Thumb Rules are very important for any civil engineer, Site engineer, or civil supervisor to obtain instant decisions on the construction site. Click here to read more
Size: 1.13 MB
Language: en
Added: Oct 19, 2020
Slides: 6 pages
Slide Content
THUMB RULES
THUMB RULE OF CONCRETE MATERIAL REQUIREMENT
Thumb rule to calculate the Steel quantity required for Slab,
Beams, Footings & Columns:
For Residential buildings - 4.5Kgs - 4.75 Kgs /SFT
For Commercial buildings - 5.0Kgs - 5.50 Kgs/SFT
Calculation of quantities of cement, sand and
aggregate in 1㎥ of concrete
8 bags of cement required for 1 cu.m of M-20 grade.
concrete.
693 kg of Sand required for 1 cu.m of M-20 grade
concrete.
1344 kg of 20mm Aggregate is required for 1 cu.m of M-
20 grade concrete.
180 litres of water is required for 1 cu.m of M-20 grade
concrete.
Example taken for M-20 (1:1.5:3) grade of concrete:
THUMB RULE FOR BRICK WORK
Size of brick : 190mm x 90mm x 90mm
Number of bricks per cum : 500