You can access a historical PowerPoint presentation on Contractor Past Performance Rating from 2014, detailing scoring systems, bidding capacity, and performance evaluation frameworks relevant for September 2014.
መድረስ የሚጠበቅበት ሲሆን፡
t
1
= (Elapsed time in months minus mobilization time in months)
(One third of the contract period in months minus mobilization time in months)
t =
የተያዘውን የግንባታ ፕሮጀክት ገንብቶ ለማጠናቀቅ በውል የተያዘለትን ጊዜ ይወክላል፣
መድረስየሚጠበቅበት
11+29t2
መሰረትተሰልቶከሚገኝውጤትላይሲሆን፡
t2 = (Elapsed time in months minus One third of the contract period in months)
(One third of the contract period in months)
t
2 = = (
ውሉ ከተያዘበት ቀን ጀምሮ ያለፈው ወራት ብዛት
-
በውል የተያዘው
1/3
ኛ ወራት
)
የሚጠበቅበት
38+32t3
መሰረትተሰልቶከሚገኝውጤትላይሲሆን፡
t3 = (Elapsed time in months minus 2 X One third of the contract period in
months)
(One third of the contract period in months)
t 3 = (
ውሉከተያዘበትቀንጀምሮያለፈውወራት
- 2 x
የውሉ
1/3
ኛውወራት
)
ተሰልቶከሚገኝውጤትላይሲሆን፡
t4 = (Elapsed time in months minus contract period in months)
(One fourth of the contract period in months)
t 4 = (
ውሉ ከተያዘበት ቀን ጀምሮ ያለፈው ወራት
-
አጠቃላይ በውሉ የተያዘው ጊዜ በወራት
)