handling 2020 CTPRODUCTION CONCRETE .pptx

ssuser92e250 39 views 90 slides Sep 27, 2024
Slide 1
Slide 1 of 90
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57
Slide 58
58
Slide 59
59
Slide 60
60
Slide 61
61
Slide 62
62
Slide 63
63
Slide 64
64
Slide 65
65
Slide 66
66
Slide 67
67
Slide 68
68
Slide 69
69
Slide 70
70
Slide 71
71
Slide 72
72
Slide 73
73
Slide 74
74
Slide 75
75
Slide 76
76
Slide 77
77
Slide 78
78
Slide 79
79
Slide 80
80
Slide 81
81
Slide 82
82
Slide 83
83
Slide 84
84
Slide 85
85
Slide 86
86
Slide 87
87
Slide 88
88
Slide 89
89
Slide 90
90

About This Presentation

handling 2020 CTPRODUCTION CONCRETE .pptx


Slide Content

Department of Civil Engineering 1 Concrete Handling in Field By: Nishant Singh Kushwaha Subject Code: 4CE4-08

Concrete Handling in field This Powerpoint presentation covers entire unit of Concrete handling in field . Most of the material covers in this ppt and rest if left please refer to M.S Shetty book.

Stages of producing concrete. 3 Batching Mixing Transportation Placing Compacting Curing Finishing

(1) Batching 4 Volume batching weight Baching

Volume batching 5 Volume batching is not good method Moist sand in loose condition weights less than the same volume of dry sand. Practiced for small work. For quality work ,weigh batching is practiced.

VOLUME BATCH Gauge box Various gauge boxes of different volumes are used. 6 Length Width Depth Volume 33.3 cm 30 cm 20 cm 20 liters 33.3 cm 30 cm 25 cm 25 liters Grade Cement- kg Sand -lts Coarse A g g r e gate lts 1:11/2:3 (M 200) 50 35 70 1:2:4 (M 150) 50 70 140 1:3:6 (M100) 50 105 210

Weigh Batch Machine 7

Weigh batching 8 Weigh batching is correct method Facilitates accuracy, flexibility & simplicity Different batching machine are available : manual machines & (b) Automatic machines Manual machine : Has two buckets Buckets mounted on common spindle about which they rotate. One is loaded while other is discharged in mixer. Spring loaded dials indicate the weight.

Automatic weigh batch 9 For large works Over head hopper and discharges into mixer. Useful in ready mix concrete plant Recorders for weight Calibration is required from time to time.

(2) MIXING 10 Mixing of cement,sand aggregates should ensure that: The mass is homogeneous Uniform in color consistent

MIXING METHODS : Hand mixing Machine mixing 11

Hand mixing Practiced for small scale work (small house, repairing of house etc) 10 % extra cement is added to compensate inferior concrete produced by this method. Spread fine & coarse aggregate in alternate layer Spread cement over it Mix with shovel till uniform color is achieved

Machine mixing 13 Medium & large scale work use machine mixing Mixing is efficient, economical & produce quality concrete. Type of mixer: Batch mixer : batch by batch with time interval Continuous mixer: continuously mixed & discharged (in dam construction)

CONCRETE MIXER 14 Pan type drum Type: tilting Non –tilting Reversing

PAN MIXER 15

PAN MIXER 16 A forced movement pan mixer has blades that are fixed to an assembly that agitates the concrete throughout the pan as the vertical shaft rotates.

DRUM MIXER 17 As per IS: 1791-1985 mixers are designated by number which shows capacity (liters) of batch: a) Tilting : 85 T, 100T, 140 T, 200T b) Non tilting : 200 NT,280 NT, 375 NT, 500 NT, 1000 R c) Reversing : 200 R, 280 R, 375 R,500 R, 1000 R T= Tilting, NT =non tilting, R=Reversing

TILTING MIXER 18

TILTING MIXER 19 Internal blades lift and tumble the ingredients onto itself. Two primary types exist: horizontal (one end has and opening for charging and a different end for discharging) single drum (materials are charged and discharged through a single opening).

NON TILTING MIXER 20

NON TILTING MIXER 21 Single drum rotating about a horizontal axis. Fixed blades work the concrete towards the discharge end of the mixer, in order to provide a rapid rate of discharge.

REVERSING MIXER 22

REVERSING MIXER 23 The entire drum rotates around its axis as materials are loaded through a charge chute at one end of the drum and exit through a discharge chute at the opposite end of the drum. Mixing blades are mounted on the inside surface of the drum and as the drum rotates the blades mix by lifting and dropping the materials during each rotation. Once the materials are sufficiently mixed the rotation of the drum is reversed and the blade arrangement pushes the concrete through to the discharge end of the mixer.

Sequence of charging drum 24 First half quantity of coarse aggregate is placed in skip Over it half quantity of sand On that full quantity of cement Over it balance quantity of coarse & fine aggregates is place. This prevents spillage of cement in air while discharging in drum

25 % Water is placed in drum and then mix from skip is discharged in the drum This prevents sticking of cement on blades 75 water is immediately poured after placing mix material (cement sand etc) in drum. 25

25 Mixing time In small machine, mixing time varies between 1-2 minutes In Ready Mix Cement mixer – 15-30 seconds RPM of drum : 15-20 Compressive strength of concrete increases with increase in mixing time but after 2 minutes increase in compressive stre n g t h is n o t si g n K i A f S i - 2 c 1 a 2 n t.

26 If concrete is not used after mixing it may set But when concrete is agitated on time to time in drum setting time rule does not follow.

27 Retempering of concrete : Some time concrete from RMC plant is not delivered to site due to traffic congestion Concrete becomes stiff and becomes unworkable Site engineers can reject the concrete if delay is more If it can be of used then small volume of water is added and again agitated in the drum. This is called RETEMPERING OF CONCRETE.

MANUFACTURING OF 29 CONCRETE With same material if care is not taken, resulting concrete will be bad concrete What are good rules to make good quality concrete.

TRANSPORTATION OF CONCRETE 30 Precaution in concrete transportation: Homogeneity of conc. Mass is maintained Movement of hand trolly or truck on rough road surface makes vibrations This results in deposition of heavy aggregates at bottom of truck Water & cement slurry comes on top.

METHODS OF TRANSPORTATION 31 Mortar Pan Wheel barrow Truck Mixer & dumpers Crane, Bucket & rope way Belt conveyors Chutes Skip & hoist Transit Mixer Pump & pipeline Helicopter

MORTAR PAN 32 Common method in India More labour required Segregation of concrete is less Greater surface area of concrete is exposed to sun, concrete dries.

WHEEL BARROW 33 When transportation of concrete is at ground level. Movement of wheel on rough road surface, segregates concrete. Some wheel barrows have pneumatic wheel to reduce vibration

CRANE 34 Used for transporting concrete above ground level. For high rise buildings. Cranes are fast Can move horizontally & vertically Concrete in skip discharge from bottom In bucket concrete is discharged by tilting.

BUCKET & ROPEWAY 35 Use for construction in: Valley Bridge pier in river Dam Adva n ta g e: Concrete is not exposed to sun or air & no loss of water.

Truck Mixer & dumpers 36 Used for large concrete works. Can travel any part of site. Dumpers - 2-3 M 3 Capacity Trucks – 4 M 3 Capacity Bottom surface of truck is kept wet Top of truck is covered to prevent evaporation

BELT CONVEYORS 37 Limited use in construction Advantages: Can transport large volume Very quick Can go where access is limited Disadvantages : On steep slope concrete segregates. Exposed to sun for long time.

CHUTE 38 For transporting from ground level to lower level. (basement etc). Used where labour can not reach due to less space in trench etc. Made of metal Slope should not be < 1 vertical : 2.5 horizontal.

SKIP & HOIST 39 Labour can go upto 3rd or 4th floors. So skip is used for transport vertically up (in multistory building). Skip travels on vertical rail. Skip can discharge manually or automatically.

TRANSIT MIXER 40

TRANSIT MIXER 41 Used for long distance travel in RMC plant. Concrete is continuously agitated in truck drum (2 – 6 rpm). Also transported mix in dry condition and water is added on reaching the destination. Wet Mix in truck must reach site in 1- 1.5 hours. Pumps are also fitted on truck mixer to discharge concrete.

PUMPS & PIPELINE 42 Most popular method Reliable & good quality pumps are used. Mostly operated by diesel. Concrete is placed in collecting hopper. Rotating blades in hopper pushes concrete towards pipe. Vacume in hose pipe (600 mm Hg) Rotating rollers in pump chambers squeeze the concrete in pipe and flow of concrete is started. Concrete is discharged from other end of hose pipe. Concrete can be pumped upto 400 m height and 2000 m distance.

SECTION OF PUMP 43

PIP E LINE 44 Pipeline should : Have correct diameter as per pump pressure. (generally 125 mm) Have sufficient thickness Good couplings Poor pipeline can cause blockage.

44 PIPELINE Thumb rule : For 30 M 3 /hr concrete and 200 m length, dia should be 100 mm. Length > 500 m then dia = 150 mm. Dia = 3 to 4 times the size of aggregate Leaky pipe & coupling result in escape of water /air & finally block the concrete. Vertical pipe should good otherwise difficult to change at height. Pump is kept at distance from building about 15 % of vertical length. KAS-2012

PUMPABLE CONCRETE 46 Concrete which can be pushed through a pipeline is called pumpable concrete. Friction between pipe wall and concrete is less. Concrete flows in the form of plug which is separated from pipe wall by a thin layer of lubricating cement paste. Flow resistant must be < pump pressure. If the concrete is more wet then water comes out of mix which makes more resistance to flow. Stiff and also very wet concrete is not pumpable.

Design of pumpable concrete 47 Concrete Mix is so designed that all material remain together. Mix must make redial movement of grout to maintain lubricating paste. Mix should be deformed at bends Cement & fine particles (0.25 mm size) are important for good flow. 350 to 400 Kg/ M 3 of fine particles are necessary for flow. Slump of pumpable concrete is above 75 mm.

PROBLEMS IN PUMPING 48 Blockage in pipe Pipe should be cleaned after each day operation Blockage can be cleaned by forward- backward pumping. Tapping pipe with hammer Clean pipe with rod or sponge ball pushed by compressed air.

PLACING CONCRETE 49 Must be placed in systematic manner. Can be placed with following methods: Within earth mould : Foundation In timber plank formwork : Road, airport slab. Steel shuttering : Dam Under water

Concrete in Foundation 50 In foundation, ground is made wet. Plastic sheet are laid between ground & slab Concrete is dumped not poured. No heap and dragging Placed in layers of 35 – 40 cm in mass concrete Avoid cold joints between 2 layers Surface of previous layer is cleaned with wire brush Sometime, cement slurry is placed on old surface Top of previous layer kept rough for good bond.

Concrete on Road, airport, floor slabs Placed in alternate bays (allow shrinkage) with contraction joints : contraction joints Bays 51

Concrete in Beams & Column 52 Reinforcement correctly placed. Correct cover required Joints of shuttering to be plugged. Mould releasing agent inside formwork

STRIPPING TIME 53 Form work should not removed until good strength has come. Type of form work Time Vertical wall, columns 16-24 hrs Soffit of slab (Prop should be refixed immediately) 3 days Soffit of beam (Prop should be refixed immediately) 7 days Props to slab Span < 4.5 m 7 days Props to slab Span > 4.5 m 14 days Props of beam (Span < 6 m) 14 days Props of beam (Span > 6 m) 21 days

UNDER WATER CONCRETE 54

UNDER WATER CONCRETE 55 Tremie (means hopper) is used. Funnel on top Pipe of 200 mm size Pipe bottom is plugged Fill pipe with concrete Lift pipe or jerk to release the plug Keep bottom of pipe inside concrete

Underwater Concrete 56 No compaction required as hydrostatic pr of water compacts concrete. Concrete of 0.3 W/C ratio can be placed with Tremie. Used for Pile or well foundation

SLIP FORM TECHNIQUE 57 2 In this method, concrete is continuously placed, compacted & form work is pulled up for next layer of concrete. Vertical slip form for Tall structure like silo, chimney Horizontal slip form paver machine (HSFP) for road construction. Concrete is dumped in front of HSFP machine by dumpers. Compaction by vibrator installed inside HSFP machines. Finishing of surface by HSF paver. Operation of road alignment, gradient, curve are controlled by Computerized Laser Control system. Speed of construction is 1 mt /min. 1 km of concrete road of 3.75 mt width is built in one day (16 hrs work). Mumbai-Pune Expressway was constructed by this machine.

VERTICAL SLIP FORM 58

HORIZONTAL SLIP FORM ROAD PAVER 59

COMPACTION OF CONCRETE 60 Compaction is a process of expelling the entrapped air inside concrete mass. During mixing, transporting & placing the concrete, air gets trapped in concrete mass. If this air is not removed, concrete will not get strength. 5 % of air voids reduces strength by 30 % 10 % of air voids reduces strength by 50 % Durability of concrete is also reduces with air voids. Insufficient compaction increases permeability of concrete. Results in entry of aggressive chemicals in solution. Chemicals attack concrete & reinforcement and life of concrete is reduced.

METHODS OF COMPACTION 61 1. Hand compaction Compaction by vibration Compaction by pressure & jolting Compaction by spinning

(2) COMPACTION BY VIBRATION 62 Internal Vibrator Formwork Vibrator Table Vibrator Platform Vibrator Surface Vibrator

(1) HAND COMPACTION 63 Hand Rodding Poking inside concrete with 1-2 mt long steel rod Ramming Unreinforced foundation & ground floor work Tamping Wooden beam is used to beat concrete (low thickness slab, road slab)

COMPACTION BY VIBRATION 64 In hand compaction w/c ratio is more so we get less strength in concrete. In mechanical vibrator w/c can be kept low so we get good strength.

INTERNAL VIBRATOR 65

(a) INTERNAL VIBRATOR 66 Most common in use Called, Needle Vibrator or Immersion vibrator or Poker vibrator. Consists : electrical/diesel power supply, Needle and shaft. Frequency of vibrations can be 12000 cycles vibration per minute. Needle diameter 20 to 75 mm Length 25 to 90 cm. Portable.

FORMWORK VIBRATOR 67 Used for columns, walls, precast slab Vibrator is clamped to formwork Vibration is given to formwork Vibration is transferred from formwork to concrete Useful in thin wall where reinforcement obstruct the needle type vibrator. Efficiency is lower then needle vibrator

TABLE VIBRATOR 68 Vibrator is clamped to table Used for concrete test cubes Cubes are kept on table to get vibrations Also used for small prefabricated slab

TABLE VIBRATOR 69

PLATFORM VIBRATOR 70 Similar to table vibrator but of large size Used for long concrete electrical pole, railway sleeper,prefabricated roofing element

PLATEFORM VIBRATOR 71

SURFACE VIBRATOR 72 Known as Screed Board Vibrator Used for thin roof slab where needle vibrator can not be used Not effective if slab thickness is more then 15 cm.

SURFACE VIBRATOR 73

COMPACTION BY PRESSURE & JOLTING Used for hollow blocks, solid concrete blocks Stiff concrete is vibrated, pressed & given jolts Stiff concrete is compacted to get dense form & good strength is achived. 74

VIBRATION BY SPINNING 75 New method Used for concrete pipes Concrete when spun at high speed gets compaction by centrifugal force

VIBRATORY ROLLER 76 Road rollers has vibrating system Roller while moving on raod slab gives vibrations Used for Lean concrete (M10) for road base 

ROLLER VIBRATOR 77

PRECAUTIONS IN VIBRATING CONCRETE Vibrator gets damaged if comes in contact with hard object (Formwork, hard concrete) Switch on when needle is inside fresh concrete mass Should conform to IS 2505-1963 Degree of compaction can be recognized from rising air bubbles & formation of thin film on top 78

HYDRATION OF CEMENT 79 Cement is made by Cao, SiO 2 , Al2O 3 , Fe 2 O 3 , MgO, K 2 O, SO 3 After burning in Kiln following products are made: - Tri calcium silicate – Di cacium silicate 3Cao. SiO 2 (C 3 S) 2Cao. SiO 2 (C 2 S) 3Cao. Al 2 O 3 (C 3 A) – Tri cacium aluminate 4Cao. Al 2 O 3 . Fe 2 O 3 (C 3 AF) -Tricalcium alumino ferrite. On addition of water in cement reaction of C 3 S, C 2 S, C 3 A & C 3 AF liberate heat. Heat is suside by addition of water.

CURING OF CONCRETE 80 Curing is defined as “ making satisfactory moisture content & favourable temperature” in concrete after placing the concrete. So that hydration may continue until the strength is developed. Curing is required immediately after placing concrete. During hydration, heat of hydration is released.

CURING OF CONCRETE 81 Concrete delivers its strength by the hydration of cement particles. Hydration is continuous & long time process. Rate of hydration is fast immediately after making the concrete Theoretically 0.23 w/c ratio required for hydration 0.15 w/c ratio required for filling the voids in gel. Total 0.38 w/c ratio is optimum In field condition, water evaporates & available water quantity reduced for hydration Extra water is given by curing

METHODS OF CURING 82 Water curing Membrane curing Application of heat Other methods

WATER CURING 83 Immersion : Slab is kept in water tank Ponding: Roof slab is filled with water Spraying : water spary on concrete wall is Wet covering : Wet gunny bags on wall

MEMBRANE CURING 84 Concrete surface is covered by plastic membrane It is used where water availability is less. Plastic sheet reduces evaporation in concrete Membrane is applied after 2 days of water curing

APPLICATION OF HEAT 85 Spraying of steam on concrete provides heat & moisture. Higher temperature accelerates hydration rate & strength of concrete is attended Early strength of structure is obtained Steam application possible at precast factory only. Precast prestressed concrete girders of bridge are cured with steam Fast construction of bridge

HIGH PRESSURE STEAM CURING 86 Superheated steam at high pressure (8.5 kg/cm2) & high temperature(175 deg C) is applied on concrete. This process is called “Autoclaving” 28 days strength of concrete is achieved in one day Concrete becomes sulphate resistant Low shrinkage in concrete Used in production of Cellular concrete products( Siporex, Celcrete)

FINISHING OF CONCRETE 87 Finishing is last operation of concrete making. Finishing of top surface is required in roads, airport strip, home floor Methods of Finishing: Form work Finish Surface Treatment Applied Finishes

FORMWORK FINISH Concrete obeys the shape of formwork Grooves & lining on formwork plate gives makes grooves & lining on concrete Prefabricated tiles can be made of any design

SURFACE TREATMENT 88 Domestic floor should be smooth, wear resistant, crack free. Mix should have good proportion without excess “Matrix” Exposed aggregate finish : Colored pebbles on top layer of wall Bush Hammering : Electrically operated Brush with teeth when applied on concrete removes top cement layer, exposes aggregates and makes shining aggregates.

APPLIED FINISH Rough cast finish : mixture of cement, sand, round gravel is applied on wall Non slip finish: Railway platform & walkway around pool are given non slippery finish by mixing large size sand particles in floor concrete.
Tags