Construction Activities and Process

12,712 views 41 slides Jul 11, 2014
Slide 1
Slide 1 of 41
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41

About This Presentation

No description available for this slideshow.


Slide Content

Building Construction 1 [ARC 1523]

Project 2: Construction Activities and Process

Tan Wei How 0310707

Week 1













Week 2

Activity 1: Grading and Site Preparation
Duration: 5 days
Materials: Timber, Hoarding
Equipment: Theodolite, waste storage tank, backhoe, shovels, truck, construction
trolleys
Skilled worker: Land surveyor, Mobilization of manpower (carpenter), general
workers (2), Backhoe operator (1)
Technical information: Clearing up the site. Land demarcation for the site
boundary of site by using hoarding as safety guideline for whole construction site.

Activity 1: Earthwork
Duration: 6 days
Materials: -
Equipment: Vibrating plate compactor, backhoe, excavator, paver, dumper
Skilled worker: Backhoe operator, excavator operator, paver operator, dumper
operator
Technical information: Site is cut and filled to required lengths, depths, breadths.
Unflatten land surface need to fill up and cut down with sand or soil just to flatten
the land boundary that had been demarked.

Week 3 - 4












Activity 1: Foundation Construction (Piling process)
Duration: 10 days
Materials: piles, pile cushion, bituminous paint
Equipment: Hydraulic drop hammer (1)
Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General
worker (2)
Technical information: Mobilize the hydraulic drop hammer to the intended pile
position after marking penetration of the piles, set out the position of drop hammer
above the pile point, pile driving, weld the joints between the piles, apply
bituminous paint around the joints of welded piles to prevent rusting.
Activity 2: Foundation Construction (Cut off process)
Duration: 2 days
Materials: -
Equipment: Multipurpose excavator, Pneumatic hammer, Oxy-cutter
Skilled worker: Excavator operator (1), General worker (2)
Technical information: Excavate 1m to 1.5m depth by using Multipurpose
excavator, Cut the piles to make sure all are in the same height using Pneumatic
hammer, the reinforcement in the pile is cut by oxy-cutter.

Week 5



















Activity 1: Foundation Construction (Setting up formwork for pile cap)
Duration: 3 days
Materials: Plywood, nails, reinforcement mesh
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general worker (2), carpenter (1)
Technical information: Set up formwork for pile cap, insert reinforcement for
pile cap, and set up the reinforcement for column stump before pouring the
concrete.

Activity 2: Foundation Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2)
Technical information: Pour the concrete into the formwork through skip from
concrete mixer truck, vibrate and mix the concrete evenly using concrete vibrator
to increase its strength by preventing air pockets.

Week 6




Week 7









Activity 1: Foundation Construction (Setting up formwork for column stump)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (1), carpenter (1)
Technical information: Set up formwork for column stump before pouring the
concrete.


Activity 1: Foundation Construction (Pile cap curing period)
Duration: 7days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete pile cap harden for 7 days to wait it
mature and sufficient strength, open formwork after completed.

Activity 2: Foundation Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2)
Technical information: Pour the concrete into the formwork, vibrate the
concrete to increase its strength.

Week 8
Activity 1: Foundation Construction (Column Stump Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column stump harden for 7 days
to wait it mature and sufficient strength, open formwork after completed

Activity 2: Slab Electrical Installation
Duration: 3 days
Materials: Metal conduit, Steel/Aluminum tubing or PVC tubing
Equipment: Plow Chute, Winch
Skilled worker: Contractor (1), General worker (2)
Technical information: Socket of connection to the utility wiring is covered
in the ground at a depth that protects conductors from physical damage and
physical contact. Burying cable preinstalled in cable-in-conduit (CIC) offers
greater physical protection against environment, abrasion, and rocks than
direct burial, which can prolong the life of the cable.


Activity 3: Slab Plumbing Installation
Duration: 3 days
Materials: PVC pipes, PVC pipefittings, soft copper tubing, septic tank
Equipment: pressure test pump, bobcat, trencher, measuring tape, shovel
Skilled worker: Plumber (1), Trencher operator (1)
Technical information: Dig trenches as needed to run the sewer pipes and water
pipes, and should smooth the dirt or sand back when finished.

Week 9

Activity 1: Ground Floor Construction (Tying Rebar for Beam)
Duration: 4 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel
cage that will reinforce the pour concrete. They are tied together with tie wire
at varying intervals.

Activity 3: Slab Plumbing Installation
Duration: 3 days
Materials: PVC pipes, PVC pipefittings, soft copper tubing, septic tank
Equipment: pressure test pump, bobcat, trencher, measuring tape, shovel
Skilled worker: Plumber (1), Trencher operator (1)
Technical information: Dig trenches as needed to run the sewer pipes and water
pipes, and should smooth the dirt or sand back when finished.

Activity 2: Slab Electrical Installation
Duration: 3 days
Materials: Metal conduit, Steel/Aluminum tubing or PVC tubing
Equipment: Plow Chute, Winch
Skilled worker: Contractor (1), General worker (2)
Technical information: Socket of connection to the utility wiring is covered
in the ground at a depth that protects conductors from physical damage and
physical contact. Burying cable preinstalled in cable-in-conduit (CIC) offers
greater physical protection against environment, abrasion, and rocks than
direct burial, which can prolong the life of the cable.

Week 10










Week 11
Activity 1: Ground Floor Construction (Setting up formwork for beam)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.

Activity 2: Ground Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2))
Technical information: Pour the concrete into the formwork through skip
from concrete mixer truck, vibrate the concrete to increase its strength.

Activity 1: Ground Floor Construction (Beam Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete beam harden for 7 days to wait it
mature and sufficient strength, open formwork after completed

Week 12











Week 13

Activity 1: Ground Floor Construction (Tying Rebar for Slab)
Duration: 5 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel
cage that will reinforce the pour concrete. They are tied together with tie wire
at varying intervals.

Activity 1: Ground Floor Construction (Setting up formwork for Slab)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.


Activity 2: Ground Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: Concrete mixer truck, Concrete vibrator
Skilled worker: Concrete mixer truck operator (1), general worker (2))
Technical information: Pour the concrete into the formwork through skip
from concrete mixer truck, vibrate the concrete to increase its strength

Week 14










Week 15
Activity 1: Ground Floor Construction (Slab Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete slab harden for 7 days to wait it mature
and sufficient strength, open formwork after completed

Activity 1: Ground Floor Construction (Reinforce Column)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for column, pour
the concrete into the formwork through skip from concrete mixer truck, vibrate the
concrete to increase its strength.

Week 16
Activity 2: Rough Electrical Installation (Ground Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members. Wiring requirements differ
depending on the construction type and building element.

Activity 3: Rough Plumbing Installation (Ground Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping

Activity 4: Rough HVAC Installation (Ground Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed and
run to each location. The furnace is installed as well.

Activity 1: Ground Floor Construction (Column Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column harden for 7 days to wait it mature
and sufficient strength, open formwork after completed

Week 17



Activity 1: First Floor Construction (Tying Rebar for Beam)
Duration: 4 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage that
will reinforce the pour concrete. They are tied together with tie wire at varying intervals.

Activity 2: Rough Electrical Installation (Ground Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members. Wiring requirements differ
depending on the construction type and building element.

Activity 3: Rough Plumbing Installation (Ground Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping

Activity 4: Rough HVAC Installation (Ground Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed and
run to each location. The furnace is installed as well.

Week 18










Activity 1: First Floor Construction (Setting up formwork for beam)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.


Activity 2: First Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-mounted
hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-mounted
hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the formwork
through pipes and large hoses, vibrate the concrete to increase its strength.

Week 19










Week 20












Activity 1: First Floor Construction (Beam Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete beam harden for 7 days to wait it
mature and sufficient strength, open formwork after completed

Activity 1: First Floor Construction (Tying Rebar for Slab)
Duration: 5 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage
that will reinforce the pour concrete. They are tied together with tie wire at varying
intervals.

Week 21



Activity 1: First Floor Construction (Setting up formwork for Slab)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for slab before pouring the concrete.


Activity 2: First Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-
mounted hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-
mounted hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the
formwork through pipes and large hoses, vibrate the concrete to
increase its strength.

Week 22

Activity 2: Staircase Construction (Ground Floor)
Duration: 6 days
Materials: Plywood, Timber Battens, rebar ribs, steel cage, concrete grade 30
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
Concrete mixer truck, Concrete vibrator
Skilled worker: Carpenter (1), Concrete mixer truck operator (1), general worker (2)
Technical information: Construct formwork by laying out riser heights and tread
widths followed by soffit, joist and stringer lines. Then lay out thickness of risers
from boards. Place rebar as instructed. Pour the concrete into the formwork. Keep
the concrete wet or damp to prevent cracks for up to one week while it cures.
Activity 1: First Floor Construction (Slab Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete slab harden for 7 days to wait it
mature and sufficient strength, open formwork after completed

Week 23

Activity 2: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Activity 1: First Floor Construction (Reinforce Column)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for column.
Concrete is pumped and poured into the formwork through pipes and large hoses,
vibrate the concrete to increase its strength.

Week 24

Activity 1: First Floor Construction (Column Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column harden for 7 days to wait it mature
and sufficient strength, open formwork after completed

Activity 2: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Activity 5: Rough HVAC Installation (First Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed
and run to each location. The furnace is installed as well.

Activity 3: Rough Electrical Installation (First Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members such as the interior walls,
ceilings and floors. Wiring requirements differ depending on the construction type
and building element.

Activity 4: Rough Plumbing Installation (First Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping.

Week 25

Activity 1: Second Floor Construction (Tying Rebar for Beam)
Duration: 4 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage
that will reinforce the pour concrete. They are tied together with tie wire at varying
intervals.

Activity 2: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Activity 5: Rough HVAC Installation (First Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed and
run to each location. The furnace is installed as well.

Activity 3: Rough Electrical Installation (First Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members such as the interior walls,
ceilings and floors. Wiring requirements differ depending on the construction type
and building element.

Activity 4: Rough Plumbing Installation (First Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threader,
steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping

Week 26
Activity 1: Second Floor Construction (Setting up formwork for beam)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for beam before pouring the concrete.


Activity 2: Second Floor Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-mounted
hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-mounted
hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the formwork
through pipes and large hoses, vibrate the concrete to increase its strength.

Activity 3: Wall Construction (Ground Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Week 27











Week 28

Activity 1: Second Floor Construction (Beam Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete beam harden for 7 days to wait it
mature and sufficient strength, open formwork after completed

Activity 1: Second Floor Construction (Tying Rebar for Slab)
Duration: 5 days
Materials: rebar ribs, steel cage
Equipment: rebar mesh making machine
Skilled worker: general workers (2)
Technical information: rebar is formed with rebar ribs to contract the steel cage
that will reinforce the pour concrete. They are tied together with tie wire at varying
intervals.

Week 29

Activity 1: Second Floor Construction (Setting up formwork for Slab)
Duration: 2 days
Materials: Plywood, nails
Equipment: hammer, measuring tape, drill, handsaw
Skilled worker: general workers (2), carpenter (1)
Technical information: Set up formwork for slab before pouring the concrete.


Activity 2: Second Construction (Pour concrete into the formwork)
Duration: 2 days
Materials: Concrete grade 30
Equipment: concrete mixer truck, concrete vibrator, pumps and boom-
mounted hoses
Skilled worker: Concrete mixer truck operator (1), pumps and boom-
mounted hoses operator (1), general worker (1)
Technical information: Concrete is pumped and poured into the
formwork through pipes and large hoses, vibrate the concrete to
increase its strength.

Week 30


Activity 2: Staircase Construction (First Floor)
Duration: 6 days
Materials: Plywood, Timber Battens, rebar ribs, steel cage, concrete grade 30
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
Concrete mixer truck, Concrete vibrator
Skilled worker: Carpenter (1), Concrete mixer truck operator (1), general worker (2)
Technical information: Construct formwork by laying out riser heights and tread
widths followed by soffit, joist and stringer lines. Then lay out thickness of risers
from boards. Place rebar as instructed. Pour the concrete into the formwork. Keep
the concrete wet or damp to prevent cracks for up to one week while it cures
Activity 1: Second Floor Construction (Slab Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete slab harden for 7 days to wait it mature
and sufficient strength, open formwork after completed

Week 31


Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Activity 1: Second Floor Construction (Reinforce Column)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for column.
Concrete is pumped and poured into the formwork through pipes and large
hoses, vibrate the concrete to increase its strength.

Week 32
















Activity 1: Second Floor Construction (Column Curing Period)
Duration: 7 days
Materials: -
Equipment: -
Skilled worker: -
Technical information: Let the concrete column harden for 7 days to wait it mature
and sufficient strength, open formwork after completed

Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Week 33















Week 34
Activity 1: Roof Construction (Reinforce Beam)
Duration: 6 days
Materials: rebar ribs, steel cage, concrete grade 30, plywood, nails
Equipment: rebar mesh making machine, hammer, measuring tape, drill, handsaw,
concrete mixer truck, concrete vibrator, pumps and boom-mounted hoses
Skilled worker: general workers (2), carpenter (1), concrete mixer truck operator (1)
Technical information: Place rebar as instructed, position formwork for beam.
Concrete is pumped and poured into the formwork through pipes and large
hoses, vibrate the concrete to increase its strength.

Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Activity 1: Roof Construction
Duration: 6 days
Materials: steel joists, concrete slab, rebar, grout (sand and Portland cement)
Equipment: Concrete mixer truck, concrete vibrator, scaffold, rebar mesh making
machine, pumps and boom-mounted hoses
Skilled worker: concrete mixer truck operator (1), general workers (2)
Technical information: Place the steel joists. The bottom of the steel joists should
rest on either a beam or a wall. This will give it the required support. Place the
concrete slab on its face. Insert full-length rebar to the unit. The grout has to be
poured into the space between the rows of concrete slabs. The joists have to be
covered completely.
Activity 2: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Week 35
Activity 1: Wall Construction (First Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Activity 2: Rough Electrical Installation (Second Floor)
Duration: 4 days
Materials: PVC insulated cable, copper/aluminum conductors
Equipment: Power strip/ surge protectors, fish tape, flex bits
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: After rough frame is completed, wiring methods have to be
installing on or through building framing members. Wiring requirements differ
depending on the construction type and building element.

Activity 4: Rough HVAC Installation (Second Floor)
Duration: 2 days
Materials: Duct HVAC, furnace, service valve adapters,
Equipment: Hand Tool Set, measuring tapes and folding rules, squares, levels,
plumb bobs and chalk lines, ladder
Skilled worker: HVAC installer (1), general worker (1)
Technical information: The ductwork of HVAC system is planned and installed
and run to each location. The furnace is installed as well.

Activity 3: Rough Plumbing Installation (Second Floor)
Duration: 4 days
Materials: cast iron pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings,
hangers, insulating materials, oakum
Equipment: pressure test pump, clamp tool, measuring tape, electric pipe
threader, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe
cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: The major categories of plumbing systems or subsystems
are potable cold and hot tap water supply, plumbing drainage venting, septic
systems, rainwater, surface, and subsurface water drainage, fuel gas piping

Week 36
Activity 2: Ceiling Installation (Ground Floor)
Duration: 3 days
Materials: Ceiling panels, main runners
Equipment: hacksaw, utility knife, measuring tape
Skilled worker: general workers (2)
Technical information: Set the main runners into place. Install the cross tee
sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a
grid opening, then carefully lower it until it rests on the bracket edges of the grid
sections.

Activity 1: Wall Construction (Second Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel
fully embedded in Portland cement grout. The steel angles, can provide all the
support, or be attached to the primary structure such as a reinforced concrete
frame, to which the load is transferred.

Week 37
Activity 1: Wall Construction (Second Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel fully
embedded in Portland cement grout. The steel angles, can provide all the support,
or be attached to the primary structure such as a reinforced concrete frame, to
which the load is transferred.

Activity 2: Ceiling Installation (First Floor)
Duration: 3 days
Materials: Ceiling panels, main runners
Equipment: hacksaw, utility knife, measuring tape
Skilled worker: general workers (2)
Technical information: Set the main runners into place. Install the cross tee
sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a
grid opening, then carefully lower it until it rests on the bracket edges of the grid
sections.

Week 38
Activity 1: Wall Construction (Second Floor)
Duration: 4 days
Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
Equipment: Rose Brick Trowels, carpenter level, brick jointer
Skilled worker: Bricklayers (2)
Technical information: Brickwork process including bricks, beds and
perpends. The bed is made up with mortar with brick is laid. It needs to be
supported over openings the opening are often supporting by reinforcing steel
fully embedded in Portland cement grout. The steel angles, can provide all the
support, or be attached to the primary structure such as a reinforced concrete
frame, to which the load is transferred.

Activity 2: Ceiling Installation (Second Floor)
Duration: 3 days
Materials: Ceiling panels, main runners
Equipment: hacksaw, utility knife, measuring tape
Skilled worker: general workers (2)
Technical information: Set the main runners into place. Install the cross tee
sections of the ceiling grid. Install the panels. Tilt each panel to angle it through a
grid opening, then carefully lower it until it rests on the bracket edges of the grid
sections.

Week 39 - 40
Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.
Activity 2: Finish Electrical
Duration: 3 days
Materials: main electrical panel, receptacle
Equipment: Driller, locknut, screw, nickel/silver, beryllium copper, plastic
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: The panel distributes the electricity to all the electrical
circuits that are installed in the house. Electrician installs receptacles for outlets,
lights and switches and runs wires from the breaker panel to each receptacle.



Activity 3: Finish Plumbing
Duration: 2 days
Materials: Waters taps
Equipment: clamp tool, flaring pliers
Skilled worker: Plumber (1)
Technical information: Water taps are installed to every sink in kitchen and
bathroom, and against exterior wall.

Week 41
Activity 4: Finish HVAC
Duration: 2 days
Materials: Thermostats, Registers
Equipment: Hand Tool Set
Skilled worker: HVAC installer
Technical information: Nearly all of the HVAC work is done during the
rough in stage. The HVAC installer install the thermostats, placed the
registers and made a few final adjustments and tests to make sure that
everything was running properly.

Activity 2: Finish Electrical
Duration: 3 days
Materials: main electrical panel, receptacle
Equipment: Driller, locknut, screw, nickel/silver, beryllium copper, plastic
Skilled worker: Electrical Contractor (1), Electrician (1)
Technical information: The panel distributes the electricity to all the electrical
circuits that are installed in the house. Electrician installs receptacles for outlets,
lights and switches and runs wires from the breaker panel to each receptacle



Activity 3: Finish Plumbing
Duration: 2 days
Materials: Waters taps
Equipment: clamp tool, flaring pliers
Skilled worker: Plumber (1)
Technical information: Water taps are installed to every sink in kitchen and
bathroom, and against exterior wall.
Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.

Week 42 - 43

Activity 2: Bathroom Equipment Installation
Duration: 2 days
Materials: Sockets, Heaters, Showers, Shower pumps, Water closet, Sink, PVC
pipes
Equipment: Clamp tool, measuring tape, steel pipe wrench, flaring pliers, pipe
vice, pipe bending machine, pipe cutter
Skilled worker: Plumber (1), General worker (1)
Technical information: Materials are installed at first fix stage as they need to
be fitted prior to the commencement of tiling. This is essential to get professional
watertight seals, as water ingress resulting from doing things in the wrong order
can cause massive problems later on.


Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.

Week 44

Activity 4: Lighting Installation
Duration: 2 days
Materials: bulbs
Equipment: Screw, screwdriver, driller, locknut
Skilled worker: Electrician (1), general workers (1)
Technical information: Light bulbs are installed in every location.
Activity 3: Kitchen Counters and Cabinets Installation
Duration: 2 days
Materials: Kitchen counters and cabinets
Equipment: Hammer, screw drivers
Skilled worker: general workers (2)
Technical information: Materials are installed at first fix stage as they need to
be fitted prior to the commencement of tiling.

Activity 1: Plastering and Painting of Exterior and Interior Walls
Duration: 8 days
Materials: plaster, mixed blended white cement, coving, paint
Equipment: trowels, floats, hawks, masonry brushes, paintbrushes, ladders,
scaffolds, tape and masking
Skilled worker: Plasterer (2), Pointing, cleaning, and caulking workers (1),
painter (1)
Technical information: Plastering on the surface of brick wall after cleaning
with masonry brush. Then, scratch first coat of render before it set to provide
key for second layer. Wall painting with color chosen.

Week 45 - 46
Activity 1: Windows, Doors and Railings Installation
Duration: 10 days
Materials: Windows, backer rod, insulation, shims, roofing nails, screws, silicone
sealant, flashing, fastener, corner guard, doors, door lock, doorknob and screws,
railings.
Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding,
square ruler, measuring tape, stapler, and screwdriver
Skilled worker: carpenter (2), general worker (1)
Technical information: Verify window opening, apply weather resistant barrier,
create flashing, prepare window for installation, set the unit and secure, apply
flashing at jambs and head, seal and insulate interior cavity, insert backer rod.
Install required door types and measurement with door lock and doorknob.
Install railings.

Week 47 – 48







Week 49 – 50

Week 51
Activity 1: Cleaning Up
Duration: 8 days
Materials: -
Equipment: Vacuum, broom, skip
Skilled worker: general workers (2)
Technical information: -

Activity 1: Test and Commissioning
Duration: 6 days
Materials: -
Equipment: -
Skilled worker: Commissioning agent (CA),
Technical information: Review design intent and basis of design documentation
(prepared by others). Assist with incorporation of commissioning requirements into
the construction documents. Develop a commissioning plan and assist with its
utilization. Verify installation, functional performance, training and operation and
maintenance documentation. Prepare commissioning report and related systems
documentation.
Activity 2: Final Inspection
Duration: 2 days
Materials: -
Equipment: -
Skilled worker: Final Inspector (professional engineer)
Technical information: Turn on and off every light fixture, run water & look under
sinks for leaks, test all appliances, check garage door openers, open and close all
doors, flush toilets, inspect ceilings, wall and floors, run garbage disposal and
exhaust fans, test heating and air conditioning, open and close windows, make
sure all debris is removed from the home

Activity 1: Hand Over
Duration: 2 days
Materials: -
Equipment: -
Skilled worker: Builder’s representative, accountant
Technical information: Take client on a tour of the home showing how everything
works and what have to do to maintain the new home, with a copy of all relevant
warranties and certificates arising from the contract. Final payment will be made.

Week 52
Activity 1: Move in Furniture
Duration: 3 days
Materials: -
Equipment: -
Skilled worker: general workers (3)
Technical information: -