Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunnel In India
hitkhanna
10,350 views
99 slides
Oct 04, 2013
Slide 1 of 99
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
About This Presentation
The Presentation Covers the General Technical Features of Tunnel T 80 across Pir Panjal Mountain Range, for Kashmir Rail Link. This presentation was made at Civil Engineering Society, IIT Kanpur on 30th September 2013.
Size: 5.15 MB
Language: en
Added: Oct 04, 2013
Slides: 99 pages
Slide Content
WELCOME YOU TO
PIRPANJAL RAILWAY TUNNEL
SITE
THE LONGEST TRANSPORTATION TUNNEL
IN INDIA
2
•Location Overview
•Salient Features of The Tunnel
•Construction Approach
•Pre-construction Planning
•Usage Of NATM in T-80
•Construction Activities
•Quality Assurance
•Environment Issues
•Social Impact
PRESENTATION COVERS
LOCATION OVERVIEW
4
ALIGNMENT PLAN
JAMMU-UDHAMPUR-SRINAGAR-BARAMULLA RAIL
LINK
QAZIGUN
D
SADUR
A
ANANTNAG
BIJBEHARA
PUNZGA
M
AWANTIPORA
KAKPORA
PAMPOR
E
SRINAGA
R
BUDGA
M
RAJWANSHE
R
PATTAN
HAMRE
SOPORE
BARAMULLA
BANIHA
LARPINCHALA
BHATTA
LOALE
KOHLISANGALDAN
BARALA
BASAND
A--DHAR
REASI
KATRA
CHAKARWAH
UDHAMPUR
SALAL
RAMNAGAR
ROAD
MANWA
L
SANGAR
BAJALT
A
JAMM
U
SURUKOT
PIR PANJAL RAIL TUNNEL
Length 11100 mts.
South portal photo
SOUTH PORTAL
11
Vertcal Shaft
55m deep,
12m dia
Cross Passage 55 m
Adit 788 m
APPROACH TO CONSTRUCTION
WITH SHAFT AND ADIT
12Time Line
PIR PANJAL TUNNEL-
EXCAVATION PROGRESS
Year Excavation
(mts.)
Remarks
2006 722Two Faces
2007 1876Start From 4 Faces
2008 2475
2009 2533
2010 1739Two Faces after Jan’10
2011 947High overburden,
Squeezing, Shale
2012 63 13
Tunnel
Cross
Section:
14
STRUCTURAL GAUGE
15
TUNNELS
SECTIONS
USED ON
KONKAN
TRACK
16
TYPICAL
RAILWAY
TUNNEL
SECTION
USED ON
JAMMU-
UDHAMPUR
RAIL LINKSHOTCRETE(25mm+WIRE MESH +50mm)
OR 50mm SFRS
300 TH. C.C. LINING
ISHB 150 @ 500 C/C
50mm TH. R.C.C. LAGGING
Min. EXCAVATION LINE
75Ø @ 2000 C/C
MS PLATE 12mm THICK
ISHB150-2NOS.
INVERT STRUT ISHB150 @ 500mm
ISHB200 @ 750 C/C
1676
R 2600
4370
1312
150
150
Max.
150(max)
50M20
1 in 40
RAIL LEVEL
FINISH LINE
PAY LINE 150 TH. FROM Min. EXCAVATION
25 mm Ø 3 to 5m ROCK BOLTS
AS PER SITE REQUIREMENT
ISHB 150 @ 750 c/c
PRESSURE RELIEF HOLES 5m DEEP @
3m c/c LONGITUDINALLY AS PER SITE
REQUIREMENT
150
PAY LINE
MIN. EXCAV. LINE
BASE PLATE
12mm THICK
R3000
ISHB 150 @ 500 c/c SHOTCRETE25mm + WIREMESH+50mm OR 50mm SFRS 50 TH. R.C.C. LAGGING
150
PRESSURE RELIEF HOLES 5m DEEP @ 3m c/c LONGITUDINALLY AR AS PER SITE REQUIREMENT
BACK FILLING M-10
50
FINISH LINE 300 TH. CONC. LINING M-20
150
100
900
BLOWER
8Ø @ 150 C/C
50675 150
100
65
675
25mmØ 3mto5m ROCK BOLT AS PER SITE REQUIREMENT
SEC. AT A-A
75
18
LOADING DIAGRAM FOR TUNNEL
TOP PRESSURE-15000KG/M
AND SIDE PRESSURE-5000KG/M
19
BENDING MOMENTS DIAGRAM FOR
D-SHAPE TUNNEL
TOP PRESSURE-15000KG/M AND SIDE PRESSURE -5000KG/M
MAX BENDING MOMENT = 137KN-M
20
BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNEL
TOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M
MAX. BENDING MOMENT = 35.80KN -M
COMPARISION BETWEEN D -SHAPED AND ELLIPTICAL TUNNEL
DESCRIPTION MAX.
AXIAL
FORCE
MAX.
BENDING
MOMENT
MAX.
SHEAR
FORCE
MAX.
DISPLACEMENT
WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE
5000 KG/M
D-SHAPED
TUNNEL
412.5KN 137KN-M 15129 KG 0.083 M
ELLIPTICAL
TUNNEL
567 KN 35.80KN-M 9025 KG 0.024 M
WITH TOP PRESSURE 15000 KG/M
D-SHAPED
TUNNEL
412.5KN 48.10 KN-M 8565 KG 0.03 M
ELLIPTICAL
TUNNEL
639 KN 35.65 KN-M 9635 KG 0.028 M
CONSTRUCTION METHOD
SELECTION
•DRILL AND BLAST
•ROAD HEADER
•TUNNEL BORING MACHINE (TBM)
22
DRILL AND BLAST
23
•CONVENTIONAL, ART
WHICH COMES WITH
EXPERIENCE
•GOOD IN HARD ROCKY
STRATA
•WITH EXPERIENCE, CAN
DELIVER GOOD PROGRESS
•NON CONTINUOUS -CYCLE
INVOLVES VARIOUS
ACTIVITIES IN SEQUENCE
•MAY SPRING SUDDEN
SURPRISES
ROAD HEADER
•CONTINUOUS ADVANCE -
LESS SURPRISES
•MORE CONTROLLED
EXCAVATION-LESS
OVERBREAK/CAVITY
FORMATION
•SUITABLE FOR MEDIUM
HARD ROCK
•CAN BE WITHDRAWN
MID WAY TO GIVE WAY
FOR OTHER METHODS
24
TUNNEL BORING MACHINE
•CONTINUOUS ADVANCE
•CIRCULAR SECTION
•NOT SUITABLE UNDER
SQUEEZING
CONDITIONS
•CANNOT BE
WITHDRAWN MIDWAY
TO GIVE WAY TO
OTHER METHODS
25
WHY NO TBM
•Likelihood of Mixed Geology
•Heavily Faulted Areas and/or Wide Fault
Zones
•High Squeezing Anticipated in middle with
High Overburden (1100 mts.)
•Heavy Water Flow in Lime Stone Zone
with High overburden
•TBM may be Trapped by Ground
Movement Behind the Face
26
PRE-CONSTRUCTION
PLANNING
PRE-CONSTRUCTION PLANNING
•Engagement of Consultant
–QCB System Of tendering
•Survey and Investigation
•Head start by Taking up ADIT and shaft
works in advance
•Tender Planning
–Key dates
–Multi Method Approach
•Road Header/ D&B
28
USAGE OF NATMIN T-80
•Suitable for poor and Varying Geology of
Himalayan Region
•X-Sectiondesigned to develop Maximum Self
Supporting Capacity
•Face Mapping, Probe Hole & Instrumentation data
input for Initial Support Design –RESS
–Primary Support System
•Resilient enough to Accept the deformations and readjustment of
stresses and Strong enough to take the loads
•Deformation Monitoring to assess the stress
redistribution, and stabilization before final lining
29
INSTRUMENTATION
To provide early information about tunnel behaviour in order to optimize
excavation & support activities during construction and to recognize the requisite
remedial measures.
Instrumentation data is basic input of the NATM, the observational approach.
Instrumentation in Pir Panjal Tunnel:
Optical 3 D monitoring: With bi-reflex targets to monitor deformation in
tunnel on daily basis
Extensometers: To measure stresses in surrounding rock mass
Radial Pressure Cells: To measure pressure of rockmass on shotcrete
lining
Shotcrete Strain meter: To monitor stresses in shotcrete lining
Piezometer: To monitor hydrostatic pressure during tunneling
30
CONSTRUCTION ACTIVITES
•Open excavation & portal development
•Tunnel mining & primary lining
•Water-proof membrane installation +
drainage system.
•Secondary lining.
•Ventilation, system and safety installations
•Track laying
31
QUALITY ASSURANCE
•Laid down responsibilities,
procedures and checklists for various
activities through:
–CPM, CQM, SH&EM
–PPM, PSM
–Organogram
–QAP
–ITP
32
QUALITY ASSURANCE (contd…)
•Availability of relevant documentation and defining the
manner of execution of various activities
•Maintaining compliance through appropriate monitoring
•Ensuring adequate support facilities for successful &
scheduled execution of work.
•Availability of competent/trained personnel to carry out
various activities
•Compliance of statutory/regulatory requirements related
to safety, environment etc.
33
Quality Assurance (contd…)
Check Lists and Forms for Process Control During
Execution of Works:
•Required Excavation and Support Sheet (RESS)
•ATSS/ Shift Report/Blasting clearance report/ R/Bolt
Installation report
•Shotcrete testing by Penetrometer test, Core crushing
test, thickness verification etc.
•Geological mapping (Geological face mapping sheet)
•Lining Air Permeability Test
•All Material Testing at Site Lab
34
ENVIRONMENT ISSUES
•Identified Muck Dumping areas
•Recycling of Excavated Rocks
–aggregate for concrete constn.
•Effluent Settling Tank
–Fit for agriculture discharge
•Ventilation during Construction Stage
–Gas Analyser for air quality monitoring
•Controlled Blasting below Inhabited areas
•Lined Waterproof Tunnel
–No long term impact on water table/ Aquifers
35
SOCIAL IMPACT
•All weather link, Alternate to Jawahar
Tunnel
•Even at Construction stage, given a boost to
–local construction-industry
–Employment
–Transportation business
•A boost to Local economy of Banihal
36
40
Miles to go……
“A thing should be made
as simple as possible,
but not simpler”.
Einstein
41
THANKS !
ENGAGEMENT OF CONSULTANT
•Investigations for Tunneling Methodology
Assessment
•Initial Design
–Usage of NATM
–Usage of Water proof Membrane for Semi Dry
Tunnel
–Development of 4-Arc Tunnel X-Section
–Additional Access through ADIT and Shaft
–Portal Location Review
•Real Time Monitoring / Instrumentation and
Design Support
42
INVESTIGATIONS & PLANNING
2003 Geological L-Section Profile Submitted by M/s
RITES based on GSI data.-
Used to decide the Bore hole Location.
2003-04Bore holes by RITES/ MECL-
To Confirm Geological Mapping inference
2004 Consultants engaged in Feb. 2004
Geological Surface Mapping along the entire alignment by -
For Detailed Geological Section
2004
Data input for Tendering and a Decision Support System for
ADIT and Shaft decision
–Adit & Shaft Work Awarded in June 2004
2004 Detailed Topographical Survey for Portal
Location
2005 Main Tunnel Construction Work Awarded in
August 2005 43
44
45
BASIC PRINCIPLES OF NATM
•Rock Mass is the major load bearing member
•Primary Support shall
maintain the integrity & strength of Rock Mass
light, have good and area contact (shotcrete)
strengthen Rock Mass (bolt, grouting)
provide protection to workers (steel rib, mesh)
installed quickly
•Provide always an effective ring closure, if
necessary by an invert if rock is not suitable
BASIC PRINCIPLES OF NATM (Contd.)
•Rounded shape of Cross-Section
•Continuous control of system behaviourby
monitoring
•Inner lining shall be installed only after
balance of stresses (“zero“ deformation)
48
49
50
3D Monitoring Targets
51
52
53
EXTENSOMETER
54
FACE MAPPING
55
PROBING SHEET
56
57
58
59
Deformation
Monitoring in Primary
Lining Before start of
Secondary Lining
60
61
62Charging of Face
63
Ventilation Duct
64
Mucking
65
Wire mesh & Lattice Girder Erection
66
Face sealing
Face sealing by Shotcrete
67
Drilling for Forepoling
68Rock Bolting
TUNNEL MINING
Activity
Cycle Time (hr.) 2 mt.
RC IV
Cycle time (hr.) 1.25
mt. RC V
Drilling & Excavation 1.7 0.9
Charging , Blasting
& Defuming
2.7 1.5
Mucking 1.1 0.8
Wire Mesh & Lattice
Girder
2.4 2.3
Shotcrete 0.9 0.8
Rock Bolting 1.8 1.0
Preparation of new
face
0.3 0.3
Maintenance 1.6 1.1
Forepoling 1.6 1.7
Total 14.1 10.4 69