REVIEW MONTHLY Penambangan Internal ( PIT B2 & B1) Periode : Februari 2025
Lembar Persetujuan Review & Monthly Plan Ragil Setyo / M. Irfan Dinda Mine Plan Dadang Hermanto Dept. Head Engineerin g Nurdian Elnandi Engineering Spt. A mron Lumban Raja Production. Spv Rudyanto Pangaribuan Dept. Head Production Engineering Department, Production Department,
Review Pencapaian Produksi ( Truckcount ) MTD 1-28 Februari 2025
Waterfall ( Truckcount ) MTD 1-28 Februari 2025
Review Productivity & Cost (MTD 26 Februari 2025)
Review Productivity (MTD 28 Februari 2025)
MONTHLY PLAN Penambangan Internal PIT B1, B2 & B5B36 Periode : Maret 2025
RL+70 Plan : P1 Expose seam S RL +64 (Lowwest Point) P2 Expose seam S RL+70 P3 Stripping/Expose seam R RL+70 Distance : IPD B1WA : 800-1.000 m Utilitation : Digger : 3 x Exc 40T Hauler : 14 x DT 10T Support : 2 x D85 Support Front & Disposal 1 x Exc 20T CG & General Dewatering : 1 x Pompa Transfer 1 x 200 m Hose line ke Void Utara Sequence PIT B1 (B1WA/R) P3 Lowwest Point P1 Foto Udara 3 Feb 2025 RL+ 64 Disposal P2
Seg - 19 Seg - 21 P2 Seg - 22 Seg - 23 Seg - 24 Seg - 25 Boundary PIT Boundary Disposal Sequence & Section PIT B1 (B1WA/R) Keterangan Section : Geology Model Situasi 22 -Feb -25 Plan Mar Topo Void P1 P3 Seg - 26 Seg - 27 RL+132 RL+133 RL+64 RL+70 Dumping Soft Material (Jarak 1.000 m) Dumping OB Kering (Jarak 700 m) Lowwest Point
P1 RL+20 Foto Udara 3 Feb 2025 Plan : P1 Stripping/ Expose seam 42 RL+20 P2 Stripping Roof/Floor RL+20 Distance : IPD 5B21 : 1.00 m Utilitation : Digger : 2 x Exc 40T Hauler : 10 x DT 10T Support : 1 x D85 Support Front & Disposal 1 x Exc 20T CG & General Dewatering : - Sequence PIT B5 (B5B36/42) Water Level 22 .3 P2 LINE-A Dumping OB (IPD B5B21/Join MPT) (Jarak 1.000 m)
Seg - 19 Seg - 7 P2 Seg - 8 Seg - 9 Seg - 10 Boundary PIT Boundary Disposal Sequence & Section PIT B5 (B5B36/42) Keterangan Section : Geology Model Situasi 22 -Feb -25 Plan Mar Topo Void P1 Seg - 11 Seg - 12 RL+ 20 Dumping OB (IPD B5B21/Join MPT) (Jarak 1.000 m)
P1 Plan : P1 Expose seam C4B RL+ 48 P2 Stripping/ Expose seam C4B RL+ 42 Distance : IPD B2A Selatan : 500 m Utilitation : Digger : 2 x Exc 40T Hauler : 6 x DT 10T Support : 1 x D85 Support Front & Disposal 1 x D375 Support Ripping 1 x Exc 20T CG & General Dewatering : 2 x MF150-65 ( Pompa Utama) 2 x 500 m HDPE line Pumping to SP-8B 1 x Pom pa Transfer Sequence PIT B2 (B2A/D) MPG-39 Water Level 52.9 P2 MPG-40 Foto Udara 3 Feb 2025 Dumping OB (Void Selatan) (Jarak 500 m) Dumping OB Jika DT Kurang (Jarak 300 m) RL+48 RL+48 RL+42 RL+70
Sequence & Section PIT B2 (B2A/D) Seg - 20 Seg - 18 Seg - 17 Seg - 16 Seg - 26 Seg - 27 Seg - 28 Seg - 24 Seg - 25 P1 Boundary PIT Boundary Disposal P2 Keterangan Section : Geology Model Situasi 22 -Feb -25 Plan Mar Topo Void RL+70 RL+60 RL+48 RL+48 RL+42 Water Level 52.9 RL+75 Dumping OB DT Mencukupi (Jarak 500 m) Dumping OB Jika DT Kurang (Jarak 300 m)
Key Points Mine Plan Maret 2025 3 x Exc 40 Ton running di PIT B1 (B1WA/R) dengan target coal product TMU40 minimal 18k MT; Week pertama s/d week ke-2 2x Exc 40 Ton running di PIT B5B36 dengan target coal product TMU42 minimal 3 k MT; Week ke-4 s/d EOM 2x Exc 40 Ton running di PIT B2 (B2A/D) dengan target coal product TMU52 minimal 6 k MT; Total target coal bulan Maret adalah 27k MT, SR Kumulatif 12,01 Dewatering : 1xMPG12 running di 5B21/B5B36 2xMPG39& MPG 40 running di PIT B2 (B2A/D) 1xPompa Transfer running di PIT B1 (B1WA/R)