FORTIS HOSPITAL, NOIDA – A Case Study SUBMITTED BY: SUPRIYA GIROTI KOMAL MITTAL SIMARPREET KAUR RAJBIR KAUR RUPINDER KAUR B.ARCH VIII SEM BATCH OF 2005-2010 SUBMITTED TO : AR. SARITA SOOD AR. RAGHAV BHARDWAJ A R C H I T E C T U R A L D E S I G N VII
FORTIS HOSPITAL IS LOCATED AT SEC -62, NOIDA ( UP) IT LIES OPPOSITE SEC -63 INDUSTRIAL AREA. SITE AREA : 7 ACRES GR. COVERAGE : 35% BUILDING HT . : 24MTS. EMERGENCY & STAFF : 95 GEN.& VISITORS :50/day 01 FORTIS HOSPITAL , NOIDA, U.P . INTRODUCTION
VEHICULAR MOVEMENT PEDESTRIAN MOVEMENT EMERGENCY MOVEMENT SERVICE MOVEMENT CLASHPOINT VERTICAL CIRCULATION 02 EMERGENCY ENTRY PEDESTRIAN ENTRY MAIN EXIT SERVICE ENTRY MAIN ENTRY N T H E S I T E
WIND DIRECTION & ORIENTATION WEST EAST SOUTH NORTH LIGHT TO OPD CONSULTATION ROOMS WARDS GET PROPER AIR CIRCULATION AND AMPLE LIGHT DUE TO DIAGONAL PLACEMENT OF THE BLOCK 03
SURROUNDINGS 04 THE SURROUNDINGS COMPRISE THE RESIDENTIAL AREA OF SECTOR 62 AND ALSO THE INDUSTRIAL AREA OF SECTOR 63 WHICH LIES OPPOSITE IT. THE HOSPITAL HAS BEEN DESIGNED KEEPING IN MIND THE ARCHITECTURE OF THE SURROUNDING BUILDINGS AND THUS IT MERGES WELL WITH THE SITE AND THE SURROUNDINGS.
05 35% BUILTUP MASS 35% ROADS & PARKING PIE-CHART - TRIANGULAR PERGOLA BALANCES AND VISUALLY CONNECTS 2 BLOCKS . 30% GREEN
59% WARDS 4% ADMN. 17% SERVICES 17% DIAG. & TREATMENT. AREA PIE- CHART DENOTING SPACE ALLOCATION 3% OPD & EMERGENCY LONG CORRIDOR CONNECTING EMERGENCY WAITING AND DIAGNOSTIC WAITING SEPARATES PUBLIC TRAFFIC FROM HOSPITAL TRAFFIC. EMERGENCY WELL CONNECTED WITH DIAGNOSTIC AREA . GRID USED = 7.2 M X 7.2 M ALL FLOOR WALL JUNCTIONS AND CORNERS ARE ROUNDED WITH EPOXY RAISINS. PROPER ZONING OF PUBLIC LIFT LOBBY HELPS PUBLIC & HOSPITAL FUNCTIONS. 06
-CENTRAL PATHOLOGY AND BLOOD BANK. - PERIPHERAL AREA GIVEN TO ADMN AND KITCHEN TO ENSURE PROPER VENTILATION . -MORTUARY PLACED NEAR TO THE LOADING AREA FOR EASY HANDLING OF DEAD BODIES . CIRCULATION SERVICES UTILITY O.T. DIAGNOSIS CONSULTANT EMERGENCY BASEMENT FLOOR PLAN 07 ADJACENT LAWN LVL BROUGHT DOWN TO FACILITATE LIGHT & VENTILATION INTO THE ADM AREA.
FORTIS FLOORING SKIRTING & DADO WALL FINISHES CEILING ENTRANCE LOBBY NON GLAZED NON SLIPPERY CERAMIC TILES MARBLE CHIPS GREEN MOSAIC SKIRTING PLASTIC EMULSION PAINT UPTO 3’6” &CREAM COLORED PAINT ABOVE GYPSUM BOARD FALSE CEILING OPD WAITING MARBLE CHIP WHITE MOSAIC MARBLE CHIP GREEN MOSAIC SKIRTING PLASTIC EMULSION PAINT UPTO 3’-6” &CREAM COLOURED ABOVE CREAM COLOURED CEILING O U T P A T I E N T D E P A R T M E N T 10
-PATIENT LIFT PLACEMENT CLOSE TO CASUALTY EASES ITS CIRCULATION TO O.T . -CORRIDOR RECEIVING DIRECT SUNLIGHT REDUCES THE EFFECT OF LONG DARK CORRIDOR. WIDTH OF CORRIDOR = 2400 MM AS PER STANDARDS = 2250 MM D I A G N O S T I C B L O C K 11
ICU’S HAVING THEIR UTILITY AREA IN THE CENTRE CORE. DUMB WAITERS HAVE BEEN PROVIDED FOR STERILE SUPPLY FROM C.S.S.D . SOUTHERN SIDE ON THE ICU FLOOR GIVEN TO DOCTORS AND RELATED SUPPORT AREAS . - ALL REQUIRED SERVICES TO THIS HIGH STERILITY AREA IS CATERED TO AT BASEMENT FLOOR . -O.T. PLACEMENT IN SEPARATE BLOCK HELPS TO FILTER THE PUBLIC TRAFFIC OF ICU AWAY FROM THIS HIGH STERILE AREA. CIRCULATION SERVICES UTILITY O.T. DIAGNOSIS CONSULTANT EMERGENCY 12 SECOND FLOOR PLAN
-NO SPECIFIED RECOVERY ROOM. PATIENTS ARE SHIFTED TO THEIR RESPECTIVE WARDS. - A CENTRALIZED NURSING STATION . DIRTY UTILITY IN LABOUR ROOM. INTERNAL CONNECTION BETWEEN LABOUR ROOM TO DELIVERY ROOM AND OPERATION THEATRE. CIRCULATION SERVICES UTILITY O.T. DIAGNOSIS CONSULTANT EMERGENCY THIRD FLOOR PLAN 14
CHANGING ROOMS FLOORING SKIRTING & DADO WALL FINISHES CEILING WHITE MARBLE CHIPS IN WHITE CEMENT MOSAIC FLOORING ROUNDED EDGE VINYL SKIRTING PLASTIC EMULSION PAINT UPTO 5 FT. AND CREAM COLOURED PAINT ABOVE GYPSUM BOARD FALSE CEILING CEMENT CONCRETE CEMENT CONCRETE WHITE PAINTED WALLS KOTA STONE 100 MM KOTA STONE WHITE PAINTED WALLS GYPSUM BOARD FALSE CEILINGS GLAZED CERAMIC TILES GYPSUM BOARD FALSE CEILINGS FLOORS REST OF FLOORS CORRIDORS BASEMENT FLR O.T. FINISHES 16
WATER SUP PLY SOURCE NOIDA MAIN SUPPLY & BORE WELL FIRE TANK 2 OF 125 KILO LTRS RAW WATER TANK 2 OF 125 KILO LTRS TREATED WATER TANK 4 OF 125 KILO LTRS ELECTRICAL SOURCES SUB ST. SEC. 62 OF 11000 KVA TRANSFORMER 1 OF 2000 KVA DG SET 2 OF 750 KVA , 1 OF 1000 KVA FOR FUTURE UPS INDIVIDUAL UPS SYS. ON EACH FLOOR SERVICES 17
MERITS: RED BANDS HAVE BEEN PROVIDED ON THE EXTERIOR IN MINIMUM QUANTITY IN CONTRAST TO THE WHITE EXTERIOR FINISH.THIS CONCEPT IS CALLED MINIMALISM ( generally used with red & white colour combination) - TO AVOID MONOTONY OF COLOUR AND FOR EASY VISIBILITY FROM ANY AIRPLANE. BUILDING FINISHES ARE KEPT LIGHT IN COLOUR TO DECREASE THE VISUAL DENSITY OF HEAVY MASS. WALL EDGES AND CORNERS ROUNDED WITH EPOXY RESINS. THE I.P.D. BLOCK IN A DIAGONAL PLACEMENT R ELIEVES THE HEAVY MASS OF BUILDING AND SETUP INTO CONE OF VISION . TO AVOID EXCESSIVE HEAT PENETRATION INTO THE ATRIUM ALTERNATE TRANSPARENT AND TRANSLUSCENT POLYCARBONATE SHEETS HAVE BEEN USED. INFERENCE 18
DEMERITS: TOO MANY ENTRIES TO THE SITE CREATE CLASH POINTS FOR TRAFFIC MOVEMENT. NO SPECIFIED RECOVERY ROOMS . PATIENTS ARE DIRECTLY SHIFTED TO THE WARDS AFTER OPERATION. NO UNLOADING AREA FOR KITCHEN AND THUS EMERGENCY TRAFFIC IS AFFECTED. AREA UNDER ROADS IS 35% OF THE TOTAL AREA: WHICH IS MORE THAN REQUIRED. --------------------------------------------- 19