Metode Pekerjaan TC Padang Warehouse..pptx

ShantChan 0 views 27 slides Oct 06, 2025
Slide 1
Slide 1 of 27
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27

About This Presentation

Metode Pekerjaan Bongkaran dan Pemasangan Atap CCEP Padang


Slide Content

WAREHOUSE RENOVATION PROJECT ( PHASE 1 ) – PADANG DC KICK OF MEETING

TIME SCHEDULE PADANG

FORMAN CIVIL WORK = 20 PERSON BAJA = 15 PERSON ROOF = 10 PERSON MEP = 10 PERSON SCAFOLDER = 5 PERSON ORGANIZATION CHART

WAREHOUSE RENOVATION PROJECT ( PHASE 1 ) – PADANG DC METHODE

WAREHOUSE RENOVATION CCDI - BANJARBARU PLANT PRELIMINARIES DEMOLITION WORKS STRUCTURE WORKS ARCHITECTURE WORKS MEP WORKS

DEMOLITION, CLEANING & REMOVING ALL DEBRIS Demolish Base On Arch PHASE 1 ( Drawing ) : Brick Wall Existing (1.975M2) Ceiling Including Frame (1.198 M2) Windows &, Door Bird Mes =(87 M2) Metal Roof 452 M2 (Monitor) Metal Clading 76 M2 Tranlusent Roof 232 M2 Gutter FRP (245 M’) Base on Structure ( Drawing ) : Concrete Slab On Ground Warehuse , suspended Warehouse Steel Structure Inlcude Gutter, Flashing Existing Beam & Kolom Base on Electrical ( Drawing ) : Electrical & electronic : Lighting & Installation item to be demolished in dicated with ( red colour )

DEMOLITIONALL DEBRIS, CLEANING & REMOVING ( PHASE 1) Concrete Slab On Groaund Warehouse = 1180 M2 item to be demolished in dicated with ( red colour ) Demolition Lantai beton Pembongkaran Lantai benton lantai 1 menggunakan alat bantu Breaker excavator PC 75 Jack hammer Menyediakan Blower / Exhouse untuk mengurangi debu Pastikan Pekerja yang melakukan pekerjaan diketinggian menggunakan APD lengkap Ex Bobokan dikeluarkan dari Area PT. Coca - Cola

Concrete Slab EL.+3000 & EL +3500= 199 M2 item to be demolished in dicated with ( red colour ) Demolition Lantai beton Lantai 2 Pembongkaran Lantai benton menggunakan alat bantu Jack hammer Menyediakan Blower / Exhouse untuk mengurangi debu Memasang jaring dan Bloesheet diarea lantai yang dibongkar, untuk menghindari material jatuh Pastikan Pekerja yang melakukan pekerjaan diketinggian menggunakan APD lengkap

START DEMOLISH FROM 2ND Floor item to be demolished in dicated with ( red colour ) Brick Wall = 1.972 M2 & Plafond Warehouse = 1.122 M2 To 1ST Floor - Demolish/ Pembongkaran dimulai dari lantai 2 menuju lantai 1

TRAF F IC MANAGEMENT DEMOLIS WALL & PLAFOND TRA F FIC Demolish wall & PLAFOND SITE OFFICE & storage UK 6 x 15 m SCAFOLDING AKSES TOILET pekerja Mengunakan existing ( PERBAIKAN PINTU ) TEMPORARY DEBRIS STORAGE AREA p1

Pembongkaran Wall menggunakan alat bantu Jeck hammer PC 50 Brick Wall = 1.972 M2 & Plafond Warehouse = 1.122 M2 Saat pembongkaran khususnya dinding lantai 2, perlu disipakan jaring & Blue Sheet untuk antisipasi bongkahan puing jatuh Pastikan Pekerja yang melakukan pekerjaan diketinggian menggunakan APD lengkap Ex Bobokan dikeluarkan dari Area PT. Coca - Cola Pastikan Pekerja yang melakukan pekerjaan diketinggian menggunakan APD lengkap Ex Bobokan dikeluarkan dari Area PT. Coca - Cola

DEMOLITION JACK ROOF & SKY LIGHT item to be demolished in dicated with ( red colour ) Menyediakan Scafolding Akses Memasang Life Line & Angkur Point temporary sebelum melakukan pembongkaran Atap, Temporary Life line perlu di Inspeksi oleh Inspektor yang memiliki TKPK tingkat 3 sebelum digunakan oleh Para pekerja Pastikan Pekerja yang melakukan pekerjaan diketinggian menggunakan APD lengkap dan sudah mengikuti Training Work At Hight Menyediakan Blue Sheet untuk antisipasi saat hujan Scafodling Akses Selling 10mm Angkur Point Blue Sheet Crane 25 T

DEMOLITION SKYLIGHT, GUTTER, FASCIA item to be demolished in dicated with ( red colour ) Scafodling Akses Scafodling Akses Selling 10mm Angkur Point

NEW CONSTRUCTION WORKS ( BASE ON BOQ PHASE-1) Roof & Finish New Wall & Finish Doors & Windows Floor Finish ( Refer to Drawing & BOQ) 5. Fitting & Miscellaneous ( Refer to Drawing & BOQ) Steel Structure ( Perkuatan Kolom & Rafter ) Slab Concrete Roof Steel Structure ( Purlin dll ) Electrical Installation Mechanical Work Testing & Commissing 1. STRUCTURE WORKS 2. ARCHITECTURE WORKS WORKS 3. ELECTRICAL WORKS

Steel Structure Warehouse item to be New Concrete Slab in dicated with ( blue colour ) STRUCTURE WORKS

Steel Structure ( Perkuatan Kolom) Persiapan Install Scafolding Mobile Alat bantu Angkat / Chain block 2 Ton Scissor Lift/ Boom Lift Fire Blanket Apar 3kg APD METHODE Pekerjaan Perkuatan Kolom, rafter, Beam & Painting dengan Alat bantu Scafodling Mobile dan Scissor lift/ Boom lift untuk area yang tidak bisa dijangkau oleh Scafodling . Lifting material Plat secara manual dengan menggunakan alat bantu Chain Block 2 Ton . Kontraktor memasang fire blanket pada area kerja pengelasan , dan menyediakan Apar Pastikan Pekerja menggunakan APD lengkap

Methode Steel Structure ( Perkuatan Kolom & Rafter, Painting ) Alat bantu Angkat / Chain block 2 Ton Hasil Pemeriksaan dan Pengujian

Methode Steel Structure ( Perkuatan Kolom & Rafter, Painting ) Scafolding Mobile , Sebagai akses naik dan turun pekerja Scafolding , Sebagai landasan /platform support material & pekerja

Methode Steel Structure ( Perkuatan Kolom & Rafter, Painting ) Scissor/ Boom lift , sebagai alat bantu kerja . Untuk pekerjaan Perkuatan Rafter dan Painting pada area yang sulit dijangkau

Crane 25 T item to be demolished in dicated with ( red colour ) Menyediakan Scafolding Akses Memasang Life Line & Angkur Point temporary sebelum melakukan pembongkaran dan pemasangan New Jack Roof Pastikan Pekerja yang melakukan pekerjaan diketinggian menggunakan APD lengkap dan sudah mengikuti Training Work At Hight Menyediakan Blue Sheet untuk antisipasi saat hujan Crane 25 Ton , untuk lifting material Atap & jack Roof Scafodling Akses Selling 10mm Angkur Point Blue Sheet New Steel Structure Jack Roof

SIMULASI BONGKAR DAN PASANG NEW JACK ROOF

Scafodling Akses Scafodling Akses Temporary Life Line Blue Sheet item to be New Concrete Slab in dicated with ( blue colour ) ARCHITECTURE WORKS New metal Roof Include Fascia = 498 M2,Translucent Roof : 48 M2, Gutter = 245 M’ Down Pipe = 298 M’ Crane 25 Ton Sebelum memulai pekerjaan pembongkaran atap pastikan Kontraktor menyediakan Blue Sheet di Area atas Atap dan Blue Sheet pada area bawah untuk menutup produk supaya terhindar dari cahaya panas dan debu saat pembongkaran atap Menyiapkan temporary Lifeline yang sudah diinspeksi oleh TKPK 3

SIMULASI LIFTING & BONGKAR PASANG SKYLIGHT

New Concrete Slab Warehouse = 1180 M2 Pekerjaan Sub Structure lantai seperti, Soil Treatmen CBR 5%, Basecoure + CBR 60%, Sand bedding, Termite treatment Lapisan lantai kerja tbl 50mm K-125 Lapisan Wire Mesh M 12 – 150 Double Layerd + Dowel Lantai Beton tbl 250mm K 250 Pengecoran lantai menggunakan Ready Mix dan Concrete Pump Finishing Lantai Trowel & Hardener Saw cut include Joint Sealant item to be New Concrete Slab in dicated with ( blue colour )

Demolition Wall & Plafond Start dari lantai 2 Pembongkaran Wall menggunakan Scafolding dan alat bantu Jeck hammer Saat pembongkaran khususnya dinding lantai 2, perlu disipakan jaring & Blue Sheet untuk antisipasi bongkahan puing jatuh Pastikan Pekerja yang melakukan pekerjaan diketinggian menggunakan APD lengkap Ex Bobokan dikeluarkan dari Area PT. Coca - Cola New Wall & Finish

HEAVY EQUIPMENT Heavy Equipment For Works : Scafolding Main Frame untuk ketinggian maximal 3 M’ Scafolding Tubulard untuk ketinggian diatas 3M’ Crane 25 ton Scissor Lift/ Boom Lift Fibro 10 Ton Jack Hummer Breaker Excavator PC 75 Concrete Pump Chain Block 2 Ton Stamper Kuda dll

SAFETY CONTROL Safety Control : HSE TEAM : HSE REPRESENTATIVE & SAFETY MAN HSE PLANT HSE REPORT HSE PATROL METHODE / INSTRUKSI KERJA : JSA, HIRADZ, TRAFFICE MANAGEMENT, SIMULASI TANGGAP DARURAT, METHODE SCAFOLDING,METHODE LIFE LINE KERJA DIKETINGGIAN DLL SAFETY TOOLS
Tags