EL ARTE DEL P&ID y algo mas de artes PDF

FernandaGarca788912 37 views 94 slides Apr 25, 2024
Slide 1
Slide 1 of 94
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62
Slide 63
63
Slide 64
64
Slide 65
65
Slide 66
66
Slide 67
67
Slide 68
68
Slide 69
69
Slide 70
70
Slide 71
71
Slide 72
72
Slide 73
73
Slide 74
74
Slide 75
75
Slide 76
76
Slide 77
77
Slide 78
78
Slide 79
79
Slide 80
80
Slide 81
81
Slide 82
82
Slide 83
83
Slide 84
84
Slide 85
85
Slide 86
86
Slide 87
87
Slide 88
88
Slide 89
89
Slide 90
90
Slide 91
91
Slide 92
92
Slide 93
93
Slide 94
94

About This Presentation

EL ARTE DEL P&ID.pdf


Slide Content

Art Of The
P&ID
1Ford, Bacon & Davis, LLC

•Piping And Instrument Diagram (P&ID) Is A
Schematic Diagram That Shows How
Equipment And Instruments Connect To Form
A Functional Process System
•The P&IDIs The Chief Control Document For
The Engineering Design Of Petrochemical And
Refinery Systems
Ford, Bacon & Davis, LLC 2

•Defines Scope
•Specifies Systems
•Identifies Essential Components
•Guides Engineering Design
•Tracks Changes
•Assists Construction
•Trains Operators
•Meets PSI Requirements
Ford, Bacon & Davis, LLC 3

Component Function
Equipment Convert
Instruments Control
Pipe Connect
Convey
Ford, Bacon & Davis, LLC 4

•EquipmentIs Shown With Symbols That
Represent Different Types Of Equipment
–Columns
–Heat Exchangers
–Pressure Vessels
–Pumps
–Tanks
5Ford, Bacon & Davis, LLC

•InstrumentsAre Shown With Symbols That
Represent Inline Or Attached Devices That
Measure Or Control The Process
–Analyzers
–Control Valves
–Flow Meters
–Local Indicators
–Software Elements
–Transmitters 6Ford, Bacon & Davis, LLC

•PipingBetween Equipment Is Shown As Lines
With Special Symbols For Piping Components
–Expansion Joints
–Insulation / Heat Tracing
–Flanges
–Reducers
–Specialty Pipe Items
–Valves
Ford, Bacon & Davis, LLC 7

•Signals Between Instruments Are Also Shown
As Lines, Usually Dashed Or With Special
Symbols
–Hard Wired Links
–Hydraulic Connections
–Pneumatic Connections
–Software Links
Ford, Bacon & Davis, LLC 8

•Locate The ROAD MAP
•Standardize On FORMAT
•LAYOUTFor Clarity
•ANALYZEContent for Accuracy
•AUDITFor Completeness
•CHECKFor Consistency
Ford, Bacon & Davis, LLC 9

Locate The
ROAD MAP
10Ford, Bacon & Davis, LLC

•Finalize P&ID Legends & Symbols Early
–Use Client Standard If Available
–Copy From Previous Client Project
–Develop For New Project & Get Client Approval
•Use PIP PIC001 P&ID Documentation Criteria
As Default
•Legends & Symbols Should Match CADD
Drafting Symbology
Ford, Bacon & Davis, LLC 11

•Use P&ID Kickoff Meeting(s) For Project Team
Review And Consensus
–P&ID Symbology / Layout
–Execution Plan
–Management Of Change
•Follow P&ID Quality Assurance Matrix And
P&ID Completeness Checklist For Each Stage
Of P&ID Development
Ford, Bacon & Davis, LLC 12

•Abbreviations
•Equipment Symbols
•Instrument Symbols
•Pipe Symbols
•Keys For Equipment, Instrument, & Pipe
Numbering
•Standard Details
Ford, Bacon & Davis, LLC 13

Ford, Bacon & Davis, LLC 14

Ford, Bacon & Davis, LLC 15

Ford, Bacon & Davis, LLC 16

Ford, Bacon & Davis, LLC 17

Ford, Bacon & Davis, LLC 18

Ford, Bacon & Davis, LLC 19

Ford, Bacon & Davis, LLC 20

Ford, Bacon & Davis, LLC 21

•Tag Numbers For Equipment
–Letter Code For Equipment Type
–Number For Specific Identification
Ford, Bacon & Davis, LLC 22

Function Type
Exchange Heat CT = Cooling Tower
FH = Fired Heater
HE = HeatExchanger (Shell & Tube)
RU = Refrigeration Unit
Move Fluid K = Blower/Fan/Compressor
EJ= Eductor/Ejector
P =Pump
ReactComponents FL= Flare
RX = Reactor (CatalystBed, Furnace)
Separate Components C = Column
F = Filter
Store Fluid D = Drum
TK= Tank
Ford, Bacon & Davis, LLC 23

•Loop Numbers For Instruments (ISA Typical)
–Letter Code For Instrument Function
–Letter Code For Instrument Type
–Number For Specific Identification
Ford, Bacon & Davis, LLC 24

Function Type
A= Analyze C = Controller
F = Flow E= Element
L = Level I = Indicator
P = Pressure T = Transmitter
T = Temperature V = Valve
Ford, Bacon & Davis, LLC 25

•Line Numbers For Piping
–Pipe Size
–Process Or Utility Service Code
–Number For Specific Identification
–Pipe Specification
–Insulation Type
–Insulation Thickness
–Heat Tracing Requirement
Ford, Bacon & Davis, LLC 26

•Specialty Item Numbers For Special Pipe
Components Not Addressed In Pipe
Specifications
•Tie Point Numbers
•Sample Connection Numbers
•Valve Specification Numbers
Ford, Bacon & Davis, LLC 27

Ford, Bacon & Davis, LLC 28

Standardize On
FORMAT
29Ford, Bacon & Davis, LLC

Ford, Bacon & Davis, LLC 30
Drawing
Title Block
Revision
Log
Notes
Reference
Drawings
List
Incoming
Stream
Arrows
Outgoing
Stream
Arrows
Stationary Equipment Title Blocks
Rotating Equipment Title Blocks
Stationary Equipment Symbols
Rotating Equipment Symbols
Upper Pipe Highway
Lower Pipe Highway
Border

Ford, Bacon & Davis, LLC 31

Ford, Bacon & Davis, LLC 32

Ford, Bacon & Davis, LLC 33

Ford, Bacon & Davis, LLC 34

Ford, Bacon & Davis, LLC 35

Ford, Bacon & Davis, LLC 36

Ford, Bacon & Davis, LLC 37

Ford, Bacon & Davis, LLC 38

Ford, Bacon & Davis, LLC 39

Ford, Bacon & Davis, LLC 40

Ford, Bacon & Davis, LLC 41

Ford, Bacon & Davis, LLC 42

•P&ID Drafting Procedure (Client)
•Drawing Size
•Borders
•Drawing Title Block
•Equipment Title Blocks
•Layers
•Line Weights
•Fonts
Ford, Bacon & Davis, LLC 43

•Standard P&ID Drawing Size Is ANSI D Which Is
22” High By 34” Wide
•11” X 17” Size (ANSI B) Is Typically Used For
Reference Is A Reduction Of The Standard Size
Ford, Bacon & Davis, LLC 44

•Identifies Boundary Of Drawing Content
•Spacing Between Edge Of Drawing And Border
To Allow For Copy Misalignment
•Thickness Of Border Line May Vary
•Drawing File Name Usually Outside Of Border
Ford, Bacon & Davis, LLC 45

•Client Name And Logo
•Location
•Drawing Subject Information
•Drawing Number
•Revision Number
•General Drafting Information
•Revision Description
Ford, Bacon & Davis, LLC 46

Ford, Bacon & Davis, LLC 47

•First Line: Plant Or Unit Or Project
•Second Line: Type Of Drawing
–Piping & Instrument Diagram
–Process Flow Diagram
–Process Block Diagram
•Third Line: Process Section Of Plant Or Unit
•Fourth Line: Key Equipment Description
Ford, Bacon & Davis, LLC 48

•Client Usually Has Specific System For
Numbering Drawings
•Typical Drawing Number Format
–Drawing Size Designator
–Plant/Unit/Process Section Designator
–Type Of Drawing Designator
–Sequential Drawing Number
Ford, Bacon & Davis, LLC 49

•Example: D- 1015-G-00233
•D = Drawing Size (22” X 34”)
•1015 = Unit Number
•G = Flow Diagram
•00233 = Sequential Number
Ford, Bacon & Davis, LLC 50

•Drawings For A Project Are Generally Issued At
Different Stages Of Development
•Each Stage More Complete Than The Preceding
Stage
•Typical Stages:
–Issue For Client Comment (IFCC) Or Preliminary Issue
–Issue For Approval (IFA)
–Issue For Design (IFD)
–Issue For Construction (IFC)
–Issue For Record (IFR)
Ford, Bacon & Davis, LLC 51

•New Drawing Will Carry a Revision Letter A, B, C,
Etc. During Preliminary, Approval, and Design
Issues
•Drawing is Typically Issued For Construction As
Revision 0 (Zero)
•Any Further Revisions Carry Revision Numbers (1,
2, 3, Etc.)
•Revision Description For New Drawing Will Use
Issue Description (IFCC, IFA, IFD, IFC, IFR)
Ford, Bacon & Davis, LLC 52

•Existing Drawing Revised For A Project Will Carry The
Next Revision Number Followed By A Letter A, B, C, Etc.
During Preliminary, Approval, And Design Issues
•When The Drawing Is Issued For Construction, The
Letter Designation Is Dropped From The Revision
Number
•The Revision Description For A Revised Drawing Will
Typically Use The Project Title Along With
Development Stage (IFCC, IFA, IFD, IFC, IFR)
Ford, Bacon & Davis, LLC 53

•Select Meaningful Drawing Titles
•Update Drawing Titles As P&ID Content
Changes
•Keep Revision Log Up To Date
Ford, Bacon & Davis, LLC 54

LAYOUT
For Clarity
55Ford, Bacon & Davis, LLC

•P&IDs Are Conceptual Drawings
•However, Presentation Should Reflect Reality
As Much As Possible
•Pipers’ Trap:
–Why Didn’t You Design It Like The P&ID?
–The P&ID Is A Conceptual Drawing!
–Why Did You Design It This Way?
–I Designed It Just Like The P&ID Showed It!
Ford, Bacon & Davis, LLC 56

Ford, Bacon & Davis, LLC 57
GRAVITY FLOW

Ford, Bacon & Davis, LLC 58
GRAVITY FLOW

Ford, Bacon & Davis, LLC 59

Ford, Bacon & Davis, LLC 60

Ford, Bacon & Davis, LLC 61

Ford, Bacon & Davis, LLC 62

•Develop A Preliminary P&ID List Based On PFD
Review
•Assign Which Equipment Goes On Each
Drawing
•Minimize Drawing Density
•Leave Room For Other Disciplines To Add Their
Symbology And Tags
Ford, Bacon & Davis, LLC 63

Equipment Number Of Items On One P&ID
Columns 1
Compressors 1 (Complex)
FiredHeaters 1
Packaging Equipment CompleteSystem If Possible
Pressure Vessels Feed –1 to 2
Reflux -1 (IncludeWith Condenser)
Storage–1 to 2
Pumps Include WithRelated Equipment (Suction)
Tanks 1to 2
Ford, Bacon & Davis, LLC 64

Ford, Bacon & Davis, LLC 65

Ford, Bacon & Davis, LLC 66

Ford, Bacon & Davis, LLC 67

Ford, Bacon & Davis, LLC 68

Ford, Bacon & Davis, LLC 69

Ford, Bacon & Davis, LLC 70

Ford, Bacon & Davis, LLC 71

ANALYZE
Content For Accuracy
72Ford, Bacon & Davis, LLC

•Standardize On Unit Operation Configurations
•Use P&ID Checklists To Validate Content
•Build Set Of Archive P&IDs For Reference
Ford, Bacon & Davis, LLC 73

Ford, Bacon & Davis, LLC 74

Ford, Bacon & Davis, LLC 75

Ford, Bacon & Davis, LLC 76

Ford, Bacon & Davis, LLC 77

Ejectors Instruments
Equipment Title Blocks Pipe
Fired Heaters Pressure Vessels
Flares Rotating Equipment
Heat Exchangers Storage Tanks
Ford, Bacon & Davis, LLC 78

Ford, Bacon & Davis, LLC 79

Ford, Bacon & Davis, LLC 80

Ford, Bacon & Davis, LLC 81

Ford, Bacon & Davis, LLC 82

AUDIT
For Completeness
83Ford, Bacon & Davis, LLC

•Each Issue Of P&ID Builds On The One Before
•Use P&ID Completeness Checklist To Validate
Completeness For Each Stage Of P&ID
Development
•When Appropriate, Use HOLD Clouds To Flag
Incomplete or Preliminary Information
Ford, Bacon & Davis, LLC 84

Ford, Bacon & Davis, LLC 85
PRELIMINARY ISSUE
EQUIPMENT WITH TAG NO. / TITLE
PRIMARY PIPE
LINE SIZES
SERVICE CODES
PIPE SPECS
KEY PROCESS VALVES
PRIMARY INSTRUMENT LOOP ELEMENTS
PRIMARY RELIEF VALVES
COMPLETE P&ID LEGENDS/SYMBOLS SHEETS

Ford, Bacon & Davis, LLC 86
PRELIMINARY ISSUE
ISSUE FOR APPROVAL
ALL EQUIPMENT DETAILS / TITLE BLOCKS
ALL PIPE SHOWN (PRIMARY / SECONDARY)
PIPE DETAILS
INSULATION / TRACING
PIPE SPECIALTY ITEMS
ALL VALVES SHOWN (TYPES IDENTIFIED)
COMPLETE INSTRUMENT LOOPS
MOTOR CONTROLS
ALL SPECIAL NOTATIONS COMPLETE
ALL RELIEF VALVES SHOWN

Ford, Bacon & Davis, LLC 87
PRELIMINARY ISSUE
ISSUE FOR APPROVAL
ISSUE FOR DESIGN
ALL DESIGN DETAILS COMPLETE
PIPE TAG NUMBERS COMPLETE
LINE NUMBERS
PIPE SPECIALTY ITEM NUMBERS
TIE POINT NUMBERS
ALL VALVE SIZES / TAGS COMPLETE
ALL INSTRUMENT NUMBERS COMPLETE
ALL LOGIC / INTERLOCKS DEPICTED
HOLDS SHOWN FOR INCOMPLETE ITEMS
ALL RELIEF DEVICES SIZES COMPLETE

Ford, Bacon & Davis, LLC 88

CHECK
For Consistency
89Ford, Bacon & Davis, LLC

•Perform Stream Arrow Cross-Checks Between
P&IDs
•Conduct Process Team Reviews
•Conduct Interdisciplinary Team Reviews
•Implement Team Reviews Per P&ID Quality
Assurance Matrix
Ford, Bacon & Davis, LLC 90

Ford, Bacon & Davis, LLC 91

•If More Than One Team Member Is Assigned
P&ID Development, Process Lead Should
Routinely Review All Drawings For
Presentation Consistency
•Use Peer Review For Completeness Checks
•Use Expertise Review For Complex Or
Specialty Systems
Ford, Bacon & Davis, LLC 92

Ford, Bacon & Davis, LLC 93
IDENTIFY
NEEDED DISCIPLINES
OBTAIN
PROJECT / LEAD SUPPORT
SET UP MEETING
PLACES / TIMES
VERIFY ADEQUATE
MEETING SPACE
ISSUE
REVIEW COPIES
EARLY
HAVE SUPPORT
CONTROL DOCUMENTS
AVAILABLE:
LINE LIST
INSTRUMENT INDEX
IN MEETINGS:
HIGHLIGHT COMPONENTS
AS REVIEWED
MAINTAIN MASTER
MARKUP SET
PLAN
FOLLOW UP
REVIEWS
AS REQUIRED

Ford, Bacon & Davis, LLC 94
Locate The ROAD MAP P&ID Legends & Symbols
Standardize On
FORMAT
LAYOUTFor Clarity
ANALYZEContent for
Accuracy
AUDITFor
Completeness
CHECKFor
Consistency
Arrange Drawing Building Blocks Effectively
Don’t Crowd P&IDs
Develop Standard Configurations & Duplicate
Use P&ID Completeness Checklist
Use Interdisciplinary Review Teams