Area FasadSelatan (Diding/Kolom/BalokCantilever)
as 1-10/A
RangkaKolom: 1 tim(3 org)
Area FasadSelatan (Diding/Kolom/BalokCantilever)
as 10-14/A
RangkaKolom: 1 tim(3 org)
Area FasadSelatan (Diding/Kolom/BalokCantilever)
as 14-16/A
RangkaKolom: 1 tim(3 org)
Area FasadSelatan (Diding/Kolom/BalokCantilever)
as 16-19/A
RangkaKolom: 1 tim(3 org)
Area FasadUtara (Diding/Kolom/BalokCantilever)
as 1-3/F
RangkaKolom: 1 tim(3 org)
Area FasadUtara (Diding/Kolom/BalokCantilever)
as 5-10/F
RangkaKolom: 1 tim(3 org)
Area FasadUtara (Diding/Kolom/BalokCantilever)
as 10-14/F
RangkaKolom: 1 tim(3 org)
Area FasadUtara (Diding/Kolom/BalokCantilever)
as 14-16/F
RangkaKolom: 1 tim(3 org)
Area FasadUtara (Diding/Kolom/BalokCantilever)
as 16-18/F
RangkaKolom: 1 tim(3 org)
Area FasadTimur (Diding/Kolom/BalokCantilever)
as 16-18/F
RangkaKolom: 2 tim(6 org)
Total Fasade
36 orng

Area as 11-
12/AF
Rangka
balok: 2 tim
(6
org)
Area as 12-14/AE
Rangkabalok: 2 tim(6
org)
Area as 15-
16/AF
Rangkablk :
2 tim(6
org)
Area as 16-
19/AF
Rangkablk:
1 tim(3
org)
Area as
11/AF
Rangka
Dinding: 1
tim(3
org)
Area as 14-15/CD
RangkaDinding: 1
tim(3
org)
Area as 16-
17/CF
RangkaDinding:
1 tim(3
org)
Area as 16-
17/AC
RangkaDinding:
1 tim(3
org)
Area as 11-
16/AF
RangkaKolom:
2 tim(6
org)
Area as 12-15/EF
RangkaDinding: 1 tim(3
org)
Total lt.1
36 orng

Area as6-
7A/F
Rangka: 2
tim(6 org)
Area as9-
10A/F
Rangka: 2
tim(6
org)
Area as15-17A/F
Rangka: 2 tim(6
org)
Area as18-19A/F
Rangka: 2 tim(6
org)
Area as 10-15/B
Rangka: 2 tim(6
org)
Area as 10-15/E
Rangka: 2 tim(6
org)
Area as 6-19/A
Interior : 1 tim(3
org)
Area as 8-9/C
Interior tepitangga:
1 tim(3org)
Area as 8-9/E
Interior tepitangga:
1 tim(3org)
Area as 16-17/B
Rangka: 1 tim(3
org)
Area as 16-17/D
Rangka: 1 tim(3
org)
Area as 16-17/E
Rangka: 1 tim(3
org)
Area as 7-10/AB
Rangka: 1 tim(3
org)
-Total MP rangkabalok
45 orng
-Total MP rangka
dinding
45 orng
Area as 8-9/B
Interior tepitangga:
1 tim(3org)
2 Tim untukRepair dan
Detail Rangka(2 Tim)
=92orng

•Tenaga
-Fasade= 36 Orang
-Interior Lt.1=36 Orang
-Interior Lt.2 = 92 Orang
-Total Tenaga = 164 Orang