ramirocid.com
[email protected] Twitter: @ramirocid
An example of Risk Analysis. In spite of is not mandatory to use it on Lean Six Sigma, it is ever
recommended to do it to get the risks of a new project, environment, change, etc. with the target of
reduce as much as possible the residual risk (the risk after apply controls):
9. Risk Analysis
CIA
factor
value
No dual power source in routers
In case some electric
phase is down the router
will be down
2 routers: Main and backup.
Backup router give service in
less than 10 seconds in case
of the main crash. Both are
connected in different
electric phases
x 1 4 1 4
No dual power source in Colt
fibber convertes in front of routers
In case some electric
phase is down the router
will be down
2 routers: Main and backup.
Backup router give service in
less than 10 seconds in case
of the main crash. Both are
connected in different
electric phases
x 1 4 1 4
Router not accessible by in case
WAN connection crashes
In case WAN connection is
down will not be able to
access to manage the
router
have a management
modem connected by an
analogic line to manage the
router by console port
x 1 1 2 2
Router Buenos Aires John Smith Michael Johnson
Location/s Power user Vulnerability description Threat descriptionExisting Controls/practicesAsset Ris k Owner ProbabilityIm pact
Risk
Value
Assets criticality