Lemery Cement Silo Tank Corporations Projects Update
Manpower Update Total projected Headcount - 87 manpower (single shift) Item Direct Hired – Direct Employee Contractual - Direct Agency Agency - Pakyaw - Project Base Projected Headcount 32 27 28 Current Headcount 13 - - Remarks 4 newly added as of July 1 1 – Mechanical 1 - Electrical 1 – Operator for Ship-Unloader 1 - CCR Operator July 16, 3 new manpower will be added for testing and running Ship UNLOADER and CCR Operations Only FORTSTEEL send quotations They have bobcat to support vessel cleaning with minimum of 6hrs per day usage with no cost effect to their current quotations. Forklift also available but with cost effect when ask to use. Friday, July 5 start to interview manpower c/o LCSTC
Project Status (Construction-Erection-Installations) Ship Un-Loader / Screw Un-Loader
Ship Un-Loader / Screw Un-Loader Ship unloader #1 Cable wirings @ 80% and mechanical/hot works @ 85% Ship-Unloader #2 90% Completions On-going DCS Module set-up and installtion Waiting for no-load commissioning-de-bugging, awaiting for RBS commitment to proceeds
Material transfer 1 and 2 Conveyor Belt 1 and 2
Material transfer 1 and 2 Conveyor Belt 1 and 2 Conveyor belt already installed and vulcanized Safety features on-going installation Bag filters, gearbox, fans and motors on-going installations and adjustment Awaiting for electrical supply for trial run for final alignment and adjustment
Cement Silo 1-4 Silo 1 and 2 done and waiting for leak testing Silo 3-4 on-going construction target completion end of July (initial target end of June) Note As of July 1, 2024 2 material funnel of Silo 4 are handed over to AOTUO for the provision of air slide connections and expected to handed over another 4 material funnel. All Cement Silo will be subjected for water leak test
Cement Silo 1-4 Silo 1 and 2 done concrete of truck driveway, waiting for 28days final concrete testing test result (July 5 schedule witnessing 7days concrete test) Silo 1-2 motor jog test done and waiting for electrical supply for motor and air slide dry run. Silo 3-4 on-going fillers and constructions inside silo Silo 3-4 for electrical terminations on motors. and hoppers air injections piping's.
Bagging facilities (Jumbo and 40kg)
Bagging facilities (Jumbo and 40kg) Airline already provided waiting for completion of Air Compressor installations. Lifting hoist for 40kg and Jumbo bag not yet installed target date of arrival of equipment July 20 as per confirmation by AOTUO and needed only 4 days for installation. 6 access ladder not yet confirmed and accepted between AOTUO and PHIL HAOTAI who will be the one to build and install. The access ladder are part of the drawing and design for 40kg bagging area. Lot number/Manufacturing date printer not yet available on-site, still in China as per AOTUO and no target date on when it will arrive and inslatted .
SILO and Packing Area Status SILO waiting for air slide connection and on-going clearing and fillers construction. 40kg packing area truck drive way on-going base course and preparation for concreting, target not yet confirmed by PHIL HAOTAI
QC Lab Status 3 QC Lab Technicians on-going lab trials and equipment familiarizations. ASTM Training on-going discussion and for approval.
SPARE PARTS SUPPLIER PROPOSAL
Projects for Approval Waiting for FRI design of the truck scale base Propose not to demolished current concreted road, the propose design less costly from the original design
Projects for Approval
Projects for Approval - Canopy (extended roof) at 40kg and Jumbo-Tonner packing-loading area
Projects for Approval
Projects for Approval TIRE Bath Waiting for final design c/o FRI
Waiting for Status Base on the last discussion with all supplier, the design and logged over-all weight of the equipment will be the same as actual. 0.45 m³ bucket capacity and capability for street sweeper for flexibility use and will be use as well as back-up for bigger equipment when under repair and will be use for final clean-up of the vessel which bigger loader cannot reach. 1 Pay Loader with 3 m³ bucket capacity, this Pay Loader is flexible for different type of Vessel size and can be lifted by lifting boom- mobile crane and no need to set-up shore crane.
Waiting for Status These equipment are essential for the successful execution of the projected commissioning and will greatly enhance our efficiency, repair and maintenance activity and productivity on-site. This will be use generally to lift heavy equipment for preventive and repair maintenance as well as lifting loader equipment during cement delivery at pier.
Waiting for Status LCSTC Internet PPE Ship Un-loader #2 Cable Tools Changes from CONVERGE Internet fiber optic to STARLINK Waiting for final cost approval for the STARLink Devices Trial test will be done on July 10 to check if no issues of connectivity. Proposal and master list of requirements already provided by Lemery Cement. Waiting for Purchasing feedback. LCSTC recommend HI-SAFEY supplier after series of test and actual usage at the site. Note: HI-SAFETY can give discount waiting for discussion from Purchasing Waiting for confirmation of repair as per last meeting no timeline given by AOTUO. 3rd party verification and qualification must be needed prior to use after repair. Cable will be replace after temporary repair but there is no black and white for final acceptance whether AOTUO really accept the responsibility to replace cable. 1 st and 2 nd batch already arrived including the hydraulic grease pump that requested by AOTOU to expedite their the OIL and grease re-fill. Next batch still on-going consolidation and review to removed what is already bought and delivered. Other tools like sealing and cable tie ( webbling TIE) for lifting and safety harness of equipment when repair and lift are under consolidations of supplier and quotations.