power plant boilerModular-Erection-Boiler.pptx

AJAYSINGH367 86 views 44 slides Jun 26, 2024
Slide 1
Slide 1 of 44
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44

About This Presentation

Boiler erection


Slide Content

Modular Erection Strand Jack Lifts Note : This Presentation Is made purely for the training purpose only, This is not a procedure or sequence document and does not refer to any project site. The photos and drawings shown in the presentation are the property of MHI, LMB, TPPC. Usage, Copying and Reproducing is not allowed without prior notice to the concerned organizations

Boiler Modular Erections Ceiling Girder block – 16 x 300MT Strand Jacks Nose Block – 16 x 185MT Strand Jacks Eco Hopper Block – 6 x 185MT Strand Jacks Intermediate Headers Front – 4 x 185MT Strand Jacks Left Side – 2 x 185MT Strand Jacks Right Side – 2 x185MT Strand Jacks Coal bunker – 4 x 185MT Strand Jacks

` Ceiling Girder Block

Ceiling Girder Block – 16 x 300MT Strand jacks Final Weight of Ceiling Girder Block- 2950MT

Pre-Assembly of Ceiling Girder – G outside The Boiler With 250MT crane JAYPEE Site photo:

Pre-Assembly of Ceiling Girder – F outside The Boiler With 250MT crane Ceiling Girder Pre-assembly Scheme:

Pre-Assembly of Inter Connecting Beams Between Girder (F-G) and alignment at outside The Boiler With 250MT crane Inter Connecting Beams (F-G)

Pre-Assembly of Inter Connecting Beams(Cantilever) Between Girder (E-F) and alignment at outside The Boiler With 250MT crane Inter Connecting Beams (E-F)

Move the assembly inside the Boiler Using Skidding system Skidding System

MHI Photo Hanger Support Beam Between Girder E-F Hanger Rod Assembly of Roof Inlet Header Hanger support Beams Between Girder F-G Hanger Rod Assembly of Front Wall outlet header Roof Inlet Manifold 2ry SH Panels, Inlet, Outlet headers Side Wall outlet Header 1ry,2ry DSH Outlet Pipe 3ry SH Element tubes Roof inlet pipe Temporary Support For Buck stay

Positioning of Ceiling Girder - H inside The Boiler With 250MT crane

Positioning & alignment of Inter Connecting Beams Between Girder (G-H)

Positioning of Ceiling Girder - J inside The Boiler With 250MT crane

Positioning & alignment of Inter Connecting Beams Between Girder (H-J)

Positioning & alignment of Inter Connecting Beams(Cantilever) Between Girder (J-K)

Skidding of Ceiling Girders into Boiler well in progress

Ceiling Girder Skidding in progress from the front side

Ceiling Girders skidded to position

All Hanger Support Beams All Hanger Rod Assemblies

Erection of Column 7 in K-Grid & Beams between 7 to 8A

Erection of K-K1 Grid @ 43.065m

Erection of K-K1 Grid @ 54.365m

Erection of K-K1 Grid @ 69.015m

Erection of K-K1 Grid @ 82.300m

Alignment of Columns & Bolt tightening Erection of Enabling Structures Positioning of Strand jacks

1 st Jack-up Preparation of Line making for Pipe placement Installation of hanger Rods Assembly

1 st Jack-down Installation of Hanger Collector Beams DSC00090

Eco hanger tubes 3ry SH,2ry RH & Collector Beams

2ry, 3ry SH Roof Panels Headers

1 st Part Buck stay Temporary Fixing 1 st part Jack-up

2 nd Part Buck stay Temporary Fixing 2 nd part Jack-up

3 rd Part Buck stay Temporary Fixing 3 rd part Jack-up

4 th Part Buck stay Temporary Fixing 4 th Part Jack-up

2ry RH Roof Panel 1ry RH Roof Panel 1ry SH Roof Panel Furnace Real wall Hanger Tubes Back Pass Front wall Upper panels Divisional wall upper panels

Final jack-up

Girder Connection Bolt Tightening

Removal of Enabling Structures

Ceiling Girder Connecting Beams (Left-out Structure)

CEILING GIRDER BLOCK PHOTOS

DURING LIFTING

CEILING GIRDER – REACHING POSTION

CEILING GIRDER – REACHING POSTION

CEILING GIRDER – FINAL POSTION
Tags