1 Mott MacDonald | Presentation Tarbela 5 th Extension Hydropower Project 14 June 2024 Transmission Line Contract
TL – Site Progress Mott MacDonald | Presentation 2 Description Section-01 Section-02 Remarks Line Length: 43.14 / 49.01 km completed. (Total Line Length is subject to change due to possible diversions) 3.04 km Section 1: Plan & Profile from t# 1 to 94 & 115 to 160 (43.14 km) has been approved. Line Route Survey from T# 94 to 115 is pending due to ROW issue of Paradise Housing Society). Section 2: 100% Plan & Profile approved. Total Towers 164 (Quantity of towers is subject to change due to diversions involved.) 10 Soil Investigation 93 / 164 10 / 10 Section 1: Due to ROW issue, no activity for last one & half month.
Mott MacDonald | Presentation 3 Description Section-01 Section-02 Remarks Tower released for erection 58 / 164 (DS1=40, DA1=10, DD1=08) 10/10 (SGM=2, AGM=1, DGM=5, DD1=1) Section 1: Foundation design for further 35 Towers has been submitted by NTT and same is under review by T5C. Foundation Work Concrete 13 / 164 completed (DS1= 08, DA1= 1.0 DD1= 4) 05 / 10 completed Section 1: Concrete of 14 Tower is in progress. Backfilling 01 / 164 completed 04 / 10 completed Section 1: T5C advised NTT to mobilize a separate crew for ‘Backfilling’. Erection Work Yet to be started. Yet to be started. TL – Site Progress
Mott MacDonald | Presentation 4 TL – Site Progress (Section-1) T80 – Foundation Concreting T67 – Stub and steel fixing
Mott MacDonald | Presentation 6 TL – Site Progress (Section-2) T1A – Backfilling inspection T2A – Foundation concrete
Mott MacDonald | Presentation 7 TL – Site Progress (Section-2) T3A – Foundation concrete T3A – Field density test
TL – Major Equipment Manufacturing and FAT Status Mott MacDonald | Presentation 8 Sr. No. Component Manufacturing Status Actual / Planned FAT Date Actual / Planned Delivery Date Section- I 1 Conductor Lot 1 Completed 29-Aug-23 21-Oct-23 2 Conductor Lot 2 Completed 26-Oct-23 19-Jan-24 3 Grounding material Completed 11-Nov-23 31-Jan-24 4 Stubs (122 Towers) Completed 14-Nov-23 18-Jan-24 5 Towers Lot 1 (122 Towers) Completed 14-Nov-23 29-Feb-24 6 Conductor Lot 3 Completed 29-Feb-24 29-Mar-24 7 OPGW In progress 17-Mar-24 06-May-24 8 Insulator In progress 23-May-24 12-Jul-24 9 Hardware and accessories In progress 01-Dec-24 20-Jan-25 10 Stubs (remaining) In progress 11 Towers Lot 2 (remaining) In progress Sr. No. Component Manufacturing Status Actual / Planned FAT Date Actual / Planned Delivery Date Section- II 1 Grounding material Completed 11-Nov-23 31-Jan-24 2 Stubs Completed 14-Nov-23 18-Jan-24 3 Towers Completed 14-Nov-23 (9/10) completed 08-Feb-24* (9/10 completed) 4 Conductor In progress 5 Hardware accessories In progress 6 OPGW In progress 7 Insulator In progress Section-1 Section-2 * Last Tower will be delivered along with Tower Lot 1 od Section-1.