FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
Sl. Identify Hazards & Assess
Risk
Identify Hazards &
Assess Risk
Risk
level
Controls to Eliminate/Reduce Risk
1 Prepare JHA, by obtaining
approval and communicate
requirements through toolbox
meeting
Failure to properly
communicate to
all involved
personnel the
necessary control
measures and
approved work
method can result
in communication
lapses and serious
incident during the
execution
Medium Method statement to be explained to all employees
and copy made available at the site.
JSA to be made available at the site and Job Specific
hazards and control measures communicate to all
personnel involved in the job.
supervisor should communicate to his crew
appropriate control measures outlined in the
approved JSA and
proper sequence of work through task-specific TBT
prior to commencing work.
to be completed and requirements discussed prior to
commencement of work.
2 Obtain Permit to Work (PTW) Failure to obtain
approved work
permit can result
in serious
incidents/PTW
violation.
Medium Obtain PTW prior to the commencement of the work
and hard copy to be kept at the work site.
Do not start any work preparation until signed permit
is in hand.
Comply with GI 2.100 requirements
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
3 Hauling/transporting / unloading
of scaffolding materials such as
scaffolding pipes, wood planks,
couplers, etc., into the work area
using transport vehicle / trailer/
forklift/crane (where required).
1.Unapproved transport
vehicle
2.Use of Non-approved
access road due to
lack of briefing /
communication with
the driver
3.Existing plant facilities
along access road,
subject to accidental
contact with vehicle
4.Prohibited movement
of vehicle in case of
plant emergency.
5.Prohibit use of
defective slings and
other lifting tackles.
6.Person could be
pinched/ crushed by
moving parts of the
crane or hit by
High the project.
1.Pre-mobilization acceptance / approved access pass
for the vehicle
1.Brief driver on emergency procedure and restriction
of vehicle movements in emergencies.
2.One assistant to accompany the driver and serve as a
banksman when ever required safety orange vest on,
using flags.
3.Use approved access route, provide drivers a route
plan.
4.Pre-transport survey of approved access clear route
to clear obstruction (if any), check overhead
structures/proximity to existing facilities alongside
access road; ensure safe access during transport.
5.Pre-agreed holding area with plant operations clear
of obstruction available prior to hauling equipment
into the plant.
6.Ensure traffic control to prevent traffic disruption to
plant equipment and personnel
7.Sort out scaffolding materials prior to hauling; ensure
only approved types are mobilized to work area. Only
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
suspended load.
7. Reversing forklift,
trailer and crane
without spotter
OSHA proof tested LVL scaffold planks will be used on
the project.
8.Rivet type couplers are prohibited.
9.Ensure scaffolding materials are properly bundled/
secured.
10.Ensure materials are properly secured on trailer
beds/ delivery trucks by using sling.
4 Hauling of materials and manual
lifting of Scaffold materials
. Fall Hazard
2 Pinched point
3. Back Injury
High Secure appropriate working permit
Secure all materials/tools on elevated areas
Use proper PPE’s and proper lifting techniques
Long tubes must be carried by two person, load
sharing
Proper tie-up of material when hoisting up only
6 Erection of scaffolding platform1.Fall from height of
personnel
2.Fall from height of
materials
3.Scaffold failure
4.Nearby existing
equipment,
Before ending shift area surround check
1.Follow / Comply with Saudi ARAMCO GI 8.001 and
Scaffold Safety Handbook (SSH) – for all types of
scaffolds (tower/mobile/ under hung special
scaffolds)
2.ARAMCO prescribed Scaff Tags currently signed by
SA-certified Scaffolding Supv / Inspector (2 weeks
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
instrument, valve,
gauges, etc., subject
to physical change
Dropped objects / tools
interval),
3.Secure area directly below by proper barricades, signs
/ warning notices on overhead activities. Assign
watch man to warn other personnel from
unauthorized entry.
4.Scaffolding platform not to be overloaded, do not
store pipes, steel for supports, etc., on personnel
platform.
5.Never exceed working capacity of platform (240 kg/sq
meter)
6.Use of Full Body Harness w/ two shock absorbing
lanyard,complying 100% tie-off.
7.Work force must under gone JGULF Golden Rules of
Working @ Heights orientation training, complete
100% hands-on.
8.Tools & equipment to be secured against fall(i.e. tied
down, use with lanyard or string)
9.Maintain 3 point contact when ascending
/descending from ladder.
10.Throwing of scaffolding pipes, planks, couplers, tools,
etc., is strictly prohibited, use of rope & material
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
bucket to hoist up and lowered materials to the
ground
11.Never remove floor grating or cut hole on floor
without approved “Grating Removal Certificate” from
HSSE / PTW office.
12.Keep scaffolding pipes / wood planks / couplers at
height secured/tied down against displacement/fall
at all times.
13.Use buckets for couplers, small tools/ materials at
heights.
14.Individual scaffold platforms will be erected /
supported independent from each other i.e. NOT
interconnected such that, future dismantling of one
platform WILL NOT affect structural integrity of the
other platforms.
15.When erecting suspended scaffolds underneath pipe
racks, consider overhead clearance required for
mobile equipment-check with civil supervisors.
16.Elevated platforms on pipe racks should have
minimum of 2 exits at opposite direction from any
work area, discharging to the ground without
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
obstruction.
17.Access tower scaffolds with intermediate landings
should be provided at minimum of every other bay or
third column from topmost working level of pipe
racks to / from the ground.
18.Intermediate step landing to be provided at least 9
meters (30 ft) of height, equipped with complete
guard rails and toe boards.
19.Any erection activity will be immediately suspended
in harsh weather condition such as
rainstorm/sandstorm/thunder & lighting storm. Work
will not resume immediately following rainfall until
scaffolding materials / tubes are dry to prevent
material slippage / accidental drops during handling
due to being slippery.
PPEs’ must be donned at all times
Scaffold
dismantling /
hauling of
dismantled
materials
1.Fall from height of
personnel
2.Fall from height of
materials
3.Scaffold failure
1.Pre-dismantling coordination review / meeting
between scaffold supervisor / focal point and affected
trade supervisor using scaffold platforms.
2.Pre-dismantling joint field inspection by scaffold
supervisor and concerned trade supervisors to field-
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
4.Improper anchorage
of FBH lanyard
5.Interconnecting
platforms being
structurally impacted
6.Dismantling not
communicated to
affected trades / users
7.Permanent plant
equipment /
instruments, valves,
gauges below, etc.,
subject to physical
damage from dropped
objects
8.Delayed hauling of
dismantled materials
confirm specific platforms to be dismantled prior to
the activity. Ensure there are NO remaining works on
the platform by other trades prior to dismantling e.g.
painting / insulation crew / punch list / pre-
commissioning etc.
3.Prior to dismantling, planned arrange for hauling
equipment i.e. forklifts / trailers – ensure access
passes current
4.Prior to dismantling any scaffold / loosening any
coupler, scaffold supervisor and Scaffolders will
thoroughly inspect the whole structure and support
to ensure adjacent or overlapping platforms will not
be affected.
5.Means of anchoring Full Body Harness lanyard should
be first identified i.e. structural beams / columns
nearby; approved extension lanyards are available to
facilitate tie-off. Properly secure the area prior to
dismantling activity, signs put in place.
6.Sensitive instruments / permanent equipment below
dismantling activity, exposed to accidental drops /
damage should first be protected by appropriate
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
means i.e. temporary overhead shed using scaffold
planks prior to dismantling or equivalent.
7.Dismantling to be carried out ONLY by scaffold
craftsmen experienced in dismantling work. Helpers
remain on ground, limited to materials handling.
8.Keep all hand tools tied off against accidental drops.
9.Keep area below properly controlled – standby man
posted to patrol barrier off area while activity is in
progress using warning tapes.
10.Dismantled materials to be stored without
obstructing access / permanent plant equipment and
hauled from the area without delay.
11.Holding racks to be prepared on the ground before
dismantling to keep dismantled materials organized
from start and get them ready for loading / transport
right away.
12.PPEs’ must be donned at all times.
Housekeeping /
Close Out Of Permits
1.Accumulation of
debris
2.Tripping hazards
1.Designate housekeeping crew and equipment for
collecting / removal wastes
2.Remove all the debris from site daily as minimum
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
3.Unclosed out permits 3.Maintain good housekeeping standards -keep area
safe, materials properly stacked, and tripping hazards
free.
4.Tidy up work area before close out of each permit.
Ensure all permits are closed out at each end of work
shift
7 Emergency contact
Numbers
TECNICAS REUNIDAS CONTACT NO.
Caner Cihan– Construction Manager 0500174341
Hakan Ayata – HSE Manager 0500605496
Edgar Arada– HSE Superintendent 0541505823
Angel Marques – QA/QC Inspector 0502760610
Yousif Ali – Site Superintendent 0561792587
RAPCO
BHAVANISHANKAR –Site Manager 0505799498
Salim KA – HSE Manager 0583431641
REQUIRED SAFETY EQUIPMENT
FACILITY/PLANT LOCATION:
JAZAN REFINERY &ECONOMIC CITY
DESCRIPTION OF WORK:
SCAFFOLDING ERRECTION
DATE:
CONTRACTOR:
TR/RAPCO
REVISION: 0
Hard Hats Other Gloves Face Shield Hand Tools & Power ToolsCranes
Safety Glass
Work Vest
Goggles
Compactor
Steel Toe Boots
Safety Harness
Barricades
Lifting Gear
Cotton Gloves
Self Retracting Lifeline (SRL)
Fire Extinguihsers
Air Hoist/Man Rider
Other Equipments/Materials
Participated Date: Sign Rew by Date Sign Approved by Date: Sign
BHAVANISHANKA
R [Site manager]
Salim. ka
Habib
[Safety Supervisor]
Ganesh
[supervisor]