2. Utility Shifting : Water Supply pipelines : Completed Electrical utility : DoP (T&G) – Completed, DoP (D & R) – Completed 3. Other Issues: NOC is received from DC, Kohima for 11.454 Km on 19.02.2024 with remarks- 1.920 Km is sub-judice. However, Writ Petition (Civil) No. 50/2022 involving the land acquisition issues filed by the land owners at Hon’ble Gauhati High Court, Kohima Bench was heard for final hearing on 18.11.2024 and it has been disposed off on 29.11.2024 with a direction to the respondents to take steps for payment of fair & just compensation to the landowners. Approval of Annulment of Realignment stretch affecting 1.15 Km has been approved by HQ NHIDCL on 08.04.2024 and the same has been conveyed to Contractor on 13.04.2024. P & P in accordance with the scope as per CA is yet to be submitted by contractor till date and therefore, is yet to be got approved by the AE for Km 40+580 to Km 43+454. Moreover, a meeting was convened on 18.12.2024 with AE, contractor, PMU & RO for last 3 km to discuss the EPC Contractor ‘s Claim of COS for 2 nos. of Bridges and 1 Nos. Viaduct, however, any clear-cut response in this regard is still awaited. During site visit of the Hon’ble Chief Secretary, GON on 18.01.2025, it has been directed to complete the road stretch from Km 32+000 to Km 35+000 for vehicular movement. 4. Issues with Contractor: The Contractor has filed the Petition of Arbitration Claim under Section 17 on 15.09.2023, for seeking interim measures of protection. Last hearing regarding arguments on Section 17 was held on 04.03.2024 and the same has been disposed off on 04.03.2024. The proceedings for recording of evidences has been conducted on 31.07.2024 and next date of recording of evidences has been scheduled on 05.02.2025. Despite repeated reminders, the Damaged PMGSY Road (Ch. 40+300) affected in a length of 0.060 Km is not yet taken up by EPC Contractor for restoration. Despite repeated reminders, Contractor yet to start Landslide Mitigation measures at the landslide prone stretches. At Ch. 33+900, a minor bridge ( COS) is required at site instead of culvert as per CA. The separate proposal is initiated by contractor and currently with the AE. The progress of the Contractor was being monitored as agreed during meeting held on 21.10.2024 under the chairmanship of the Hon’ble Minister, RT&H for next two months. Accordingly, in failing to achieve any substantial progress, the EPC Contractor has been served Notice for Intention to Terminate the Contract on 18.01.2025. Action Taken The local hindrances were discussed with the DC, Kohima, Deputy CM, Nagaland during meeting on 16.10.2024, with the Hon’ble Minister, RT&H during meeting on 21.10.2024, with the Revenue Officer, DC office, Kohima on 13.01.2025 and with the Hon’ble CS, GoN during meeting on 18.01.2025 for resolution of Hindrances. Furthermore, a joint verification is scheduled on 07 th Feb’2025. EPC Contractor declared as Non-Performer on 07.03.2023. Fresh Cure Notice period for 60 days under Cl. 23.1(i) of Contract Agreement has been issued to the EPC Contractor on 24.06.2024. However, the Contractor during meeting held under the chairmanship of Dir (T), HQ, NHIDCL requested for extension of cure period. The same is also requested by EPC Contractor vide their letter dated 21.08.2024. PMU in this regard has forwarded a letter to RO-Kohima on 22.08.2024. During meeting held on 21.10.2024 under the chairmanship of the Hon’ble Minister, RT&H, it has been directed to closely monitor the progress and to take suitable action, if no substantial progress is observed in next two months. The EPC Contractor has been served Notice for Intention to Terminate the Contract on 18.01.2025. AE has been directed to prepare the schedule for balance works, which shall be submitted after taking a decision on the matter. Status as on: 27.01.2025 14. Name Of Project: - Construction of two lane with paved shoulder of Kohima-Bypass Road connecting New NH-02 and New NH-29 from design km 32.000 to km 43.454 in the state of Nagaland under SARDP-NE on EPC mode (Package-IV) Milestone I II III Completion Req. Progress 10% 35% 70% 100% Schedule 25.04.2021 09.09.2021 25.01.2022 17.04.2022 Extended 13.03.2022 01.07.2024 16.11.2024 06.02.2025 Actual 13.03.2022 Not achieved Not achieved Not achieved Progress (%) As on date One month ago 6 months ago Physical 27.58 26.96 26.90 Financial 25.04 25.04 23.27 Revenue Land (ha) 3A date 3D date Compensation amount with CALA (LA+ Dmg. Compen) Amount disbursed Land Made available Mutation status 42.06 NA 37.23 Cr 32.38 Cr 42.06 Ha Yet to be done Forest Land (ha) Stage-I date Working permission date Total no. of trees Trees felled Un- encumbered Land available Stage -II status No Forest Land Involved. NA Total Un- encumbered length (ROW) available for construction As on Appointed Date Today Date of 100% length availability 0.00 Km 11.454 Km [Including sub-judicious stretch of 1.920 Km (now disposed off)] 19.02.2024 (As per NOC) 25 Major Structures Design / Drawing Status Foundation Sub-Structure Super-structure Minor Bridge (1 nos.) Approved 00/00/ 01 no 00/ 00/ 04 no 00/ 00/ 03 span Major Bridge (1 nos.) Approved 00 /00/ 03 no 00 / 00/ 03 no 00/ 00/ 02 span Viaduct (….nos.) - - - - ROB/RUB (…..nos.) - - - - 1. Land Acquisition & Forest Clearance :- Scheme SARDP-NE Contractor M/s Pele Khezhie Authority’s Engineer M/s CEMOSA(JV) PCPL in Association with M/s Nexgen Infra Solution PMU Jakhama TPC & AAFS Date Rs. 202.36 Cr. dated 31.07.2020 Awarded Cost Rs. 118.56 Cr. (excl. GST) Date of LOA 14.08.2020 Appointed Date 15.10. 2020 Schedule / Likely Completion 17.04.2022 / 31.03.2026 Contract Length 11.454 Km DELAYED Broad Scope of work :- (Completed/Ongoing/Total) Construction Targets vs Ach. For F.Y 24-25 : 2.530 / 1.030 KM Total Comp. Ong. Total Comp. Ong. Formation Cutting 11.45 Km 8.100 0.100 Seeding and Mulching 21020 Sq.m 3500 Sub-grade 11.45 Km 7.900 0.200 Culverts 67 16 02 GSB 11.45 Km 6.178 0.400 Drain 11.456 2.090 0.100 WMM 11.45 Km 4.200 0.500 Retaining Wall 100 100 00 DBM 11.45 Km 2.500 0.00 Breast Wall 2890 905 00 BC 11.45 Km 0.260 0.00