National Electricity Demand and Projections

hossainec 7 views 16 slides Aug 22, 2024
Slide 1
Slide 1 of 16
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16

About This Presentation

Presenationon


Slide Content

Country Presentation
(Bangladesh)


M. Khalaquzzaman, PhD
Bangladesh Atomic Energy Commission
INPRO Dialogue Forum 11 “Roadmaps for a Transition to Globally Sustainable Nuclear Energy Systems”
October 20-23, 2015

Country Overview
National Electricity Demand and Projections
Current Status of Nuclear Power Program


Outline
2

Country Overview
Area : 147,570 sq. km.
Population : 159 Million (appx.)
GDP : $174 billion USD,
(2014)
GDP Growth : 6.1%
Electricity demand growth : 7%
(appx.)

3
Commercial Energy Resources:

Natural Gas: 20 TCF
Coal : 884 MM Tones
Hydro : 800 GWh

Generation Capacity by Fuel
Total 9821MW (Yr. 2014)
Gas, 61.26%
Furnace Oil,
20.87%
Diesel, 8.40%
Coal, 2.04%
Hydro, 2.34%
Import power,
5.09%
4
Gas, 72.42%
Furnace Oil,
15.44%
Diesel, 2.91%
Hydro, 1.39%
Coal, 2.46%
Imported Power,
5.37%
Total 42195 GWh (Yr. 2014)

0
5000
10000
15000
20000
25000
30000
35000
40000
2010 2015 2020 2025 2030
MW

Year
Government Policy GDP 7%
GDP 6%
Electricity Demand Forecast
Source: Power System Master Plan 2010
5

Power Generation-mix
6
Considering the fuel diversification issue, the Power
System Master Plan-2010 aims to acquire the fuel mix as
follows:
• Coal 50% (30% domestic coal and 20% imported
coal),
•Natural gas 25% (including LNG),
• Liquid fuel 5% and
•Nuclear 20% (including renewable and cross-border
trade)

7
Current Installed capacity: 11,877 (as of October 2015)
Peak Load : 8000 MW
Energy Target
Current (%) 2021(%) 2030 (%)
Gas 72% 30 28
Coal 2.46% 53 38
Oil 18.35% 3 5
Hydro 1.39% 1 4
Nuclear 0 10 19
Renewable - 3 6
Proposed Power Generation-mix (contd.)

B a y o f B e n g a l Proposed
Power
plant
Location
Ganges
Gorai
Proposed Power plant
Location
Ganges
Gorai
LOCATION OF THE RNPP SITE
AREA Project Site Area : 105 Hectare
Residential Area : 13 Hectare

8
8

9
National Energy Policy, 1996: Nuclear energy was
considered as a energy supply source of generation-mix
approved by the Govt.
Bangladesh Nuclear Power Action Plan (BANPAP) was
approved by the Govt. in 2000
Nuclear power has been included in the Power System
Master Plan (PSMP)-2010
Government’s Commitment for NPP

Nuclear Energy Planning
10
A decision for implementation of the Rooppur NPP was
approved by the parliament in 2010;
•Perspective Plan of Bangladesh: 2010–
2021 and PSMP- 2010 outlined:
Medium
range
plan
•Construction of 2000 MW Rooppur
NPP by 2021;
•Additional 2000 MW by 2030;
Capacity

11
Nuclear Energy System Collaboration Strategy
Inter-governmental Agreement (IGA)between Russia
and Bangladesh in 2011 for installation of 2x1000 MWe
VVER

•Designing
•Construction
•Operation
•Spent Fuel Management
Co-operation in the following areas:

Fuel Cycle
No activities associated with nuclear fuel
cycle that are not under the IAEA safeguards
Nuclear fuel in the form of ready fuel
assemblies
Front-end fuel cycle
Returning the nuclear spent fuel to the
supplier

12

13
Implementation of NPP Project
•The “Bangladesh Atomic Energy Regulatory Act-2012”
passed by the government;
•An independent nuclear regulatory authority was
established
• An bilateral Agreement on cooperation in nuclear and
radiation safety was signed in February 2012 between
the Nuclear Regulatory Authority, Russian Federation
and the MOST, Bangladesh;
•Nuclear Power Plant Act 2015 was passed by
government and NPP operating organization is
established
Nuclear Power Plant Company Bangladesh Limited
(NPCBL) was established

The preparatory phase of construction activities of the
first NPP, “Rooppur NPP” has already been started;
Development of the second NPP project at the
Southern Part of the country is in active consideration
of the government.
Implementation of NPP Project
14
◦Contract I : Feasibility Evaluation and EIA
◦Contract 2 : First priority working documentation and
engineering survey for the design stage of
Rooppur NPP
◦Contract 3 : Performance of first priority Works for the
Preparatory stage of Rooppur NPP
construction.

Thank You !
16
Tags