SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Gotthard Base Tunnel:
High-Speed Rail Line Through the Alps
presented by: presented by:
Michael Rehbock, Michael Rehbock, M. Sc. Mining EngineerM. Sc. Mining Engineer
Member of the Board, Member of the Board,
Head of Tunnelling Department Amberg Head of Tunnelling Department Amberg
Engineering Ltd., Regensdorf, SwitzerlandEngineering Ltd., Regensdorf, Switzerland
SEMINAR ON PRACTICAL TUNNEL DESIGN AND
CONSTRUCTION
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Content
1. Project overview
4. Excavation in fault zone Sedrun
2. State of the works
3. TBM excavation with open gripper TBM
5. Special planning aspects
Special geotechnical aspects, experience from the
site Rolf Stadelmann
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Content
1. Project overview
4. Excavation in fault zone Sedrun
2. State of the works
3. TBM excavation with open gripper TBM
5. Special planning aspects
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
The Alp Transit Scheme
Bern
Solothurn
Basel
Neuchâtel
Lausanne
Genève
Sion
Zermatt
Chur
St. Moritz
Bellinzona
Luzern
St. Gallen
Zürich
Baden
Schaffhausen
GBT
Gotthard
Base Tunnel
LBT
Lötschberg
Base Tunnel
F
D
F
I
I
A
Lugano
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Longitudinal Profile
ExistingGotthard-
RailwayTunnel
ExistingCeneri-
RailwayTunnel
Existing
Zimmerberg-
RailwayTunnel
ExistingGotthard-
RailwayTunnel
ExistingCeneri-
RailwayTunnel
Existing
Zimmerberg-
RailwayTunnel
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Gotthard Base Tunnel, Alignment and Tunnel Lots
Total length: 57 km
Three intermediate points of attack
5 Construction sections
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Evaluated Tunnel Systems
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Tunnel System
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Gotthard Base Tunnel, Overview
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Longitudinal, Geological Profile and Investigations
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Geology and Heading Sections of the GBT
Drill and Blast
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Design Joint venture
Amberg is involved in the project since 1990
The work is done in an engineering joint venture together with
Lombardi SA and Pöyri Ltd.
The JV is responsible for all design works from the first studies to the
drawings “good for construction” and the site management
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Content
1. Project overview
4. Excavation in fault zone Sedrun
2. State of the works
3. TBM excavation with open gripper TBM
5. Special planning aspects
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
GBT, State of Excavation June 1st, 2006
Southportal
Bodio
already excavated
excavation and lining
accomplished
tunnels still to be excavated
Of the total of 153.5 km of
access passages, shafts and
main tunnels 94.1 km or 61.3 %
have already been excavated
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Erstfeld
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Erstfeld
Beginning of work: July 2004
Beginning of the TBM excavation: 2006
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Amsteg
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Amsteg, Tunnel Boring Machine
At June 1st, 2006
TBM east reached the end of
the section (length 11.3 km)
TBM west about 1.5 km to the
border
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Logistic Concept
Sedrun shaft
Portal installation
field
Northern drives
Foot of shaft
Concrete plant, silos
Access tunnel
Pipeline for
pneumatic
cement conveying
Depth ~800 m
Trackbound transport
Counterweight
Gotthard Base Tunnel
Trackbound transport
Southern drives
Head of shaft
- carrying persons
- excavated material
Cage for:
- construction material
Ventilation tunnel
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Shaft Cross Section
Fresh air
Waste
7.75 m
8.60-9.00 m (cross section = 63m )
2
air
Pipes for dewatering
Additional man riding hoist
Counter weight
Pipes for supply
Separation wall
In situ concrete lining
Big Cage 5.5 x 2.8 m
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Shaft Bottom
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Logistic Problems
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Method of Shaft 2
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction of Shaft 2, Pilot and Raise Boring
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction of Shaft 2, Shaftboring Machine
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Northern Tunnels
1.5 km excavated
About 500 m to go for
breakthrough towards
Amsteg section
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Southern Tunnels
Suspended Platform
Mucking and work at the
invert at the same time
2.5 km excavated
About 3 km to be excavated
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Back-up Installations
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Investigation Drilling
Preventer:
Shear Preventer
Pipe Ram
Roto Pac
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Faido
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Faido, Model of Multifunctional Station
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Faido, Cross Cavern,
Unexpected Downfall April 2002
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Faido, fault Zones
Original layout
Revised layout
Move of large caverns into better
geological conditions
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Bodio
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Bodio, Steel Arch of TBM
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Bodio, Installation of Sealing
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Bodio, Curing
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Bodio, Completed Single Track Tunnel
14.5 km excavated
< 1 km to be excavated
Breakthrough to Faido in
September
70 % of the final lining
finished
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Content
1. Project overview
4. Excavation in fault zone Sedrun
2. State of the works
3. TBM excavation with open gripper TBM
5. Special planning aspects
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Overburden at the GBT and the Channel Tunnel
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Special Conditions and Requirements of long and deep-
lying tunnels
High overburden and changing rock conditions
different types of rock support necessary
quick reaction to the actual geological situation necessary
flexible equipment on the tunnel face necessary
open TBM, no shilded TBM in this section
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
TBM in Squeezing Conditions
L* L*
1 2
u
r
p
a
DeformationDeformation
Support pressureSupport pressure
Resistance PrincipleResistance PrincipleYielding principleYielding principleFlexible Principle Resistance Principle
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Amsteg
Installation of flexible support
After
Deformation
15
Ortbetonverkleidung
min. Stärke = 35 cm
ø 9.20 m
ø 9.50 m
15
SOK
Segment 1. Ring: TH 44 (6 Stk.)
Segment 2. Ring: TH 44 (6 Stk.)
Ausbruchsicherung
Deformation = 15 cm
max. Stärke = 30 cm
Länge = 4.72 m
Länge = 4.75 m
Before
Deformation
1
1
ø 9.50 m
SOK
Segment 2. Ring: TH 44 (6 Stk.)
Segment 1. Ring: TH 44 (6 Stk.)
Länge = 4.72 m
Länge = 4.75 m
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
TBM Ecavation, Brittle Failure after Cutterhead
Picture: Vereina Tunnel
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
TBM Ecavation, Brittle Failure after Cutterhead
Picture: Vereina Tunnel
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
TBM Ecavation, Buckling and Spalling Effects at TBM Face
Picture: Lötschberg Tunnel
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
TBM Cutterhead
Vereina Tunnel, domed Gotthard Base Tunnel, flat
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
L
Z
0
1
#
5
7
2
4
8
Investigation, Prediction
•Additional Investigations ahead the tunnel front are necessary
•Investigation drilling (percussion and core drilling) takes time
• TSP-Measure little interruption of the excavation work
TBM Experience
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
L
Z
0
1
#
5
7
2
4
8
TBM Experience, Exploratory Drilling through Cutterhead
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
L
Z
0
1
#
5
7
2
4
8
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Crossing fault zone
Hydrothermally
weakened Rock
TBM West blocked in fault zone
in June 2005
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Crossing fault zone, Counter attack
East Tube
West Tube
Injections
Counter attack
Access and injection tunnel
from east tube
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Crossing Fault Zone, Revised Cutter Head
Restart TBM West end of 2005
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Crossing Fault Zone, Restart of Cutter Head
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Content
1. Project overview
4. Excavation in fault zone Sedrun
2. State of the works
3. TBM excavation with open gripper TBM
5. Special planning aspects
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Longitudinal, Geological Profile and Investigations
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Full Face Excavation
Tavetsch Intermediate Massiv
Squeezing rock conditions with expected deformations up
to 1 m over a length of more than 1‘000 m
Choosen Excavation System
Full Face Heading with intensive face anchoring and
yielding steel support
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Face Bolting
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Standard Cross Sections
Exc.diameter: 9 m
Exc. diameter: 13 m
Deformations: 20 cm
Inner lining: 30 cm
Deformations: 80 cm
Inner lining: 120 cm
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Support Placement Rig
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Construction Section Sedrun, Flexible Steel Arches TH 44
Radial Deformations up to 80 cm
Average advance rates of 90 cm/day
Support System and full face
heading proved itself
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Content
1. Project overview
4. Excavation in fault zone Sedrun
2. State of the works
3. TBM excavation with open gripper TBM
5. Special planning aspects
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Overburden at the GBT and the Channel Tunnel
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Forecast Rock Temperature at Base Tunnel Level
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Special Conditions and Requirements of long and deep-
lying tunnels
High rock temperatures
Cooling during construction and perhaps during operation
special requirements for the shotcrete and the concrete
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Amount of Excavation Material
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Material Preparation Plant and Processing Steps
Requirement for concrete
lining: 100 years without
major maintenance
Use of excavated material
as concrete aggregates
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Concret and Shotcrete Prequalification,
Test Gallery Hagerbach, Sargans
Installation of
Simulating
Transport
Conditions
Agreements in contract for
necessary adjustments
during construction
Prequalification of concrete
systems
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Heatable Gallery, Part of Test Gallery Hagerbach, Sargans
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Test Gallery Hagerbach, Sargans
Hagerbach test Gallery belongs to
Amberg Group
5 km of galleries and tunnels
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Safety aspects
During construction
Overall safety concept for each section (with SUVA)
Reduce risk and be prepared in case of an accident or fire
During operation
Two Multifunctional stations and cross cuts all 300 m
Ventilation for different possible events
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Fire Event with Blocked and without Blocked Staff at the Front
with
blocked
staff
without
blocked
staff
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Impressions of the Safety Concept during Construction
Safety control centre Exercises with the
external fire brigade
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Faido Multifunctional Station, Layout
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Multifunctional Station, Emergency Stations
Self rescue within 45 minutes
External rescue within 90 minutes
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Faido Multifunctional Station, Ventilation during Construction
fresh air
exhaust air
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Fresh and Exhaust Air System for Fire Events
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Normal concrete
Without any special fire protection
measures
After 20 minutes
Concrete disturbed (11.5 cm deep)
Fire Protection Tests, Test Gallery Hagerbach, Sargans
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Fire Protection Tests, Test Gallery Hagerbach, Sargans
2 kg PP-fibres:
4 cm chips
3 kg PP-fibres:
1 cm chips
1 kg PP-fibres:
6 cm chips
2 kg PP-fibres:
4 cm chips
2 kg PP-fibres:
4 cm chips
3 kg PP-fibres:
1 cm chips
3 kg PP-fibres:
1 cm chips
1 kg PP-fibres:
6 cm chips
1 kg PP-fibres:
6 cm chips
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Break Through
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
Thank you for
your attention!
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
TBM versus D & B, Comparison of Heading Time for Faido
TBM
D&B
Contractor I Contractor II Contractor III Contractor IV
month
SEMINAR ON PRACTICAL TUNNEL DESIGN AND CONSTRUCTION 26/06/06
TBM versus Drill & Blast, Comparison of Costs for Faido
Offered Price Lot Faido, GBT
3 %
3 %
9 %
0 %
Contractor I Contractor II Contractor III Contractor IV
TBM
D&B
Tender Price