jsa for painting.docx for construction activities

Bhavanishankarshetty1 68 views 3 slides Mar 11, 2025
Slide 1
Slide 1 of 3
Slide 1
1
Slide 2
2
Slide 3
3

About This Presentation

jsa


Slide Content

FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
HAND BRUSH PAINTING
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
Sl. Job Step Identify Hazards &
Assess Risk
Risk
level
Controls to Eliminate/Reduce Risk
1 Work planning prior to start In competent person
Poor planning
Non- compliances to PPE
requirement
Permit To Work Only
Do not start any work preparation until signed permit is in hand
All involved departments and contractor shall have a joint
Inspection and a meeting prior start the job
Survey work area and address safe work method .hazards and
Precaution
JSA must be followed and to be explained to all employees
During TBT prior to start of activities and it must be made
Available at the site
2 Site preparations Un authorized person entry
Poor access
Tripping slipping hazardous
Medium work location must be barricaded and signboard shall be placed
prior to start area must be clean and tidy
work materials and tools properly stored
TBT shall be conducted prior to start
3 Painting storage Chemical spill
Fire& explosion
Chemical reaction
High Provide proper shelter for chemical storage
Fire extinguisher required
MSDS must be required at Paint storage area
DO not keep any unnecessary materials in the paint storage area
Spill kit shall be required on site
4 Hand brush paintings Chemical spill
Oxygen deficiency
Vomiting
Skin damage
High Proper PPE must be worn spatially chemical protection mask and
Hand gloves [including respirator]
Before take a food/ drinking water hand must be wash
Proper supervision required

FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
HAND BRUSH PAINTING
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
5
House keeping
Fire
Person injury
Poor access
Tripping slipping falling hazard
Medium
Fire extinguisher keep at work place
Access free from obstruction
Work location must be clean and tidy
Materials properly stored
Unnecessary materials remove from the location and avoid
Slipping tripping falling hazard
6 Permit closeout Before ending shift area surround check
Permit receiver closeout daily permit
7 Emergency contact
Numbers
TECNICAS REUNIDAS CONTACT NO.
Caner Cihan– Construction Manager 0500174341
Hakan Ayata – HSE Manager 0500605496
Edgar Arada– HSE Superintendent 0541505823
Angel Marques – QA/QC Inspector 0502760610
Yousif Ali – Site Superintendent 0561792587
RAPCO
Samson David –Site Manager 0505799498
Salim KA – HSE Manager 0583431641

FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
HAND BRUSH PAINTING
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
REQUIRED SAFETY EQUIPMENT
Hard Hats Other Gloves Face Shield Hand Tools & Power ToolsCranes 
Safety Glass

Work Vest

Goggles

Compactor
 
Steel Toe Boots

Safety Harness

Barricades

Lifting Gear
 
Cotton Gloves

Self Retracting Lifeline (SRL)

Fire Extinguihsers

Air Hoist/Man Rider

Other Equipments/Materials

Participated Date: Sign Rew by Date Sign Approved by Date: Sign
Samson david
[Site manager]
Salim. ka
Habib
[Safety
Supervisor]
Ganesh
[supervisor]