Ministry of Water Supply
National Water Supply & Drainage Board
Ambatale Water Supply System Improvement
& Energy Saving Project (AWSSIESP)
Eng. V.G.U. Ranjith
Project Director
Project Management Unit
AWSSIESP
Presented By :
Progress Review Meeting
Construction of Gothatuwa 15,000 m3 Reservoir and
Booster Pump Station with supply and laying of 5 Km,
1200 mm DI Pipes (GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
ICB 031
Supply and laying of 9km DI pipes (1200 mm Dia.) and
Accessories from Ambatale to Ellie House Reservoir
(GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
ICB 042
Reliability Enhancement and Energy saving of Ambatale
Production Facilities Electrical , Mechanical,
Instrumentation & Civil Works
(GCWWMIIP/AFD/AMB/PLANT/ICB 05)
ICB 053
Supply of Equipment & Machineries to Western
Production, NWS&DB (07 Lots of Supply)
(GCWWMIIP/AFD/AMB/EQUIP/ICB 06)
ICB 064
Contract Packages
Design Review & Construction Supervision Consultancy
Services (GCWWMIIP/AFD/CONSULT/DRCSC/QCBS/02)
DRCSC5
Ambatale Water Supply System
Improvement & Energy Saving
Project (AWSSIESP)
ScopeoftheProject:
Enhancethereliabilityofproduction,introducing
energysavingmeasures&improvingtheefficiency
oftheconveyancefacilitiesatAmbatale.
Source of Funding : AFD/ADB & GOSL
Project Cost : USD 100 Mn
Foreign : USD 70 Mn
(AFD)
GOSL : USD 30 Mn
Project Duration : June, 2016 –
June, 2019
Revised Project Duration: June, 2016 –June 2023
Beneficiaries : Western Production
Project Map
Supply and laying of 9km DI pipes (1200 Mm Dia.) and
Accessories from Ambatale to
Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Construction of Gothatuwa 15,000 m
3
Reservoir and
Booster Pump Station with supply
and laying of 5 Km, 1200 mm DI Pipes
(GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
Reliability Enhancement and
Energy saving of Ambatale
Production Facilities –
Electrical , Mechanical,
Instrumentation & Civil Works
(GCWWMIIP/AFD/AMB/PLANT/ICB 05)
Moragasmulla
booster Pump
House
Construction of Gothatuwa 15,000 m3 Reservoir and Booster Pump Station with
supply and laying of 5 Km, 1200 mm DI Pipes (GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
ICB 031
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from Ambatale to
Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
ICB 042
Reliability Enhancement and Energy saving of Ambatale Production Facilities Electrical ,
Mechanical, Instrumentation & Civil Works (GCWWMIIP/AFD/AMB/PLANT/ICB 05)
ICB 053
Supply of Equipment & Machineries to Western Production, NWS&DB (07 Lots of Supply)
(GCWWMIIP/AFD/AMB/EQUIP/ICB 06)
ICB 064
Contract Packages
Design Review & Construction Supervision Consultancy Services
(GCWWMIIP/AFD/CONSULT/DRCSC/QCBS/02)
DRCSC5
Progre
ss
Issue
s
Contract
Informatio
n
Construction of Gothatuwa 15,000 m
3
Reservoir and
Booster Pump Station with supply and laying of 5 km,
1200 mm DI Pipes (GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
Construction of Gothatuwa 15,000 m3 Reservoir and Booster Pump
Station with supply and laying of 5 km, 1200 mm DI Pipes
(GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
•Scope:
Supply and laying of 5 km, 1200 mm DI Pipes
Construction of Gothatuwa 15,000 m
3
Reservoir
Booster Pump Station at Moragasmulla
•Contractor : M/s. CMEC –BPPE JV
•Contract Sum : LKR 2,667,603,503.11
•Contract Duration : 20 Months
•Commencement Date : 07.10.2020
•Scheduled Date of Completion : 20.09.2022 (With EOT)
Contract Details
Construction of Gothatuwa 15,000 m3 Reservoir and Booster Pump
Station with supply and laying of 5 km, 1200 mm DI Pipes
(GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
Progress
Contract
packages
Physical Progress as
at 15.03.2022
Financial Progress as
at 15.03.2022
Target ActualTarget Actual
ICB 0363.63%42.64%50.22%45.09%
No. Milestones Weightage
Cumulative Physical
Progress as at
15.03.2022
TargetActual
1Preliminary Works 3.00% 100.00%100.00%
2Site Mobilization 4.00% 100.00%99.25%
3Local material approval 2.00% 100.00%99.00%
4Preconstruction Works 5.00% 100.00%98.00%
5Procurement 15.00% 94.00%86.27%
6Diversion of existing lines (additional scope)1.00% 100.00%100.00%
7Construction of Ground Reservoir at Ambatale12.00% 66.17%43.33%
8Construction of High Lift Pump house at Ambatale7.00% 35.00%26.43%
9
Construction of Booster pump house at
Moragasmulla
8.00% 83.00%45.00%
10
Construction of Transmission main from Gothatuwa
to Maligakanda
42.00% 41.67%10.00%
11End of the Project 1.00% 0.00% 0.00%
Total 100.00%63.63%42.64%
Photographs
Construction of Gothatuwa 15,000 m3 Reservoir and Booster Pump
Station with supply and laying of 5 km, 1200 mm DI Pipes
(GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
Construction of Proposed Ambatale reservoir
500 mm DI pipe laying at
Moragasmulla
Road Reinstatement of 500 mm DI pipe laying
1200 mm DI pipe laying at Dodangahahena Road
Photographs
Construction of Gothatuwa 15,000 m3 Reservoir and Booster Pump
Station with supply and laying of 5 km, 1200 mm DI Pipes
(GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
Diversion of Transmission
Pipeline under ICB 03
Underground Utility investigation
(ICB 03 pipe laying)
Construction of Moragasmulla Booster
Pump station (ICB 03)
Pipe bridge Constructions across Kolonnawa canal Boundary Retaining wall at Moragasmulla pump house access road
Photographs
Construction of Gothatuwa 15,000 m3 Reservoir and Booster Pump
Station with supply and laying of 5 km, 1200 mm DI Pipes
(GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
Imported material at Pipe Yard –
Welivita.
Construction of Gothatuwa 15,000 m
3
Reservoir and Booster Pump
Station with supply and laying of 5 km, 1200 DI Pipes
(GCWWMIIP/AFD/AMB/CIVIL/ICB 03)
Issues
Contractor’s progress is behind the schedule.
Contractor is not following the works according to the work programmes(Daily/ weekly). Therefore,
more attention shall be paid to the followings,
•Contractor shall start more pipe laying sections
•Excavation works of Ground Reservoir is not finished
•Construction of Moragasmullapump house
Lack of Labourforce & the required resources
•Pipe laying teams
•Formwork teams of the ground reservoir
Bridge crossing Construction works are not in progress since Mid of Feb 2022.
Progress IssuesContract
Information
Supply and laying of 9km DI pipes (1200 mm Dia.) and
Accessories from Ambatale to Ellie House Reservoir
(GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
•Scope : Supply and laying of 9 Km, 1200 mm DI Pipes
•Contract Sum : LKR 2,565,286,703.70
•Contractor : M/s. JITF –KDESH JV
•Date of Commencement : 01.07.2016
•Date of Recommencement : 25.11.2019
•Date of Completion : 17.05.2022 (with EOT)
Contract Details
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Progress
Contract
packages
Physical Progress as
at 15.03.2022
Financial Progress as
at 15.03.2022
Target ActualTarget Actual
ICB 04 92.11%89.81%75.02%68.04%
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
The total pipe laid length is 8423 m out of 9247 m.
Completed length of pressure testing = 6158 m
Total road length of handed over to RDA = 4720 m
No.Description Weightage
Physical Progress as
at
15.03.2022
TargetActual
1Preliminary Works 5.00% 99.80%99.80%
2Trial Pits/ Trial Trenches 3.00% 99.33%99.33%
3
Supply of DI Pipes Fittings & Specials (including
handling)
25.00%99.76%97.00%
4Pipe Laying 58.00%90.07%89.78%
5
Construction of Valve Chambers and Fixing of
Valves and related pipes and fittings
2.00% 96.50%78.50%
6Bridge & Pipe Support 2.00% 89.50%40.00%
7Pressure Testing 2.00% 75.50%78.50%
8Permanent Road Reinstatement 2.00% 86.50%79.00%
9Cleaning and Disinfection 1.00% 0.00% 0.00%
Overall 100.00%92.11%89.81%
1200 mm Dia. Pipe Laying.
Existing Pipe Crossing
Photographs
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Photographs
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Photographs
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Pipe Section Joining
Chamber casting
Fixing Sluice Valve in Washout
Photographs
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Line Valve installation
Pipe Bridge Crossing Construction across the
Sebastian Canal (Nagalagam Street)Air Valve installation
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Difficulties
during pipe
laying work
Low-Level Road Crossing
Photographs
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
1.Progress of the Construction of Pipe bridge at Kiththmpahuwa Canal (Kalupalama) at Ch. 7+875 is very
slow (long time is taken for casting one pile of the pipe bridge).
2.Approval for the changed pipe trace under RDA Bridge “Kalyani Piwisuma” is to be taken from RDA (@
CH. 8+800).
3.Contractor shall take necessary actions to complete pressure testing works of section 01 of the Pipeline
trace (Ch. 0+118 –Ch. 1+100)
4.The Contractor shall complete the balance works of pressure tested sections in order to hand them over
to RDA. (Ch.4+320 –Ch. 5+097 & Ch. 6+597 –Ch. 7+278)
5.Contractor shall attend often for the maintenance of Sedawatta road (temporary reinstated area).
6.Road full overlay is required by Contractor from Ch.4+320 to Ch. 4+470 & from Ch. 4+985 to Ch. 5+050.
7.Difficulty in the finding of repair materials for Cast Iron (CI) distribution mains (OD 262mm).
Issues
Supply and laying of 9km DI pipes (1200 mm Dia.) and Accessories from
Ambatale to Ellie House Reservoir (GCWWMIIP/AFD/AMB/CIVIL/ICB 04)
Progress IssuesContract
Information
Reliability Enhancement and Energy saving of Ambatale
Production Facilities Electrical , Mechanical,
Instrumentation & Civil Works
(GCWWMIIP/AFD/AMB/PLANT/ICB 05)
Reliability Enhancement and Energy saving of Ambatale Production
Facilities Electrical , Mechanical, Instrumentation & Civil Works
(GCWWMIIP/AFD/AMB/PLANT/ICB 05)
Contract Sum:
USD 28,654,139.28+ LKR 573,196,859.31
Contractor:
Ms. Zhongnan –SZSG –JH JV
Date of Commencement: 13.12.2018
Date of Completion : 26.01.2022 (with EOT)
Contract Details
Scope:
•Design, supply and installation of 17 Nos. pumps
•Design and construction of 8,000 m
3
ground reservoir.
•Design, Supply and Installation of process automation
system (SCADA System) with two storied control
building
•Design and Construction of 22,000 m
3
backwash
recovery system and sludge treatment system.
•Five story Staff Accommodation Building.
•Gantry Crane, Coarse Screen and Fine Screen for the
intake plant.
Progress
Contract
packages
Physical Progress
as at 15.03.2022
Financial Progress
as at 15.03.2022
Target ActualTarget Actual
ICB 05100.00%47.79%100.00%21.19%
Reliability Enhancement and Energy saving of Ambatale Production
Facilities Electrical , Mechanical, Instrumentation & Civil Works
(GCWWMIIP/AFD/AMB/PLANT/ICB 05)
No. Milestones Weightage
Cumulative Physical
Progress on 15.03.2022
Target Actual
M1Preliminaries and General 8.00% 100.00%89.25%
M2Design and Documentation 15.00% 100.00%80.93%
M3Supply of Plant & Spare Parts 35.00% 100.00%49.37%
M4Civil Works 20.00% 100.00%52.50%
M5Mechanical & Electrical Installations15.00% 100.00% 4.87%
M6Testing and Commissioning 7.00% 100.00% 0.00%
100.00%100.00%47.79%
Photographs
Construction of five storied staff quarters building at
Ambatale WTP
Construction of Proposed Ellie House Ground Reservoir (ICB 05)
Construction of proposed Control
building at Ambatale WTP
Laying of 1200mm dia. DI Pipes (Yard Piping) (ICB 05)
Pipe Connection of Churchill Pipe lines
Photographs
The delivered pumps & motors are stored at Warehouse
Construction of Soakage pit of Staff Accommodation
Mobilization of Backwash recovery and sludge treatment Plant
1.The performance of the Contractor has been improved up to some extent after assigning of new project
Manager. The Contractor shall provide more resources to speed up the progress.
2.Final proposal of Electrical Installation Sub Contractor is not submitted.
3. Reservoir Construction
Construction works are ongoing. The Contractor shall provide more resources to improve the
progress. The Contractor shall complete the concreting works of the sump area of the reservoir
before the rainy season is started.
4. Construction of five-storied staff accommodation building and two-storied Control Building
Contractor is still unable to complete and hand over the building to NWSDB. The new deadline of
building handover is the First week of April 2022.
Issues
Reliability Enhancement and Energy saving of Ambatale Production
Facilities Electrical , Mechanical, Instrumentation & Civil Works
(GCWWMIIP/AFD/AMB/PLANT/ICB 05)
Issues
Reliability Enhancement and Energy saving of Ambatale Production
Facilities Electrical , Mechanical, Instrumentation & Civil Works
(GCWWMIIP/AFD/AMB/PLANT/ICB 05)
5. Backwash recovery and Sludge treatment Plant (BR&STP)
Piling work of the structure to be started. The contractor shall speed up the constructions
works in order to complete the structures.
Contract has not opened LC for the approved machinery and equipment for BR&STP.
6. Modification in Intake Structure
Activities under intake structures are not yet completed. The progress of Intake
modification works is very slow.
7. Other issues
Progress of the Civil Sub Contractor is not satisfactory.
Lack of Supervisory staff.
No proper yard facilities and no adequate storage facility to store the materials.
Design of Medium voltage panel to be finalized.
Progress
Contract
Information
Supply of Equipment & Machineries to Western Production,
NWS&DB (07 Lots of Supply)
(GCWWMIIP/AFD/AMB/EQUIP/ICB 06)
Supply of Equipment & Machineries to Western Production, NWS&DB
(07 Lots of Supply) (GCWWMIIP/AFD/AMB/EQUIP/ICB 06)
Contract Sum:
Yen 2,085,930.00 + USD 29,250.00 + LKR 91,692,631.05
Nos. of supply lots: 07 Nos Lots
Date of Commencement: 19.10.2018
Date of Completion: 31.12.2019
Status: Completed
Contract Details
Scope: Supply of
•Crane Mounted Truck (10 Ton)
•Aerial Work Platform (200Kg)
•Engine Driven Forklift (5 Ton)
•Submersible Dewatering Pumps (6 inch)
•35 kVA Mobile Generator (Diesel)
•Crew Cab Vehicles (Short Wheel Base)
•Crew Cab Vehicles (Long Wheel Base)
•Tipper Truck (Dump Truck)
Progress
Contract packages
Physical Progress as 15.03.2022Financial Progress as at 15.03.2022
Target Actual Target Actual
ICB 06 100.0% 100.0% 100.0% 100.0%
Supply of Equipment & Machineries to Western Production, NWS&DB
(07 Lots of Supply) (GCWWMIIP/AFD/AMB/EQUIP/ICB 06)
Photographs
Supply of Equipment & Machineries to Western Production, NWS&DB
(07 Lots of Supply) (GCWWMIIP/AFD/AMB/EQUIP/ICB 06)
Progress IssuesContract
Information
Design Review & Construction Supervision Consultancy
Services (GCWWMIIP/AFD/CONSULT/DRCSC/QCBS/02)
Design Review & Construction Supervision Consultancy Services
(GCWWMIIP/AFD/CONSULT/DRCSC/QCBS/02)
Cost: USD 2,237,748.05 +LKR 165,049,400.00
Consultant: M/s. Safege -Ceywater -RDC JV
Date of Commencement : 01.06.2016
Original Date of Completion : 31.05.2019
Date of Completion (EOT 04) : 31.01.2023 (Additional funds : not required)
Contract Details
Scope:
•Assist PMU in Contract Management
•Contract supervision in ICB 03 & ICB 04 Contracts
•Construction supervision & Design Review in ICB 05 contract.
Progress
Contract packages
Physical Progress as at 15.03.2022 Financial Progress as at 15.03.2022
Target Actual Target Actual
DRCSC 100.00% 99.02% 100.00% 80.13%
Design Review & Construction Supervision Consultancy Services
(GCWWMIIP/AFD/CONSULT/DRCSC/QCBS/02)
EOT approval has been given up to 31 Jan 2023.
•Additional funds will be required for the further project extension which is planned to
utilize funds from Physical contingencies of AFD Credit Facility Agreement.
Issues
Design Review & Construction Supervision Consultancy Services
(GCWWMIIP/AFD/CONSULT/DRCSC/QCBS/02)
Overall Project Progress -AWSSIESP
Project
Physical Progress as at
28.02.2022
Financial Progress as at
28.02.2022
Target Actual Target Actual
AWSSIESP 88.48% 62.45% 81.16% 49.54%