IEEE-PES-ICC-Fall-2022-Presentation complete

poeta30 13 views 30 slides Jul 17, 2024
Slide 1
Slide 1 of 30
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30

About This Presentation

NEETRAC - IEEE-PES-ICC-Fall-2022-Presentation complete


Slide Content

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
From A to Z –Methods, Experiences, and Lessons Learned
from the Installation of a Critical MV Power Cable System –
Sub F
JC Hernandez-Mejia – GT NEETRAC – [email protected]
Stacy Elledge – GT NEETRAC – [email protected]
Joshua Perkel – EPRI – [email protected]
Nigel Hampton – UL – [email protected]
Sept. 30
th
to Nov. 2
th
, 2022 – Orlando, FL

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
2
Outline
• Background
• Critical Circuits
• From A to Z Methods –Highest Reliability & Case Study
–Factory Acceptance Test – FAT
–Site Acceptance Test – SAT
–Site Overview
–Installation Acceptance Test - IAT
–Takeaways
–Other important steps
• Summary

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
3
Background
• Utilitiesrecognizethe value ofcommissioningand
condition-based asset management of their distribution
cable circuits
• There isready availability of voltage sources and well-
established condition assessment criteria toundertake the
condition-based maintenance
• IEEE-PES-ICC Spring 2022 –Sub F –“Considerations
when Managing Critical MV Cable Circuits”

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
4
Critical Circuits
• The definition would likely change from utility to utility
• Specific cases may require unique parameters
• Circuits are considered crit ical when the risk and consequences of a
failure severely impact the users, system, and/or third parties
• Drivers might include:
–Critical infrastructure
–Impact to the end customer
–SAIFI and SAIDI
–Circuit Access (Location/Parts)
• Performance requirements remain constant across utilities
perspectives, i.e. highest possible reliability
• To ensure the highest possible reliability, methods from cable design
to manufacturing and installation are required
Case study presented here

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
5
From A to Z Methods –Highest Possible Reliability Q: How to get highest reliability?
A: By been involved from the beginning to end –A to Z
The A to Z process:
Utility
Need
Cable Manufacture
Accessory Selection
Handling
System
Design
Installation
Cable
Joints
Terms
Reliable
Service
Life
Critical
Circuit
AZ
Diagnostic
Intervention
FAT IAT MTSAT
Diverse/Complimentary
Set of Diagnostic
Technologies
FAT: Factory Acceptance Test
SAT: Site Acceptance Test
IAT: Installation Acceptance Test
MT: Maintenance Test
Utility

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
6
Critical Circuit –Case Study
• Feeder Type
• Three-Phase
• Bay Crossing
• One Spare
• 8 Reels (6,000 ft)
• 4 Joints
• 8 Terminations
• 2 cables installed
at the time
On-site Cable System Geographical Layout
Cable Lay
Cable Lay

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
7
Factory Acceptance Testing –FAT
• Witness electrical routine
test / review quality records
for each reel by experienced
representative on behalf of
the end user
• FAT conducted in addition to
standard Routine Test
• Consider augmenting
standard test frequencies for
critical cases
Case Study

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
8
Site Acceptance Test -SAT
Ensure that the cable did not
suffer any damage during
handling and transportation
• Visual Inspection
•TDR
• VLF Tan δ
• PD with DAC
• PD VLF Monitored Withstand
New cables were OK after factory
handling and transportation

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
9
Site Overview (1 of 3)

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
10
Site Overview (2 of 3)

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
11
Site Overview (3 of 3)

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
12
Installation Acceptance Test (IAT) -Stages
Near End
Stage 0 – First half of cable installed
Sea Bed
Reels
Barge
Cables
Far End

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
13
Installation Acceptance Test (IAT) -Stages
Near End
Stage 1 – Jointing on barge
Sea Bed
Joints
Far End

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
14
Installation Acceptance Test (IAT) -Stages
Near End
Stage 2 – Joints buried in seabed
Sea Bed
Far End

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
15
Installation Acceptance Test (IAT) -Stages
Near End
Stage 3 – Installation complete
Far End
Seabed

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
16
Installation Acceptance Test -Stage 1
Test
Sequence
Test Test Voltages
Applicable
Standards
1TDR N/A IEEE 400
2PD with DAC
0.5 U
0
, U
0
, 1.5 U
0

1.7 U
0
IEEE 400.4
3MWT PD with VLF30 min IEEE 400.2
4PD with DAC
0.5 U
0
, U
0
, 1.5 U
0

1.7 U
0
IEEE 400.4
Stage 1 - Joint Acceptance:
•Completed half crossing
•Joint assembly on barge
•Test terminations

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
17
Installation Acceptance Test -Stage 2
Test
Sequence
Test Test Voltages
Applicable
Standards
1TDR N/A IEEE 400
2PD with DAC
0.5 U
0
, U
0
, 1.5 U
0

1.7 U
0
IEEE 400.4
3MWT PD with VLF60 minIEEE 400.2
Stage 2 - Joint Submergence:
•Completed half crossing
•Joint assembly laid on seabed
•Test terminations

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
18
Installation Acceptance Test -Stage 3
Test
Sequence
Test Test Voltages
Applicable
Standards
1TDR N/A IEEE 400
2PD with DAC
0.5 U
0
, U
0
, 1.5 U
0

1.7 U
0
IEEE 400.4
3VLF Tan δ 0.5 U
0
, U
0
, 1.5 U
0
IEEE 400.2
4MWT PD with VLF 30 min IEEE 400.2
Stage 3 - Final Commissioning:
Completed full crossing
Joint assembly buried
Final pre-molded terminations

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
19
Feeder
Phase
Stage 1
Joint
Acceptance
Stage 2
Joint
Submergence
Stage 3
Final
Commissioning
Cable 1√ joint mechanical damage Abandoned
§: Needed because Cable 1 was Abandoned
Summary of Test Results by IAT Stage

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
20
TDR for Cable 1 (Abandoned)
After Trenching
On Barge

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
21
Summary of Test Results by IAT Stage
Feeder
Phase
Stage 1
Joint
Acceptance
Stage 2
Joint
Submergence
Stage 3
Final
Commissioning
Cable 1√ joint mechanical damage Abandoned
Cable 2
Red Phase

√√
Rejoint
§
PD at Joint – replaced

Cable 3
Spare Phase
PD at Joint – replaced
√√

§: Needed because Cable 1 was Abandoned

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
22
IAT DAC PD Location Tests Results
Cable 2 (Red Phase)

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
23
Cable 2 (Red Phase) Joint Dissection
Insulation Shield Cutback Defects

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
24
Summary of Test Results by IAT Stage
Feeder
Phase
Stage 1
Joint
Acceptance
Stage 2
Joint
Submergence
Stage 3
Final
Commissioning
Cable 1√ joint mechanical damage Abandoned
Cable 2
Red Phase

√√
Rejoint
§
PD at Joint – replaced

Cable 3
Spare Phase
PD at Joint – replaced
√√

Cable 4
Blue Phase
√√√
Cable 5
White Phase
√√√
§: Needed because Cable 1 was Abandoned

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
Other Important Steps

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
26
Cable Quality Assurance
• Perform QA checks on all shipping reels to ensure each
reel meets design specifications
• Ensure at least spare reels are available should issues
arise

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
27
Manufacturer Selection / Qualification to Bid
• Require qualification reports
• Require monthly CV qualification reports > 12 months
• Review experience of production of the design being
purchased –has this design been manufactured before?
• Manufacturer may be audited considering quality and
technical parameters
• Remember that a factory visit is nota full audit

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
28
Cable Design –Case Study
• EPR was the utility choice
• Only MV production plants can be used
• Limits the length to approximately 6,000 ft
• Jointing is required during the crossing
• Water blocked, fully encapsulation, and no armor

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
29
Accessory Selection
• Use only qualified joint designs (IEEE 404)
• Request qualification reports
• Use only qualified connectors –consider own experience
• Stick with joint designs and installation practices that utili ty
crews are most familiar with

IEEE PES ICC Fall 2022: From A to Z – Methods, Experiences, and Lessons Learned from the Installation of a Critical M V Power Cable System – Sub F
30
Summary
• Successfully conducted subsea commissioning program
• Commissioning integrated with the installation
• Designed to detect manufacturing and installation issues as
soon as practical avoiding risk
• Multiple and complimentary diagnostic tests / technologies to
improve accuracy
• Reduced repair/replacement costs
• The methods and processes can be used as guidance for
other critical circuit applications
Tags