MMS (Choice Based) SEM-IV / Subject : Project Management (Answer-Key) / QP Code: 67654 (May 2019)
Page 3 of 16
1 b)
i) Ranking of options based on Payback Period (2 Marks)
Cumulative returns for the 3 options are as shown in table below:
Year Option-1 Cumulative Option-2 Cumulative Option-3 Cumulative
0 (5,00,000) --- (5,00,000) --- (5,00,000) ---
1 2,50,000 2,50,000 50,000 50,000 50,000 50,000
2 2,50,000 5,00,000 50,000 1,00,000 2,50,000 3,00,000
3 50,000 5,50,000 2,50,000 3,50,000 2,00,000 5,00,000
4 50,000 6,00,000 1,50,000 5,00,000 3,50,000 8,50,000
5 50,000 6,50,000 5,00,000 10,00,000 50,000 9,00,000
From above table, ranking of options will be – 1) Option-1, 2) Option-3, 3) Option-2
i) Ranking of options based on NPV (3 Marks)
NPV calculations for 10% discount rate are as follows:
Year Option-1 Option-2 Option-3
PV
Factor
Present
Value
(Option-1)
Present
Value
(Option-1)
Present
Value
(Option-1)
0 (5,00,000) (5,00,000) (5,00,000) -5,00,000 -5,00,000 -5,00,000
1 2,50,000 50,000 50,000 0.909 2,27,250 45,450 45,450
2 2,50,000 50,000 2,50,000 0.826 2,06,500 41,300 2,06,500
3 50,000 2,50,000 2,00,000 0.751 37,550 1,87,750 1,50,200
4 50,000 1,50,000 3,50,000 0.683 34,150 1,02,450 2,39,050
5 50,000 5,00,000 50,000 0.621 31,050 3,10,500 31,050
NPV
= 36,500 1,87,450 1,72,250
From above table, ranking of options will be – 1) Option-2, 2) Option-3, 3) Option-1
1 c) ‘S’ Curve: (5 Marks)
„S‟ curve is graphical representation of “Cumulative project cost” (y-axis) against “Time
schedule‟ (x-axis)
It is also plotted “Cumulative man hours” (y-axis) against “Time schedule” (x-axis)
This plot takes shape of English alphabet „S‟, so it is known as „S‟ curve.
It is plotted over the phases of project life cycle.
Shape is always travelling in upward direction, as cost is cumulative.
Application in project management to asses / estimate: time, baseline, cost, time etc.
Downloaded by Drishti Desai (
[email protected])
lOMoARcPSD|40491798