Project: ADIT Presented by: Planning Department AOP Review Railway Metro Tunnel Hydro Logistics Park
Index MOM Salient Features of the Project Project Milestones HSE Performance & Focus Area Quality Insight & Focus Area Pictorial Progress Plan Vs Achieved Critical issues Asking Rate Cycle Time Monitoring Client Billing Wastage RFI Status Overbreak Project Photos Profit & Loss Statement
Salient Features of the Project Project Name CONSTRUCTION OF TUNNEL WORK BETWEEN KM.153.0 TO 180.0(ADENIGARH - PURUNAKATAK) CONSISTING OF TUNNEL-T4, T5, T6 & T7 (APX.LENGTH OF 7.492KM.) & ALLIED WORKS OF KHURDA-BOLANGIR NEW RAIL LINE PROJECT IN EAST COAST RAILWAY. Employer East Coast Railway Project Value ₹ 587.59 Crores Date of LOA 28-Mar-23 Commencement Date 16-Jul-23 Tender Security Amount ₹ 2.0 Crores Period of Completion Appointed date +30 Months Bonus for Early Completion 0.03% of CV for each day (Limited to 5% of CV). Bonus is applicable on overall completion Defects Liability Period 02 years commencing from the date of Provisional Certificate or expiry of a period 18 months from the date of Completion Certificate, whichever is later. Source of Fund Government of India Project Length 7.492 Km (T-4: 4.185KM, T5: 0.317KM, T6: 0.315KM, T7: 1.975KM & Escape Tunnel 0.700 Km and approaches) Performance Security 3% of Contract Price (within 30 days of Issuance of LOA)
Salient Features of the Project Project Name CONSTRUCTION OF TUNNEL WORK BETWEEN KM.153.0 TO 180.0(ADENIGARH - PURUNAKATAK) CONSISTING OF TUNNEL-T4, T5, T6 & T7 (APX.LENGTH OF 7.492KM.) & ALLIED WORKS OF KHURDA-BOLANGIR NEW RAIL LINE PROJECT IN EAST COAST RAILWAY. Liquidated Damages 0.05% of CV for delay of each day specified in Schedule – I, until such Project Milestone is achieved. Shall not Exceed 10% of the CV. LD will be imposed for each milestone but will be refunded if the project is completed within the contractual time (including EOT) Mobilization Advance 10% of OCV if required in 2 installments with interest rate Bank Rate plus 4% per annum. Subjected to irrevocable and unconditional BG of 110% of such instalment. Recovery of Advance Shall be recovered between 50% to 90% billing of CV. Limited to 30% from Each IPC. Time for Access to Site Core Land- Within 15 (fifteen) days of the signing of the Agreement or within 30 (thirty) days of the date of receiving the Performance Security from the Contractor, whichever is later. Non-Core Land- Within another 30days of handing over of land mentioned in Part-A. Environmental Clearance Environmental Clearance is not required for this project.
Project Milestones Project Milestones Days from AD Fin. Progress (%) Expected Date Amt (Cr) Project Milestone - I After completion of 10% of the contract price (T4, T5, T6, T7) 180 10% 29-Feb-24 58.76 Project Milestone - II After completion of 35% of the contract price (T4, T5, T6, T7) 270 35% 205.65 Project Milestone - III After completion of 70% of the contract price (T5, T6) 365 70% 411.31 Project Milestone - III After completion of 70% of the contract price (T7) 450 70% Project Milestone - III After completion of 70% of the contract price (T4) 545 70% 411.31 Project Milestone - IV Construction should be completed in accordance with the agreement (T5, T6) 545 100% 587.59 Project Milestone - IV Construction should be completed in accordance with the agreement (T7) 730 100% Project Milestone - IV Construction should be completed in accordance with the agreement (T4) 900 100% 587.59
Project Milestones (Revised)
HSE Performance- ADIT(To Be update) Target FTM Apr. 24 % Mar. 24 % Leading Indicators Cumulative Benchmarks 4,098 1,738 42% 30% TBT- Hrs. 5529 Total Manpower*6= TBT man hours 683 398 58% 62% Trainings- Hrs. 1455 Nos. of Avg. Manpower= Target Training hours 78 86 110% 96% Inspection-Nos. 629 Nos. of HSE Staff * Nos. of workdays 156 120 77% 59% Observation-Nos. 916 SE Staff * Working days * 2 NA 294 NA NA Permit- Nos. 1784 As actual- 100% NA NA NA Near Miss- Nos. 6 100 % Near Miss Should record & report NA 102 NA 60 Induction- Nos. 679 100 % Induction should be done for all newcomers. 1 1 100% 100% Mock Drill- Nos. 5 01 mock drill/ Month FTM Up to Previous month Lagging Indicators Cumulative 03 25 First Aid Cases- Nos. 28 Medical Treatment Cases Road Traffic Accidents Fatalities Loss Time Injuries FAC Details While shotcrete work at T4P1, the pipeline of the shotcrete machine got choked and during cleaning the operator applied reverse stroke due to which few aggregate flew and hit Raju, he received minor cut injuries on his face. While Mr. Maheshwar Reddy (Mechanical Helper) was getting down from the shotcrete machine, he slipped, and he fell 1.5 meters and got minor injury in his leg. When Mr. Nima Biswas was shifting the steel plate, finger of his right hand got stuck between the ground and the plate, due to which got a minor cut injury. Leading Indicators Lagging Indicators
Focus Area- ADIT(To be update) Mass TBT with PM & HODs and reward distribution. 01 million safe manhour certificate from client . Cut & cover area barrication & rope light installed . Mock Drills- Material fall Daily Gas, Lux level & Air Velocity monitoring at Site Blood donation camp. .
Pictorial as on 03-July-2024
FTM Plan Vs Achieved Item Description PCC Done Waterproofing Not Done Invert Lining In Progress Inner Gantry Shutter Erection start completed Outer Gantry Shutter Erection start Completed Overt Concrete (48 M) completed Lining concrete Start Started 29.05.2024 C&C Lining Plan
Critical Issues
Project Completion Asking rate : Excavation
Cycle Time Monitoring ** The planned cycle is effective cycle time as per average pull in each tunnel
Cycle Time Monitoring(Overt Cycle Time T4 Cut & Cover)
Cycle Time Monitoring(Overt Cycle Time T5)
Wastage Report ( T4)(To be update)
Financial Progress : Client Billing Status IPC No Month Submitted Certified Withheld Remarks if any SPS 01 Up to 31-Oct-23 8.87 8.87 - SPS 02 Up to 10-Jan-2024 18.90 18.90 - SPS 03 Up to 10-Feb-2024 19.17 18.29 - SPS04 Up to 22-March-2024 22.17 22.17 SPS05 Up to 30-April-2024 25.9 25.79 SPS06 Up to 05 th June-2024 17.24 16.95 SPS07 Up to 30 th June-2024 13.47 TOTAL 125.75 110.97 - Financial Progress for the month of July’24 (DPR till 03.07.2024 ):- 1.64 Crs . (Incl. GST)
RFI STATUS FOR CLIENT BILL
Overbreak Report Status of Percentage Over Break Till March-24 Sr. No. Location Rock Class Avg. Overbreak Location wise Remarks II III IV V 1 T4-P1 13% 7% 10% 2 T4-P2 11% 5% 8% 3 T5-P1 6% 6% 4 T5-P2 8% 8% 5 T6-P1 11% 7% 6% 8% 6 T7-P1 8% 7% 12% 9% 7 T7-P4 4% 5% 8% 6% Avg. Overbreak Class Wise 6% 9% 9% 6% 8%
Progress Photographs- T4 Cut & Cover SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 Overt Gantry Lining Concrete Ch 156231.5 to 156+279.5m Completed
Progress Photographs- T4 P1 SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2
Progress Photographs- T4 P1(Escape Tunnel) SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2
Progress Photographs- T4 P2 SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1
Progress Photographs- T4 Escape Tunnel Open Excavation SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1
Progress Photographs- T5 P2 Kerb Concreting &Overt Lining in Progress SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 T5 Kerb Concrete, Geotextile fixing, PVC Water Proofing Membrane & Overt lining in Progress-180 Rm Completed
Progress Photographs- T6 Overt Lining & C&C Progress photographs SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2
Progress Photographs- T7 P1 SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2
Progress Photographs- T7 P4(Presently moving in low cover Zone) SPF Fob main trestle bracing welding work Girder alignment and level checking work SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2 SPF Fob girder top roof truss welding work completed for Span 1 SPF Fob girder top roof truss welding work completed for Span 2