Application of neat cement slurry @ 2.75Kg. of cement per m2. Applied by brush
M itred joints at the corners Straight line at intermediate with panel joints
Cement concrete shall be placed in position and beaten with trowel and finished smooth. Beating shall cease as soon as surface is found covered with cream of mortar.
The mixture so obtained shall then be laid on the base course within 2 to 4 hours of latter's laying
After the starting of initial setting, the surface shall be finished smooth and true with steel floats