Detailed information about Bandra Worli sea link Mubai.
Size: 2.5 MB
Language: en
Added: May 17, 2020
Slides: 41 pages
Slide Content
Belagavi -590018
Technical Seminar On
BANDRABANDRA--WORLI SEA WORLI SEA
LINKLINK
Visvesvaraya Technological University
LINKLINK
By:
KAVYA HULLUR
(USN : 2VX19CSE05)
Under the Guidance
Prof. KIRAN MALIPATIL
DEPARTMENT OF CIVIL ENGINEERING
VTU BELAGAVI.
2
CONTENTS
Introduction
Location
Objectives
Sequence of the project
Characteristics
Main components
Main components
Foundation and substructure construction
Superstructure construction
Cable stayed bridge
Loading
Conclusion
References
INTRODUCTION
TheBandra-WorliSeaLink,officiallycalledRajiv
GandhiSeaLink,isacable-stayedbridgewithpre-
stressedconcrete-steelviaductsoneithersidethat
linksBandraintheWesternSuburbsofMumbaiwith
WorliinSouthMumbaiacrosstheMahimBay.
Bandra-WorliSeaLinkisthelongestseabridgeof
india.
Designed By : Sheshadri Srinivasan(Structural
engineer ).
Commissioned By : Maharashtra State Road
Development Corporation.
Cont..
Constructed By : Hindustan Construction company,
India ( HCC)
The foundation stone was laid in 1999,Construction
started on 2000, opened to the public on 30 June
2009, all eight lanes were opened on 24 March 2010.2009, all eight lanes were opened on 24 March 2010.
The original plan estimated the cost at ₹6.6 billion to
be completed in five years but the project was
subjected to numerous public interest litigations, with
the 5 year delay resulting in the cost escalating to ₹16
billion .
LOCATION
Side view of main cable stayed
Front view of main cable stayed
Construction of foundation below the
cable stayed portion
RCD Drill Bit used in RCD Rigs for
foundation construction
ThePiersforthebridgearehollowbutthePiercaps
aresolidmassofconcrete.Prefabricatedreinforcement
cagesarebroughtatsitefortheconstructionofthe
piersandsacrificialconcretelinesareinstalledwitha
Pile cap and Pier
SUB STRUCTURE CONSTRUCTION
piersandsacrificialconcretelinesareinstalledwitha
topcoversoastocreatethehollowpartinsidethem.
Onceinnerlinersareinstalledthecageisalignedin
thepositionandplacedasrequisiteandconcretingis
doneafterinstallingtheouterform.Therecessfor
bearinginstallationiscastwithPiercap.
Pile Cap Reinforcement
Cross section of pier
The formwork for the Sub structure Completion of pierThe formwork for the Sub structure
construction
Completion of pier
Constructed piers
SUPER STRUCTURE CONSTRUCTION
Segments
Thesegmentsarecastatacentralizedpre-casting
yardusingshortlinemethodofcasting,whichmeans
onceasegmentiscasteditsconjugatesegmentisonceasegmentiscasteditsconjugatesegmentis
castedrightafteritsoasthetwoofthemmatches.
Atypical50mspancomprisesof15numbersof
precastsegments.
Thesegmentweightsvaryfrom110tonsto140tons
persegment.Thesegmentlengthvariesfrom3000mm
to3200mm.
Segment being cast and its conjugate
Segment being taken from the casting yard
to jetty
Top View of the Casting Yard
Erection gantry
The details of the Erection Gantry
CABLE STAYED BRIDGE
Complete cable stayed bridge at Bandra-side of the Sea Link
Cablestayedbridgeconstructioncanbedivided
amongfollowingcomponents:
Construction of foundation
Construction of Tower or Pylon below deck
Construction of Diaphragm
Construction of Pier Table
Construction of Tower or Pylon above deck
Erection of Deck and Stay Cables
Stressing of Stay Cables
Wet Joint Construction
Continuity PT and Grouting of Cables
Force adjustment and fine tuning.
Construction of foundation
TheP19PylonofBandraWorliSeaLinkstandsona
foundationcomprisingof52nos.M50Piles,eachof2m
diameters.
Construction of Tower or Pylon below deck
TheconstructionofPylonbelowincludes6liftsofM60grade
concreteeachof3.0mand1liftof3.260m.Therebarlayoutfor
everylegispredesignedandthesteelbarsarebeingcutandbentas
pertherequirementsoftheprefabricatedreinforcementcagesatthe
rebarfabricationyard.
Construction process of pylon
Construction of Tower or Pylon above deck
The following wind speeds are
binding according to the static
calculations:
During working and
climbing process:
Max wind speed = 70kmph
Bandra cable stayed
Max wind speed = 70kmph
Wind speed-exceeding
70kmph:
All working and climbing
process to be stopped
Wind speed-exceeding
100kmph:
Close formwork
Erection of Deck and Stay Cables
The deck or road bed is the roadway surface of a cable-stayed
bridge.
Dead loads are taken to be just the weight of the precast deck
section; any reinforcing steel is assumed to be accounted for by the
increased density of the concrete.
Density of reinforced concrete = 2400 kg/m3=24 KN/m3
Cross-sectional deck area =7.2m2 Cross-sectional deck area =7.2m2
Force per unit length on deck=Density ×Area=24 ×7.2=172.8
KN/m
Deck Cross Section
Cables
Eachcableconsistsagroupofsteelwires(6wires)hasadiameter
7mmwithabreakinglimitof6.28Tonnes.
GroupofthesewireswaspackedintwolayersofHDPE(High
Density Poly Ethylene) material, Six different sizes of cables were
used in the cable stayed portion. The difference between them was
only on the basis of number of steel wires in each cable. Six different
types used were of 61, 73, 85,91, 109 and 121 steel wires.
.
Loading
Dead Loads
Super-imposed Dead Load
Live Traffic Loading
1. HA : HA is the combination of the effects of a
UDL over a notional lane and a knife-edge load place
at the most critical point within this lane.at the most critical point within this lane.
2. HB: HBloading takes account of a particularly
large truck placed at the most critical point along the
bridge.
Wind Loading
Seismic Loading
Natural Frequency
Loading Calculations
Loads Factors Value
Dead 1.05 177.9kN/m
Super-imposed
Dead
1.75 178.5kN/m
HA 1.5 13.5kN/m
HB 1.3 45 units,
nominally
146.3kN per
wheel
CONCLUSION
Having studied the Bandra Worli Sea Link in depth
we can appreciate that it is a worthy representation of
current bridge engineering technology and a good
example of what is possible in the current climate.
The optimised execution of the inverted Y design of
The optimised execution of the inverted Y design of
the pylon is a solution that is both aesthetically and
technically successful.
The use of tensioning mechanisms has provided an
efficient compromise between deck sizing and costly
strengthening methods.