Month of June – 2024 TAWI RIVERFRONT DEVELOPMENT JAMMU SMART CITY LIMITED RATHI HYDRO PROJECTS Pvt. Ltd .
Tawi Riverfront Project is one of the most prestigious and flagship project being executed under the aegis of JSCL. The project has been conceived with twin objectives of: Flood mitigation/Flood protection for Jammu City. Creation of recreational spaces and Central Business district in its surroundings.
Construction of embankments with stepped retaining wall and diaphragm wall with channelized section 250m-300m wide and for a length of 2.7 km on both sides from 4 th bridge upto upstream of Bikram Chowk Bridge. In Phase 1 of the project embankments are being constructed for a length of 2.7 km on both sides of the river from Bhagwati Nagar barrage to Bikram bridge including central island. 4 No. Promenades being created. Lower Promenade -8m wide Intermediate Promenade (2 nos.) -5.75m wide Top Promenade- 6m wide Salient features of the Project
Name Of Project Tawi Riverfront Project Total Cost 143 Cr. Location of Project 4 th tawi bridge to Bikram chowk Bridge, Jammu. Client Of Project Jammu Smart City Limited Contractor Shree Balaji Engicons Limited Sub - Contractor Rathi Hydro Projects Pvt. Ltd. Total Length of Embankment (Phase-I) 2.70 km on each side (L/B & R/B) Commencement Of Project January 2022 Expected Date of Completion June 2024 (Need Extension of Time)
Length to be taken up in Phase 1 on both sides – 2.70kms. 0.49km 1.07km Tawi Bridge Phase 1 Gujjar Nagar Bridge 1.13km Barrage
Total Project Cost : 143 Cr Completed Work : 117.24 Cr. Balance work (as per site : 13 Cr. Condition) Expected Date of Completion : June 2024 Tendered Cost Left Bank 68.47 Cr. Right Bank 74.53 Cr. Balance Work 12.94Cr. 12.82 Cr. Total 25.76 Cr.
Area Planned Target Achieved Target RIGHT BANK 1.54 Cr. 87.93 lakhs LEFT BANK 1.47 Cr. 79.97 lakhs CENTRAL ISLAND 49.53 lakhs 29.35 lakhs Achieved Target Total Projected Target – 3.51 Crores Of July 2024 Total Achieved Target – 1.97 Crores Of July 2024
Hinderances - Heavy Rainfall & Wind at Site dated 05.06.2024, 06.06.2024 & 28.06.2024 Rise of water Level in River dated 28.06.2024 Shortage of Manpower as compared to required at Site Strike of Labour dated 26.06.2024 due to Payment Issue L/B Railing team not Available since 15.06.2024 All L/B Dumper not Working in Night Shift
WATER LEVEL RISE IN RIVER 01-07-2024
Dumper Breakdown 1586 dated 19.06.2024, due to fall in river TM B/D (0447,) dated 01.06.2024 TM 0526 Breakdown dated 19.06.2024, due to fall in river Hinderance (Machinery) -
TM - 0447
Manpower Report
Labour Add On Plan
Machinery List
Hired Machinery List
Projected Target For July 2024 Total Projected Target For July 2024 – 3.51 Crores