Formwork shall include following
Splayed edges, notching, allowance for overlays and passing at angles, sheathing battens,
strutting, bolting, nailing, wedging, easing, striking and removal.
All supports, struts, braces, wedges as well as mud sills, piles or other suitable arrangements to
support the formwork
Bolts, wire ties, clamps, spreaders, nails or any other item to hold the sheathing together
Working scaffolds, ladder, gangways and similar items
Filleting to form stop chamfered edges or splayed external angles not exceeding 20 mm wide to
beams, columns and the like
If required, temporary openings in the forms for pouring concrete , inserting vibrators, and
cleaning holes for removing rubbish from the interior of the sheathing before poring concrete
Dressing with oil to prevent adhesion
Raking or circular cutting
Method of measurement
Formwork shall be measured in square metres as the actual surfaces in contact with the
concrete
Where formwork is required to be lined with wall board, hardboard, polythene sheet
No deduction shall be made for openings up to 0.4sqm. No deduction shall be made for any
opening/cutouts when slip form technique is used.
Raking or circular cutting and rounded or moulded edges shall be measured in running metres.
Moulded stopping shall be enumerated.
Formwork to secondary beam shall be measured up to the sides of main beams, but no
deduction shall be made from the formwork of the main beams where the secondary beam
intersects it.
Formwork to beam shall be measured up to sides of column, but no deduction shall be made
from the formwork to stanchion or column casings at intersections of beam.
Method of measurement of Steel work and Iron work
Part 8
STEEL AND IRON WORK : K. G.
Reinforcement shall be measured to nearest 0.005m.
Dimensions like cross sections to nearest 0.001sqm
STRUCTURAL STEEL :
Normally steel work shall be measured by weight.