Discuss how pricing policy is adopted by managers and discuss the major issues
considered to adopt a certain pricing policy
• Identify the pricing arrangements in contracts and discuss what bidding
strategy can be adopted by a firm from a project to maximize wealth.
• For a strategy to be adopted one needs to know the tendering procedures and
the associated issues.
• Determining a firm’s mark-up target
• Discuss the major construction contracts and their risk structure to the
contracting parties .
Chapter Summary
Introduction
Factors that need to be considered in construction pricing
•Work at hand,
•The geographical areas in which the firm will operate,
•Type of client the organization is to favor, ( private, local
authority, community services, )
•Projected risks and uncertainties of the project,
•Form of the bid: (open, short-listed, pre-qualification, etc.)
Bid Qualification
Procedure
Competitive Bid Negotiated Bid
Short listed Open Bid
One Stage ProcedureTwo Stage Procedure
Pre-Qualification Post Qualification
In a competitive tendering situation, the contracting firm is
constantly facing a tradeoff of submitting a high price for
getting profit and the resulting shortage of work, with that
of a low price for winning the contracts, but allow little
profit margin.
A bidding pattern could be worked out for his major
competitors.
An optimum bid could be ascertained by combining the
probability curves (the Z-distribution) and developing a
bidding curve using a linear regression line for this
situation.
Develop a bidding strategy to determine the
OPTIMUM BID
First step: MAP THE BIDDING PATTERN OF KEY
COMPETITORS
ii) Plot the information on a scattered diagram
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
0 200,000 400,000 600,000 800,000 1,000,000 1,200,000 1,400,000
Scattered Diagram
W
i
n
n
e
r
’
P
r
i
c
e
Contractor’s Own Price
iii) Draw the most likely curve regression line
0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
0 200,000 400,000 600,000 800,000 1,000,000 1,200,000 1,400,000
Scattered Diagram
W
i
n
n
e
r
’
P
r
i
c
e
Contractor’s Own Price
2
2
xxn
yxxyn
m
2
2
2
xxn
xyxxy
b
222
2
1
xy sms
n
n
VARIANCE
Y = mX + b
Where: Y: refers to the most likely winning price,
X: refers to contractor’s tender prices
m & b are coefficients of the regression line.
m: The slope of the line
b: The intercept of the line.
n : number of samples.
Furthermore, one has to determine the standard deviations, to
define the probable region of winning a tender.
S
y
= STDEVA (Y values)
S
x
= STDEVA (X values)
iY
Z
iv)The final step is to decide the probability of
winning a tender using the normal distribution
Yi Price
= probable cost
Z
Probability
P
Normal Dist
n
45%45%
Determining Probability
Z values: table
Z 0.00 0.01… 0.09
1.9 0.47130.4719 … 0.4767
.
.
1.6
.
.
.
.
.
.
= 615,251 Tender amount
(Birr)
Yi
P( Yi ) = 95%
Z = 1.645
50%50%
Example: For the example in (i), suppose the
contractor’s tender sum amounts to 675,000 Birr.
Determine the rebate to be improvised with 95 %
probability of winning the tender.
m= 0.813, b= 66476.91, Standard deviation = 55509.2
The most likely winning price, Y = 0.813(675,000) + 66476.91 =
Birr 615, 251.91:- taken as the mean value (µ) with a winning
chance of 50%.
The Z-values of 95% probability, from the table = 1.645. The
relation between Z and probability in this case is inverse.
Higher probability is achieved by reducing the bid price and hence
we need to use the negative value of what we read from the table.
Z= -1.645, µ = 615,251.91 and δ = 55509.2,
Yi = Birr 523,939.28
Rebate (R) = 100% -- (523,939.28/675,000) x100%
= 22.38 % (95% probability of wining)
= 8.9% (50% probability of winning)
i) Decision to Tender
• Production workload,
• Future commitments,
• Market,
• Capital,
• Associated risk,
• Estimating workload,
• Time for preparation of tender,
Procedure for tendering:
ii. Collection of Information:
Time scale for tendering with key dates as mentioned in the invitation to bid,
Examination of contract documents, with preliminaries attached with the
tender,
Assessment of client and design team,
Enquiries to suppliers and sub-contractors with a time scale,
Site and locality visit,
Discussion with site management, plant and planning department,
Evaluation of alternatives
Preparation of detailed construction method statement and pre-tender
programme, developed to include production outputs, gang sizes, plant
details, etc.
iii .Preparation of estimate:
Iv .The tender:
V. Action with tender results:
Mark up can be seen as the sum of general overheads, provision for
risks and profit margin.
General Overheads
Costs entailed in administering the company and providing off-site
administration
Several expenses incurred at the corporate headquarters of a
company cannot be directly traced to any particular project
Research and development
publicity and advertisement
cost of unsuccessful bids
recruitment of personnel
security personnel at the head office etc
Contingency for Risks
Construction projects are risky proposition full of uncertainties and
risks.
In spite of different details known at the tendering stage there are
uncertainties and risks pertaining to :
•timely completion
• budget escalation
• site conditions
• soil characteristics
•labor, and material availability and so on.
In order to safeguard against these eventualities contractors keep certain
contingencies provisions so that should these risks materializes one can
use the contingency.
Profit
This is a reward of carrying out the business and thus taking risk.
Risky business carries more profit and vice versa.
Factors Affecting Mark-Up
Number of competitors and the intensity of competition
Size, cost, and intensity of the project;
Type of projects such as buildings or infrastructure
projects etc.
Duration of the project
Location of the project
Season in which the work is done
Degree of hazard and difficulty associated with the project
Name of owner/consultant and designers and date and place of
bid submission;
Labour availability and productivity
Material availability and costs;
Per cent of the work which is to be subcontracted and the bids of
sub- contractors
Insurance cost and Fringe benefits;
Supervisory talent availability
Method of performing the work
Uncertainty in estimate and historic profit;
The current and forecasted economic conditions
The contractor's risk attitudes
-To determine firm’s mark-up target, it is required establish:
i) Return on Capital Employed (ROCE), which is made to
account the following costs:
·
The average weighted cost of capital ( Interest of capital employed)
·
Profit margin (dividends, capital reserves...)
·
Corporate obligations such as taxations and deprecation costs.
·
Contingencies to cover uncertainties ( Risks)
ii) Annual Turnover on contracts. This can be obtained from
the firm’s short-term plan committed or planned for execution
in the current year.
iii) General overhead costs (off-site administration)
Example
Assumptions
Capital Employed: Birr 2,000,000
Turnover on contracts for year:Birr 4,000,000
General overheads: Birr 160,000
Return on Capital Employed 17%
Target: Contracts must contribute (Head office Mark-up)
General overheads Birr 160,000
Return ( ROCE) 17% ( 2,000,000 ) Birr 340,000
Head office Mark-up = Birr 500,000
Production Costs = 4,000,000 – 500,000 = Birr 3,500,000
Mark-up on contracts = (500,000 / 3,500,000) x 100 = 14.3%
The distribution of markup is also an important decision that a contractor has
to take.
Example: total value of the project was Br. 500 million and the markup
amount was Br 50 million. Thus the total cost to the contractor for this project
works out to be Br. 450 million. The markup in terms of percentage works out
to be 10% of the value or 11.11% of the total cost. There are different ways to
distribute the markup amount of Br. 50 million. Although it does not affect the
total bid price, the timing of cash receipt plays an important role in easing the
negative cash flow which is usually encountered in the beginning phases of a
project.
Uniform loading
Front loading and
Back loading of Markup
Sl. No.
Item Description Bid
Amount
In million
Total Cost
In million
Markup distribution (Total mark up amount = br. 50 million)
Uniform Loading Front Loading Back Loading
Mark up
amount
Mark up % Mark up
amount
Mark up % Mark up
amount
Mark up %
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
1 Earthwork - All Soils5 4.5 0.5 11.11 1 22.22 0.25 5.56
2 Concrete works 80 72 8 11.11 10 13.89 6 8.33
3 Formwork 42 37.8 4.2 11.11 7 18.52 3 7.94
4 Reinforcement works 112.5 101.25 11.25 11.11 13 12.84 7 6.91
5 Brickwork
34 30.6 3.4 11.11 4.7 15.36 2 6.54
6 Plastering - All types
15 13.5 1.5 11.11 1.5 11.11 3.05 22.59
7 Painting - All Types 5 4.5 0.5 11.11 0.5 11.11 1 22.22
8 Flooring - All Types
110 99 11 11.11 7 7.07 14 14.14
9 Waterproofing works
12 10.8 1.2 11.11 1.2 11.11 1.2 11.11
10 Aluminum work
13.5 12.15 1.35 11.11 0.5 4.12 2.5 20.58
11 Electrical work
35 31.5 3.5 11.11 1 3.17 6 19.05
12 Sanitary & Plumbing
works
20 18 2 11.11 1 5.56 1 5.56
13 Road Works
16 14.4 1.6 11.11 1.6 11.11 3 20.83
Total500 450 50 100% 50 100% 50 100%
Table shows the three ways in which the total mark up has
been distributed.
In the first case the total mark up is distributed uniformly
across all the activities of the project.
In the second case, the activities which are likely to be taken
up early in the project carry a higher mark up percent. This
is known as ‘front end rate loading’ and has an effect of
improving the cash flow in the early stages of the contract.
In the third case, the mark up percent is higher for the items
which are planned to be completed in the final or later
stages of the project. This is referred to as ‘back end rate
loading’
All Pricing arrangements have some common features in
the form of the legal documents binding the owner and
the supplier (s) of the facility.
Common types of Pricing arrangements are:
1)Competitive Bidding
• Final bid
submitted on lump
sum or unit price
basis
2) Negotiated Contracts
•Reimbursement is direct
project cost plus the
contractor’s fee
All forms of construction pricing arrangements pose
differed level of risk to the parties in the contract.
Hence, it is important to identify the provisions for risk
in contracts.
Force major : "Acts of God" and other external events such
as war, etc
Indemnification: third party liability transfers
Differing site conditions,
Delays and extensions of time,
Liquidated damages,
Occupational safety and health of workers,
Termination for default by contractor,
Suspension of work
etc
In addition to serving as a means of pricing construction,
contracts also structure the allocation of risk to various parties
involved:
I. Lump Sum Contract
All risk assigned to the contractor
II. Unit Price Contract
In a unit price contract the owner and the contractor agree as to
the price that will be charged per unit for the major elements of
the project.
Problem: Unbalanced Bid
Description Actual
Quantity
Unit prices (Birr)
Contr. A Contr. B
Actual Amount ( Birr)
Contr. A Contr. B
Masonry Works200 m3 250 400 50,000 80,000
Re. Bars 5100 kg 8 6 40,800 30,600
90,800 110,600
50,000 52,500
30,000 40,000 6 85000 kg Re. Bars
20,000 12,500 400 25050 m3 Masonry Works
Tender Amount ( Birr)
Contr. AContr. B
Unit prices (Birr)
Contr. A Contr. B
Estimate
Quantity
Description
III. Cost + Contracts :negotiated contract b/n contractor and client.
Actual cost+profit+allowance for risk
1. Cost Plus Fixed Percentage Contract
Purpose: for new approach/technology yet to be analyzed
The owner takes all the risks of cost
overruns
2. Cost Plus fixed fee contract
3. Cost plus variable percentage contract: used for
compromising b/n cost plus fixed fee and Cost Plus Fixed
Percentage Contract.
4. Target Estimate Contract
Actual costs measured against target estimates of the contractor.
This is another form of contract which specifies a penalty or
reward to a contractor, depending on
whether the actual cost is greater than or less than the
contractor's estimated direct job cost.