct allopenings with area >0.5 m2.
•Include openings with area <0.5 m2.
•Deduct halfthe area (volume) of arches.
•Deduct allConcrete elements.
•Separate item for each brick type
91
Finishing works
Plastering
•Internal Plaster:
•Engineering measurement by area (m2).
•All openings with area ≥ 1 m2 are deducted.
•Openings with area < 1 m2 are not deducted.
•Openings sides are not added.
•Inclined slabs are calculated based on their
horizontal projection.
92
Finishing works
Plastering
•External plaster:
•Engineering measurement by area (m2).
•Openings with areas ≥ 1 m2 are deducted.
•Openings with areas < 1 m2 are not deducted.
•Openings sides are not added.
•Cantilever slabs < 1 m projection not added.
•Add half the area of cantilever slabs ≥ 1 m.
93
Finishing works
Wall covering
•Engineering measurement by area (m2).
•Ceramic
•Granite
•Wood
•Brick
•Stone
•Wall trim measured in linear m
•Circular columns measured in linear m
94
Finishing works
Stair steps covering
•Engineering measurement by linear m.
•May be measured by unitof steps.
95
Finishing works
Flooring
•Engineering measurement by area (m2).
•Floor Trim ( ةرزو)
≥
20cm measured in (m
2
)
•Floor Trim ) ةرزو( < 20cm measured in (m)
•Types are:
•Tiles
•Ceramic
•Granite
•Wood
96
Finishing works
Painting
•Engineering measurement by area (m2).
•All openings are deducted.
•Openings sides are added.
•Wood painting measured by unit.
97
Finishing works
Water Proofing
•Engineering measurement by area (m2).
•Footings Isolation
•Column neck Isolation
•Ground beam Isolation
•Bathroom Isolation
•Roof slab Isolation
98
Finishing works
Example
99
4.8m
5.6m
W1
D1
AA
W2
D2
1.1 m
1.8 m
Finishing works
Example
100
0.00 m
Section A-A
0.25 m
3.5 m
0.15 m
3.00 m
Brick wall 0.25 m thick
-Top slab Beam 0.3m x 0.5m
-Column 0.3m x 0.3m
-External Brick wall = 25 cm thick
-Internal brick wall = 12.5 cm thick
-Top roof wall = 12.5 cm thick
-W1: Window 1.2x1.2, sill height = 1.2 m
-W2: Window 0.5x0.5, sill height = 2.0 m
-D1: Door 1.0x2.2 m
-D2: Door 0.8x2.2 m
-Slab-on-grade thick = 0.15m
-Room Internal plastering = 2 cm thick
-Bathroom Internal finishing is ceramic tiles
-External plastering = 2 cm thick
-Flooring is ceramic tile thick = 1 cm
-Mortarand Sand layersbelow ceramic = 2
and 7 cm thick respectively.
-Moisture isolation above Slab-on-grade.
-Moisture isolation above roof slab
-Mortar and Sand layers below roof tiles = 2
and 7 cm thick respectively.
-Roof tiles = 2 cm thick
1.05 m
0.15 m
Finishing works
Example
It is required to estimate the quantities of
the following work items:
•Internal brick work
•External brick work
•Plastering
•Isolation
•Ceramic wall
•Ceramic flooring
•Painting
•Doors and window
101