Page 11 of 39 MI-70071-002 B UNITED CONVEYOR CORPORATION
Fly ash silos are equipped with a fluidizing system, fluidizing air heater,
vacuum/pressure safety relief valve, level instruments, and a bin vent filter for
exhausting conveying and fluidizing air to the atmosphere.
4A.2 DETAILED SYSTEM DESCRIPTION OF DEPAC® SYSTEM
Pressurizing air is taken from an air receiver located near the precipitator building
in ESP area. The receiver is charged by any two of the three oil free rotary screw
compressors. Two compressors are required to provide the air flow needed to
convey ash in three conveyors at a time. There is a total of four lines/conveyors
(three lines from ESP and one line from air heater). In Cleanout mode only one
line should be selected at a time. Other lines should not be under operation due to
high air requirement for the line under Cleanout mode.
There are two conveyor lines from ESP Field 1 and 2 named Conveyor A and
Conveyor B. The remaining fields are connected to another conveyor named
Conveyor C. Air heater hoppers, which are conveyed with a NUVA FEEDER
system, are connected to dedicated line Conveyor D. Conveyor A and Conveyor B
are designed to operate for six hours in an eight hour shift. Conveyor C is designed
to operate for three hours followed by Conveyor D for another three hours in an
eight hour shift.
A manual knife gate is provided for isolation of each hopper. Each hopper is tied
into the conveyor branch line by Ash Inlet Valve and a DEPAC
vessel, which is an
integral part of the conveyor line.
Ash conveying rows are designated in P & I Diagrams. Three conveyors will be
started at a time. For Conveyor A, it will be started from Field 1; two vessels will
be filling while two others will be under conveying. After completion of
conveying, the system will shift to Field 2. Conveyor B, which is connected to the
remaining hoppers of Field 1 and 2, will convey in the same manner. At the same
time, Conveyor C will convey sequentially from Field 3 to Field 8. In each field (3
to 8), four vessels are conveying at a time while four are filling. After completion
of Conveyor C conveying, the NUVA FEEDER system which is connected to
Conveyor D, to be taken up.
During one conveying sequence, fly ash collected in the precipitator hoppers is
gravity fed into the DEPAC vessels. The ash, from hoppers, simultaneously fills
the group of vessels until a fill timer expires or a level probe is met. One vessel in
each conveying row is provided with a high level switch. This level switch is used
to close the Ash inlet valves and can also be used to set the fill timer of the vessel
during start-up or during plant operation. With all vessels (if not bypassed) in the
first row of the selective group filled with material, the Ash Inlet valves will close
on all vessels in the group. Once the limit switches prove that the DEPAC Inlet
valves are closed, there is a 3 second delay, then the vent valves close. After the
DEPAC inlet and vent valves have closed, there is a 3 second delay, then the
Conveying air valve will open. After this the fluidizing phase commences by
opening the Pressurizing valve while the DEPAC Inlet, vent, and discharge valves
remain closed. In normal operation, after opening of the Conveying air inlet valve
followed by Pressurizing valve the system waits for normal pressure. This pressure
is set very low (2 psig~), so almost immediately the discharge valve will open.
With all vessels (if not bypassed) in the first row of the selective group filled with
material, the ash is conveyed and discharged to the selected fly ash silo. At the silo,