CIVL 411 Shotcrete Presentation 2017 (for distribution).pdf

sogeek 10 views 62 slides Feb 28, 2025
Slide 1
Slide 1 of 62
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62

About This Presentation

Presentation


Slide Content

TEMPORARY
EXCAVATION SUPPORT SHOTCRETE USE IN LOCAL PRACTICE Presented to CIVL 411
March 6, 2017
Steven Fofonoff, M.Eng., P.Eng.

Outline •
Review of shoring and shoring types

Introduction to anchored shotcreteshoring

Design considerations

Example simple design calculation

Construction sequence

Case Studies

Shoring •
What is Shoring?

the process of supporting a building, vessel, structure, or tre nch
with shores (props) when in danger of collapse or during repair s or
alterations (from Wikipedia)

Shoring types

Anchored Retaining Walls

Reinforced shotcrete

Secant pile, jet-grout, diaphragm walls

Sheet pile walls

Soldier pile with lagging (Timber or Shotcrete)

Cantilevered Retaining Walls

Pipe pile supported walls

Sheet piles walls

Soldier pile walls with lagging

Anchored Shotcrete Shoring •
What is Anchored Shotcrete?

An anchored reinforced concrete membrane (diaphragm) tied back
into the earth

Anchored Shotcrete Shoring

Anchored Shotcrete Shoring: A Brief Introduction •
Originally use was for tunnel support

In 1960’s, adopted for use in excavations by E. Mason

By 1970’s used in over 30 excavations and patented in
US and Canada

After seeing the successful use by Mason, designers and
contractors started to emulate the practice (mid 1970’s)

Since then methods modified by designers to meet project
needs and based on experience

From Shoring Practices in Greater Vancouver, British Columbia, Naesgaard, MacLeod, and Inglis, In proceedings of 48th Canadian
Geotechnical Conference, Vancouver, B.C., September 1995

Anchored Shotcrete •
Why do we use anchored shotcrete?

Proven to work

Most common method in Greater Vancouver

Contractors are familiar with the method

Economical

Lower material cost, relatively fast

Flexible

Highly adaptable to geometry

Can be used in tight spaces

Allows for construction at property line

With permission to encroach on neighbours property

Design of Anchored Shotcrete Shoring •
Design of anchor length, type, and spacing to support the
excavation

Requires making an estimate of earth pressure how it changes as
the excavation proceeds

Design Considerations •
Geology!!

Soil Type (frictional/cohesive)

Geometry (Height)

Site Constraints

Property lines – encroachment

Neigbouring buildings, services, and utilities

Surcharge Loads (Concrete Trucks, Cranes, Etc.)

Anticipated Impacts (On-Site and Off-Site)

External Loads Design Life?
Other Design Considerations

Well points installed to temporarily
dewater shoring face
Development of sand boils inside
excavationOther Construction Considerations: Dewatering

A large void developed over the weekend from the piping
of fines behind the shotcrete wall
Pre-Glacial Sands (Void)

Potential Failure Modes to Consider •
Internal Failure –Anchor Failure

Steel tendon failure (load exceeds tensile strength / damage)

Grout to ground bond failure

Grout to tendon failure

External Stability

Global Stability Failure (circular, wedge, compound)

Bearing Capacity

Base Heave

Design Earth Pressure •
Depends on…

Soil Type

Friction Angle

Cohesion

Groundwater Level / Dewatering

Excavation Sequence

Estimating Lateral Earth Pressure for Design
(Peck, 1969)

Apparent Earth Pressure Diagrams
SandSoft to Medium ClayStiff Clay
2
=
L 0.65?*-
a
2
=
L 0.2?* PK0.4?*
2
=
L?*
1F
4?
?*
(Peck, 1969)

Example Basic Design Calculation •
Assume an excavation in dense partially cemented sand

Excavation is 30 feet deep

Anchor spacing is 6 feet horizontally and vertically

This is typical for dense sand or glacial till site in Vancouve r

Design Calculation –determining anchor design
loads •
Assume an Apparent Uniform Pressure Distribution(Pa)
Pa = 0.65KaγH; Ka=(1-sinΦ)/(1+sinΦ)
Pa = 0.65(0.27)125lbs/ft^3 x H (height)
Pa = 22*H

Load Calculation

assume 30’ depth, with spacing at 6’ horizontally and verticall y
F = Pressure x Tributary Area
F = 22(30’) x 30’(6’)
F = 118,800 lbs ≈ 120 kips

Determine Anchor Design Load
Anchor Design Load = Total Load / # of Anchor Rows
(Number of anchor rows would be 4 in this case_
Anchor Design Load = 120 kips / 4 Rows = 30 kips Horizontal
Anchor Design Load (installed at 15°) = 30 kips / cos (15°) = 31 kips

Anchor Design •
Choosing an Anchor Bar Type –considerations

Application (Permanent or Temporary)

Soil Type (Competent, Collapsing)

Groundwater Level

Capacity - Load / Testing Requirements

Design (<0.6Pu Permanent, <0.7Pu Temporary)

Test Load (<0.8Pu)

Required Anchor Capacity

31 Kips Design (from previous calculation)

Test Load = 1.3xDL = 40 kips

Test Load < 0.8Pu

So 40 kips x 1.25 = 50 kips

Refer to table from anchor supplier

Anchor Design

Choosing an Anchor Length

Calculate Required Bond Length

Based on friction along area of drill hole

Factors; normal stress, adhesion, mobilized friction

Drilling Techniques

Must be beyond active failure plan

Calculate Required Free Length (within active wedge)

Assuming level ground behind wall
measured from bottom of excavation

Generally works out to be 1H:2V

Design Example -Typical Shoring Section

Building an Anchored Shotcrete Wall

Typical Construction Sequence –First Lift

Soil berm removed; preparing for
shotcrete application
Temporary soil berm in place to
ensure stability
First Lift

Subsequent Lifts

Drilling anchors with an air track drill
for the next row; berm in place
Underpinning of a building
Drilling / Underpinning

Large “floaters” being prepared for
blasting
Continuous trimming in competent
sandstone

Bottom of the excavation Construction of the underground
parkade

Field Review •
Confirm inferred ground conditions

Review contractor sequence / methods

Review reinforcement placement and shotcrete
application

Anchor Test Review

Anchor Testing -Basic •
Confirm design load is achieved

Typical test of grout to ground bond is 1.33 to 1.5 times desig n load
for temporary applications

Confirm free length is achieved

Some elastic elongation should be observed

Test load is typically held for 2 minutes for proof test

Anchor Testing –PTI (1996) •
Proof Test Procedure

Anchor is incrementally loaded to Test load, held, and then ret urned to
the alignment load.

Creep – anchor held at test load for 10 min.

Acceptance Criteria

Movement between 1 and 10 min should be less than 1 mm

If criteria exceed test should be held to 60 min and log cycle between 6 min
and 60 min should be less than 1 mm

Free Length – elastic elongation

Theoretical Elongation can be determined from PL/EA

Acceptance Criteria

Minimum 80% design free length

Maximum 100% design free length plus 50%

Load Displacement Plot –Insufficient Free Length

Measured Elongation vs. Theoretical –Insufficient Free Length

Anchor Creep vs. Time (Acceptable)

Anchor Creep vs. Time (Failure)

Special case: what if you can’t encroach? •
Most often encroachment rights are required to place
anchors on adjacent private or city property.

It is not always possible to achieve this.

Alternative designs could include:

Internally Braced Excavations

Struts

Rakers

Corner Bracing

RakerSystem
1. Vertical shoring elements installed
2. Internal shotcrete waler
3. Bulk excavation
1. Rakers welded to wall and placed
in footings
2. Footings constructed
3. Hold down anchors installed

Building footing and drain pipes
installed
Soil berm left in pl ace until hold down
anchors are installed

Case History -UV Disinfection Plant –
Coquitlam Watershed

UV Plant -Shoring Considerations •
Large, temporary excavation approximately 18 m (~60
feet) deep

Permanent excavation was to be up to 9 m in height;
permanent retaining wall required

Considerations

Sloping ground behind

Water Table / Saturated Sands

Dewatering

Monitoring

Seismic design for permanent wall

Corrosion

Wall finish

UV Plant –Typical Shoring Section

UV Plant –Global Stability Check

Continuous Flight Auger Method Typical Secant Pile Cut-off Wall Layout

Secant Piles Exposed Beneath
Temporary Shotcrete
Drilling Anchors Through Secant Piles

Instrumentation –Vibrating Wire Piezometers

UV Plant –NW Wall Monitoring

UV Plant –Permanent Shoring Complete

Permanent Architectural Concrete in
Place
Reinforcing Being Placed for
Permanent Retaining Wall

UV Plant –Permanent Shoring Complete

Case History

Shoring Considerations •
Large, deep excavation –approximately 18 m

Adjacent to Canada Line Piers and Cambieand Marine
Station

Low tolerance for wall movement

Extensive monitoring required

Translink required minimal impact to facilities during construct ion

We demonstrated minimal settlement and displacement would occur,
using finite element modelling

Marine Gateway Shoring –Excavation Underway

Marine Gateway Shoring –Partially Shored

Marine Gateway Shoring –View From Excavation

Marine Gateway Shoring –Numerical Modelling -Settlement

Marine Gateway Shoring –Numerical Modelling –Horizontal Displac ement

Marine Gateway Shoring –Final Depth Achieved

Marine Gateway Shoring Inclinometer Results

Overview •
Anchored shotcrete shoring is the most common method of
supporting excavations in the Greater Vancouver area

Adaptable to project demands and soil conditions

Design assumptions (soil conditions) must be verified by
observation and testing during construction

Monitoring provides ongoing feedback of overall excavation /
shoring performance – early detection of unexpected behavior
allows design to be modified during construction if necessary

Thanks for listening – any questions?
Tags