JAMMU RHPPL Presentation for Tawi Riverfront project.pptx

vikass3443 66 views 29 slides Aug 17, 2024
Slide 1
Slide 1 of 29
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29

About This Presentation

jammu Tawi riverfront Project


Slide Content

Month of June – 2024 TAWI RIVERFRONT DEVELOPMENT JAMMU SMART CITY LIMITED RATHI HYDRO PROJECTS Pvt. Ltd .

Tawi Riverfront Project is one of the most prestigious and flagship project being executed under the aegis of JSCL. The project has been conceived with twin objectives of: Flood mitigation/Flood protection for Jammu City. Creation of recreational spaces and Central Business district in its surroundings.

Construction of embankments with stepped retaining wall and diaphragm wall with channelized section 250m-300m wide and for a length of 2.7 km on both sides from 4 th bridge upto upstream of Bikram Chowk Bridge. In Phase 1 of the project embankments are being constructed for a length of 2.7 km on both sides of the river from Bhagwati Nagar barrage to Bikram bridge including central island. 4 No. Promenades being created. Lower Promenade -8m wide Intermediate Promenade (2 nos.) -5.75m wide Top Promenade- 6m wide Salient features of the Project

Name Of Project Tawi Riverfront Project Total Cost 143 Cr. Location of Project 4 th tawi bridge to Bikram chowk Bridge, Jammu. Client Of Project Jammu Smart City Limited Contractor Shree Balaji Engicons Limited Sub - Contractor Rathi Hydro Projects Pvt. Ltd. Total Length of Embankment (Phase-I) 2.70 km on each side (L/B & R/B) Commencement Of Project January 2022 Expected Date of Completion June 2024 (Need Extension of Time)

Length to be taken up in Phase 1 on both sides – 2.70kms. 0.49km 1.07km Tawi Bridge Phase 1 Gujjar Nagar Bridge 1.13km Barrage

Total Project Cost : 143 Cr Completed Work : 117.24 Cr. Balance work (as per site : 13 Cr. Condition) Expected Date of Completion : June 2024 Tendered Cost Left Bank 68.47 Cr. Right Bank 74.53 Cr. Balance Work 12.94Cr. 12.82 Cr. Total 25.76 Cr.

Area Planned Target Achieved Target RIGHT BANK 1.54 Cr. 87.93 lakhs LEFT BANK 1.47 Cr. 79.97 lakhs CENTRAL ISLAND 49.53 lakhs 29.35 lakhs Achieved Target Total Projected Target – 3.51 Crores Of July 2024 Total Achieved Target – 1.97 Crores Of July 2024

Planned Quantity Achieved Quantity Percentage Embankment 15000 m3 10688 m3 71.25 % PCC M-15 229.73 m3 224.84 m3 97.87 % RCC M-25 759.35 m3 666.65 m 3 87.79 % CC Blocks 300 nos. 16 nos. 5.33 % Railing 49 nos. 53 nos. 108.16 % RIGHT BANK LEFT BANK Planned Quantity Achieved Quantity Percentage Embankment 15000 m3 9248 m3 61.65 % PCC M-15 207.36 m3 114.11 m3 55.02 % RCC M-25 790.33 m3 368.26 m 3 46.59 % CC Blocks 300 nos. 212 nos. 70.66 % Railing 270 Nos. 83 Nos. 30.74 % ISLAND Planned Quantity Achieved Quantity Percentage Embankment 5000 m3 2440 m3 48.80 % PCC M-15 33.3 m3 53.76 161.44 % RCC M-25 215.77 m3 170.89 m 3 79.20 % CC Blocks 300 nos. 79 nos. 26.33 % July 2024 Summary

Hinderances - Heavy Rainfall & Wind at Site dated 05.06.2024, 06.06.2024 & 28.06.2024 Rise of water Level in River dated 28.06.2024 Shortage of Manpower as compared to required at Site Strike of Labour dated 26.06.2024 due to Payment Issue L/B Railing team not Available since 15.06.2024 All L/B Dumper not Working in Night Shift

WATER LEVEL RISE IN RIVER 01-07-2024

Dumper Breakdown 1586 dated 19.06.2024, due to fall in river TM B/D (0447,) dated 01.06.2024 TM 0526 Breakdown dated 19.06.2024, due to fall in river Hinderance (Machinery) -

TM - 0447

Manpower Report

Labour Add On Plan

Machinery List

Hired Machinery List

Projected Target For July 2024 Total Projected Target For July 2024 – 3.51 Crores

Right Bank – 1.54 Crores

Left Bank – 1.47 Crores

Island – 49.53 Lakhs

SITE PHOTOS –

Compaction Work

CC BLOCKS

ANCHOR SLAB WORK

R-100 Nallah Work

Curing Work

THANK YOU
Tags