FABRICATION ROOFING & SIDING PROGRESS CUT OFF AUGUST 2024 ANU PROJECT 99 th INTERNAL WEEKLY MEETING
ISSUES Delayed Production Roofing & Siding Fabrication Delayed Raw Material delivery from overseas Workshop cannot produce material as per planned Proposed Solutions
Outstanding 18000 m2 To be completed until the end of the year Proposed Recovery Plan PROGRESS STATUS
POTENTIAL SOLUTIONS Inc rease Productivity (Night Shift & Weekend) Pros : Cost Efficiency Direct Monitoring Cons : Uncertain Production Capacity Narrow Storage Area Using Third Party additional workshop Pros : Certain Production Capacity Dedicated Storage Area Cons : Indirect Monitoring Additional Cost