Foundry Park
Ranihati-Amta Road, Howrah, West Bengal
developed by
Foundry Cluster Development Association
Department of MSME&T, Govt. of West Bengal
Nodal Organization:WBSIDCL
State Approved Industrial Park (SAIP)
State Approved Industrial Park (SAIP)
LOCATED IN :-
HAULIBAGAN
SAMANTI, JALABISWANATHPUR & SUVARAH
MOUZA), HOWRAH DISTRICT, WEST BENGAL
SITE POTENTIAL :-
THE SITE IS LOCATED IN THE HEART OF
FOUNDRY INDUSTRY IN EASTERN INDIA
THE APPROACH TO SITE IS FROM HOWRAH-
AMTA ROAD CONNECTED TO NH-6
Site Location
RegisteredunderSection8ofCompaniesActon29
th
March,2005withapprovalofWBIDC
andWBPCB.
ProjectbeingimplementedwithpartialgrantforinfrastructuraldevelopmentfromGovt.
ofIndiaundertheIndustrialInfrastructureUpgradationScheme(IIUS),Departmentof
PromotionofIndustryandInternalTrade(DPIIT),MinistryofCommerce&Industry,GoI.
StateGovthasalsocontributedbywayofsettingupofSTPandupgradationoflocal
sewarageanddrainagesystem
Phase-Iofaround600acreswith150foundriesandalliedunitstobeaccommodated.Total
areaoftheprojectenvisagedis924acres
About Foundry Park
ProjectFeature Information
TotalNumberofUnitsPlannedFoundryUnits:
100nos.intotalin600acres
Allied(Coremaking,patternmaking,fettling,painting,fabrication
andmachiningshops,rawmaterialbanksetc.):50nos.
TotalEnvisagedCastingsOutputByendof5
th
yearofCommercialOperations:5lakhtonnesper
annum.
TotalEnvisagedInvestmentby
FoundryUnits
Rs.2500crores
Employment Potential Direct Employment: 10,000 people (approx.)
Indirect Employment: 30,000 people
About Foundry Park
Land Parcel for LTS Coverage
SlNoMajorItems of Work Scope
1 ROAD WORK 11840 M
2 STORM WATER DRAIN WORK 18225 M
3 EXTERNAL WATER SUPPLY WORK 13000 M
4 WATER WORKS
UGR 3 nos
OHT 3 nos
PH 3 nos
TUBE WELLS 4 nos
5 SEWER NETWORK 12800 M
6 POWER DISTRIBUTION SYSTEM 33/11kv substation 2 nos
Major Scope of Work
7Common Facility Buildings
IT I building
Testinglaboratory & Tool room building
Information,Marketing, HRD & Management upgradationcentre
Pumphouse & its UGR for CFB units
Sub-station building for CFB units
Boundary wall around CFB units
Stakeholders Contribution
Contribution from
Govt. of West Bengal
Grant from
Department of Promotion of Industry and
Internal Trade (DPIIT) Govt. of India
TotalProjectCost
Rs 95.02 Cr
1.129 plots already allotted to stakeholders all from MSME
sector
2.34 nosstakeholders have started factory construction
activities out of which 9 noshave started production after
obtaining all statutory clearances
3.Foundries and units manufacturing Light Engineering
Products are being set up
Plot Status
Status of approvals of Foundry Park under SAIP
‘FinalApproval’infavourofFoundryParkwasaccordedon20.04.2022.
Nowhehasrequestedforforthereleaseof‘1
st
installmentofIncentives’
ofthesaidIndustrialPark.
Checklist according to parameter for 1
st
Incentive payment
Sl
No
Criteria as per guideline Comments of PMU, WBSIDCL
1Mutation,conversion®istrationof
thelandinSPV’sname
Mutationhasalreadybeendonefortotallandsbutconversionis
yettobedone.Italsoattractsthememono.796-GE(M)/3M-
68/11;dated25.02.2021.
2FormationoftheSPVandobtaining
finalapprovaloftheAIPfromthe
SLEC
SPValreadyformedandobtainedfinalapprovaloftheAIPfrom
theSLECon20.04.2022.
ThisParkhasbeenvisitedon14thJuly,2022bythePMUTeamofWBSIDCLinpresenceofMr.Mukul
Maity,SiteEngineer,FoundryClusterDevelopmentAssociationalongwithhisteamandafter
inspection&checkingoftheprojectithasbeenfoundthatallbasicandessentialinfrastructures
havebeencompletedasperSAIP2020Guidelinebut,theSPVhasdevelopedtheParkwiththe
assistanceofGovernmentfunds.
AccordinglyWBSIDCLhasnotrecommendedforreleaseof‘incentive’infavourofFoundry
Park.SPVhasalsoappliedforreimbursementofstampdutyandregistrationfeesandthe
reimbursementofsaidfeeshasbeenrecommended.
….cont’d
Sl Criteria as per
guideline
Comments of PMU, WBSIDCL
3Completion of
constructionofBoundary
Wall,Landfillingand
InternalRoads
Land filling Work is almost completed (95%).
The total length of Boundary Wall executed at site is 3400m (approx). So the
Construction of Boundary Wall is almost completed.
Internal Road Work has been completed and the total length of about 7760m. As
informed by FCDA, total thickness of the internal road is 580mm consisting of
230mm GSB, 250mm WMM, 60mm DBM & 40mm BC. Two (02) nosCulvert have been
constructed.
Drainage System is done comprises with RCC Wall and the total length of about
7760m. Many portions of drain are choked & damaged. Irrigation Deptthas
initiated the work of improvement of drainage congestion. Copy of all documents
relating to KMDA work is attached.
Regarding Electric Connection, FCDA informed WBSEDCL will set up a 220KVA
substations from which power will be drawn for the project by two 33KVA
substations. Twenty Four (24) nosStreet Light have been installed along the road.
Setting up of 0.80MLD CETP is under going on at the end of KMDA.
Vivekananda Industrial Training Institute
Collaborated with PaschimBangaSociety of Skill Development (PBSSD)
under the aegis of Ministry of Technical Education & Skill Development,
Govt. of West Bengal for:
Foundry courses including Melting, Mouldingand Core making.
Theoretical Class Practical Training Class Hostel facility for Students
Library & reading Room
Administrative Office
Conference Room with Projector
Infrastructure
Facilities in Training
Institute