ELECTRONIC INTERLOCKING INSTALLATION,TESTING,MAINTANANCE, PRECOMMISSIONING CHECK LIST , PRECAUTIONS AND TROUBLE SHOOTING
Electronic Interlocking -Installation &commissioning SIP & TOC All Required Materials and man power IFC and EI Plan Installation and Wiring IFC and App.Logic Design by OEM FAT with OEM Circuit Bell test and other necessary tests SAT with OEM -- by yard simulator SAT- by connecting signalling gears in yard Pre-commissioning Check list with OEM commissioning of EI system Data logger validation and MT Testing
Electronic Interlocking -INSTALLATION Pre-Installation work: 1.obtaining Approved EI Architecture Centrailsed Distributed 2.Approved Floor plan for EI Room Power Room SM’s OPerating Room Battery Room
Electronic Interlocking -INSTALLATION EI Room Installation Installation of Relay Racks Ensuring realay rack is to be insulated from ground racks to be erected with necessary suppoting for vibration free ladders and the cable trays shall have sufficient space lateral space b/w cable trays 6 inch vertical space b/w cable trays 9 inch
Electronic Interlocking -INSTALLATION Installation of EI Racks To be Installed with insulation bush with the floor Sufficient space to be provided for opening the equipment door and accessing the cards and circuit Installation of VDU Table suitable size to be installed for accomodating Dual VDU, Embedded PCs, DC-DC converter , VDU supply standby arrangement, SM key box,etc VDU orientation shall be as per SIP
Electronic Interlocking -INSTALLATION wiring of Relays and EI Euipment using standard wire coil with diferent ampacity as per approved interface circuit In all the interface circuits paralleling of contacts to be carried out in order increase the reliability colour codes shall be used as per Railway Pactice for Input , Output, Read back, Datalogger and internal wiring routing of cables from one rack to another rack/EI rack/D/L etc to be carried out with seperate dedicated cable ducts( like inputs with one duct, output with another duct , power cables with seperate duct)
Electronic Interlocking -INSTALLATION cable Terminaion in Terminals to be done with tag/sleeves (printed/painted) spacing between relays shall be carried out for easy view of relay contacts Relays to flashed and Tested for contact resistance using Relay Test kit before inserting in to the jack.this test has to be recorded Relay Test kit --manual and microcontroller based Ensure data logger contact to be front contact to most extent Before inserting relays in to jack check all contacts are proprerly inerted and locked
Electronic Interlocking -INSTALLATION Circuit wiring Test(Bell Test) before pluging relays circuit wiring test to be carried out carefully. while carrying the bell test all the EI cards and equipqmnts to be disconnected Bell test to be carried out from relay contact to next contact and from ternination to next termination. Datalogger wiring , power supply wiring and all wirings to be bell tested.
Electronic Interlocking -INSTALLATION Earthing and Bonding
Electronic Interlocking -INSTALLATION Wire Component/Bonding Material Size Main equi-potential earth busbar (MEEB) Copper 300X25X6mm(min.) Sub equi-potential earth busbar (SEEB) Copper 150X25X6mm(min.) Individual equipments to SEEB using tinned copper lugs with stainless steel nut and bolts Multi-strand single core PVC insulated coppercableasperIS:694 10Sq.mm. SEEB to MEEB using tinned copper lugs with stainless steel nut and bolts. Multi-strandsinglecorePVC insulated copper cable as per IS:694 16Sq.mm. Surge protection devices(SPDs) to MEEB using tinned copper lugs with stainless steel nut and bolts. Multi-strand single core PVC insulated copper cable as per IS:694 16Sq.mm. MEEB to main earth electrode Multi-strand single core PVC insulated copper cable as per IS:694(Duplicated) 35Sq.mm. Main earth pit to other earth pit in case of loop earth. Copper tape OR solid copper round conductor 25X2mm.or8mm.dia.
Electronic Interlocking -Testing Testing In case of EI, it is carried out by testing integrity of Application Logic (Software). It is possible to carry out this test by using Simulator and Emulator at factory, drawing office as well as the site as an offline activity. Interlocking Testing for EI is done in two stages : a) Factory Acceptance Test (FAT) b) Site Acceptance Test (SAT)
Electronic Interlocking -Testing a)FAT Test Purpose : a) Ensure that the Interlocking system fulfils the station Interlocking & Route Control Chart requirements and workings in safe manner even if any false inputs received. b) Minimises the site errors & risks and reduces the corrections at site. This results in saving of time at site testing. FAT is carried out through simulation set up (using Simulator Panel with toggle switches or Simulator PC with Interlocking Simulation Setup - software) in which all field inputs are simulated. .
Electronic Interlocking -Testing
Electronic Interlocking -Testing During FAT, Timers in Application logic are modified for the FAT testing reduced from 120 seconds to 12 seconds to speed up the testing. In FAT setup, the I/O boards are not physically present and the same are simulated using the test setup. To carry out FAT, the following inputs are required: a) Signal Interlocking Plan (SIP) b) Route Control Chart (RCC). c) Control cum Indication Panel Diagram. d) Cross Table/Square sheet.
Electronic Interlocking -Testing When Railways/Customer testing is completed, the Check sum and CRC values of the FAT simulated application logic will be recorded b)Site Acceptance Test (SAT) Site testing of Station Interlocking System, where tests are executed at site environment. Ensures a)all the equipments installed at site are functioning correctly as per approved system b)configuration and station interlocking requirements and working in safe manner and failsafe even if any equipment fails/false inputs/information received
Electronic Interlocking -Testing
Electronic Interlocking -Testing To carry out SAT, the following inputs are required: a) Application source file, Application listing file, Application program file (Hardcopy & Read-only Softcopy) b) Station SIP c) Station Route control chart d) Station Control cum indication panel diagram e) Square Sheets/Cross tables f) Wiring Circuits
Electronic Interlocking -Testing All the field inputs are simulated by using simulation panel through toggle switches inputs are sent to EI via relays and the field outputs are sent to lamps through relays The following testing shall be carried out while doing SAT: Visual test Communication testing Correspondence Test System Integrity Test Interlocking testing Change over test
Electronic Interlocking -Testing As explained above SAT is performed in two stages: 1. Testing of Electronic Interlocking at site with E.I. hardware and simulation panel. 2. Testing of the outdoor gears, viz., points, signals, track circuits, LC gates etc Guidelines: SAT for EI should be done first from panel and there after from VDU. If dual VDU is provided, then SAT to be done with each VDU separately. Above tests may be under taken using data logger also.
Electronic Interlocking -Testing Automatic Site Acceptance Test(ASAT) carried out to test TOC /SLCT automatically uses software which executes Test by simulating the signalling gears Test reports will be generated for every route
Electronic Interlocking-Precommissioning Check list To be carried jointly by OEM and Railway M/s Hitachi Rails M/s Kyosan M/s Medha M/s Westrace(Siemens)
Electronic Interlocking - Maintanance some periodical and preventive maintenance is necessary to ensure safe and efficient functioning of the systems. The maintenance of Electronic Interlocking System involves the following activities : (a) Checking of System Power supply. (b) Visual inspection of the EI system. (c) Checking of interface relays and cable terminations. (d) Verification of System changeover from active to standby and vice versa. (e) Downloading and analysis of user log, event log and error log from Maintenance Terminal. (f) Verification of system clock
Electronic Interlocking - Maintanance (g) Maintenance of earthing and surge protection arrangement. (h) Checking of communication links between system and peripherals. (i) Checking the function of peripherals like Operator VDU, Panel Processor etc. (j) Checking the function of cooling fans in the system racks. (k) Verification of the Checksum /CRC and version numbers of current software of the system. (l) Verification of correct logging of data in external data logger. (m) Testing the integrity of application program with the help of TOC.
Electronic Interlocking - Maintanance (a) Checking of System Power supply : (i) Ensure that the DC –DC converters are in working order. (ii) Check the fuses for proper housing and tightness. (iii) Measure the output voltages at DC-DC Converters, fuses and at system terminals and ensure that they are within the specified limits. (v) Ensure that standby power supply modules are available and are in working order. (b) Visual inspection of the EI system : (i) Ensure all the PCBs are properly housed and plugged in the system card file/housing/OC. (ii) Ensure all the normal indications are available in all PCBs of the system.
Electronic Interlocking - Maintanance (c) Checking of interface relays and cable terminations : (i) Ensure proper housing and fixing of Relays and connectors. (ii) Measure the input and output interface voltages and ensure that they are withinthe specified limits. (iii) Check that diodes across the vital output relays are in order. (iv) Ensure particulars of relays and terminals are available &visible . (d) Verification of System changeover from active to standby and vice versa : Where warm standby is available, reset the On line system and see that change over takes place properly and the stand by system is also working properly
Electronic Interlocking - Maintanance (e) Downloading and analysis of user log, event log and error log from Maintenance Terminal : (i) Download user data log, event log and error log from the EI system to the maintenance terminal at regular intervals. (ii) Analyze the event and error log to identify system faults if any and take necessary corrective action. (f) Verification of system clock : (i) Verify the current time of the system and see that it is correct or not. (ii) If it is not matching then set the time of the system using maintenance Terminal.
Electronic Interlocking - Maintanance (g) Maintenance of Earthing and Surge protection arrangement: (i) Measure the resistance of the ring/perimeter earth provided for the EI system and ensure that it is < 1 Ω. (ii) Check that all the earth electrode connections are properly welded and no rust formation is there at the terminals and joints. (iii) Inside the EI equipment room check that all terminations and connections at the MEEB, SEEB and at the equipment racks are properly fixed and tightened. (iv) See that cable armory /shield are connected to earth terminals properly. (v) Check that all Surge protection devices are connected properly and are in working order
Electronic Interlocking - Maintanance (h) Checking of communication links between system and peripherals : (i) Check that all the communication links between system and peripherals are in working order. (ii) Ensure that the power supply and ground connections to the communication equipment are provided properly. (i) Checking the function of peripherals like Operator VDU ,Panel Processor etc : (i) Verify that all field gears can be controlled and operated with the Operator VDU / CCIP. (ii) Check that the changeover between Panel & VDU /VDU & standby VDU is taking place in proper sequence. (iii) Verify that sufficient backup supply through UPS is available for VDU.
Electronic Interlocking - Maintanance (j) Checking the function of cooling fans in the system racks : (i) See that the cooling fans provided inside the system rack are in working order. (k) Verification of the Checksum /CRC and version numbers of current software of the system : (i) Run the maintenance tool and verify the Checksum, CRC and version of the current application logic and executive logic. (ii) See that they are tallying with the past record.
Electronic Interlocking - Maintanance (l) Verification of correct logging of data in external data logger : (i) Check the serial communication connections between EI System & Protocol converter and between Protocol converter & Data logger. (ii) See that normal indications are available in protocol converter. (iii) Ensure that the user data log is logging properly in the external data logger (m) Testing the integrity of application program with the help of TOC : (i) This test has to be conducted when ever any modification has been done in the existing application logic. (ii) It has to be conducted periodically also to ensure proper functioning of the existing logic as per the TOC.
Electronic Interlocking - Maintanance Periodicity of Maintenance As per the IRSEM general maintenance schedule for Electronic interlocking is provided for guidance at Annexure: 21-MS3 in Appendix-I the periodicity of different maintenance tasks for EI for some items are as mentioned below
Electronic Interlocking - Maintanance
Electronic Interlocking -Trobleshooting Identifying Faults The failures occurring in EI systems are broadly divided into two categories. They are System level faults and Card level faults. System level faults: All the faults other than the hard ware failures of system cards can be treated as system level faults. The system level faults may occur due to problem in any one of the following sections of the EI system. (a) System Power supply (b) Interface wiring (c) Interface Relays and Relay contacts (d) System changeover circuit
Electronic Interlocking -Trobleshooting (e) Panel/VDU (f) Application logic (g) Communication equipment Card level faults Most of the cards in the EI system are provided with some indications on the front panel. These indications reflect the normal or abnormal functioning of the respective cards.
Electronic Interlocking -Trobleshooting For the sake of trouble shooting the EI Installation can be divided into the following sections : (a) EI System Card file (b) Peripherals (c) Interface circuits (d) Power supply system (e) Communication cables and equipment (f) Outdoor gears (g) Software
Electronic Interlocking -Trobleshooting Identifying and localization of the fault: (a) Indications on System Card file (b) Indications on the CCIP/VDU (c) User log and Event & Error log in Maintenance Terminal A general flow chart for trouble shooting the failures in EI system
Electronic Interlocking -Trobleshooting
Electronic Interlocking -Precautions DO: 1. Tighten the boards after insertion. 2. Ensure all terminations are fully tightened. 3. Place the removed boards with a tag into a conductive shielding bag. 4. Download user data log / Event log / Error log data periodically. 5. Maintain minimum 12V/24V DC at the card file back plane. 6. In case of Warm Standby System Ensure diagnostic switch in “NORMAL” position before starting the system. 8. Keep the EI room free from dust
Electronic Interlocking -Precautions Don’t: 1. Reset the system when working. 2. Remove or insert boards, VCOR relays, Fuses / Links and pin connectors when the system is on. 3. Forcible insertion of the boards in to the slots. 4. Change jumper settings in PCBs. 5. Touch the board components. 6. Repair boards on your own. 7. Alter EI system, Maintenance Terminal and Operator VDU setting without authorization. 8. Delete / Modify application program Logics without authorization. 9. Use blower for cleaning dust