Formwork Installation Pointers and Inspection Guide


Slide Content

GETO Aluminium Formwork System – Installation, Inspection, and Safety Guide Training for Construction Workers Prepared by: ___________ Date: ___________

Overview What is GETO Formwork System? Why use aluminium formwork: Speed, quality, reusability, reduced plastering.

Main Components Wall panels Beam forms Slab panels Corner panels Props and accessories (pins, wedges, ties)

Preparation Before Installation Check layout lines and levels Inspect panels and hardware Clean slab surface Ensure all workers wear proper PPE

Step 1: Wall Panel Installation Start from corners or wall junctions Fix panels with pins and wedges Insert wall ties through tie holes Check verticality using plumb bob or level

Step 2: Beam and Slab Setup Install beam sides and bottoms Place slab panels on props Adjust height and level using jacks or adjustable props

Step 3: Accessories & Embedded Items Apply release agent lightly on panel surfaces Install embedded conduits, sleeves, or boxes Check tightness and alignment

Step 4: Concreting Operations Pour concrete evenly and layer by layer Use vibrator to remove air pockets Avoid overfilling to prevent deformation

Step 5: Dismantling Remove wall panels after 18–24 hours Remove slabs after 3–5 days (with re-propping) Clean panels immediately after removal