STAGE OF CONSTRUCTION
2
BLOCK STAGE OF CONSTRUCTION
Block 1
STP Wall and Column Reinforcement & Shuttering work in
progress.
Block 2
Terrace – Parapet Wall Shuttering and reinforcement work
in Progress.
Block 3- P1
11th Roof – Wall Reinforcement & Shuttering work in
progress.
Block 3-P2
12th Roof – Wall & Roof Shuttering Work In Progress.
Block 3-P3
3rd Roof – Wall Reinforcement & Shuttering work in
progress.
Block 3-P4 First Roof – Wall & Roof Shuttering Work In Progress.