Kearney XX/ID
1
Arteries of New India -Highways and Roads to the Future

Kearney XX/ID
2
Corridor Name: Jodhpur Ring Road Section-I
Feature Information
Name of Concessionaire
M/s JRR Highway Pvt.
Ltd.
Length (km) 74.619 Kms
Total Awarded Cost (INR Cr.) 1161 Cr/ 1308 Cr
Appointed Date 14.12.2018
Schedule Date of Completion
& EOT
12.12.2020 /
12.02.2024
Physical Progress (%) 55.075%
Financial Progress (%) 55.075%
Possession (km) 74.244 Km (99.50%)
Hindrances (km)
0.375 Kms(0.50%)
In Scope Subgrade Top GSB DLC/WMM PQC/DBM SMA/BC
74.619 (MCW) 49.420 45.012 43.872 39.711
68.510 (SR) 52.483 46.665 38.870 38.730 2.11
Progress of PQC (in km)
Overall Progress of Package
Structure In Scope Completed In Progress Target Completion
Service Road (km) 51.400 2.110 44.690 Feb-24
Slip Road 17.110 - 12.580 Feb-24
Major Bridge 1 - 1 Oct-23
Minor Bridge 4+2 1+1 2+0 May-23
Fly Over 9 - 9 Jan-24
VUP/ LVUP
VUP-1
LVUP-6
VUP-1
LVUP-6
- Completed
ROB 2 - 2 Sept-23
Culverts 121 104 17 May-23
Bus Bays & Bus Shelters 36 - 29 Feb-24
Truck Lay Bay 3 - 3 Feb-24
Toll Plaza 2 - 02 Feb-24
Major / Minor Junction 4+66 - - Feb-24
Progress of Major Structures

Kearney XX/ID
3
Corridor Name: Jodhpur Ring Road Section-II
Feature Information
Name of Concessionaire
M/s SpetsdorstroyLCC -
OSS Construction Pvt.
Ltd. (JV)
Length (km) 30.093 Kms
Total Awarded Cost (INR Cr.) 298.78 Cr/ 675 Cr.
Appointed Date 29.08.2022
Schedule Date of Completion
& EOT
28.08.2024
Physical Progress (%) 27.50%
Financial Progress (%) 22.24%
Possession (km) 27.553 Km (91.56%)
Hindrances (km)
2.54 Kms (8.44%)
In Scope
(BHS in KM)
Earthwork up
to top of the
sub-grade
GSB/CTSB WMM DBM SMA/BC
30.093 22.8 5.98 - - -
Progress of DBM (in km)
Overall Progress of Package
Structure In Scope Completed In Progress Target Completion
Service Road (Both side)15.820 0 0 Aug-24
Culverts 54 49 3 Aug-24
Bus Stand 1 0 0 Aug-24
ROB 1 0 0 Aug-24
Flyover 2 0 1 Aug-24
VUP 7 0 7 Aug-24
LVUP 2 0 1 Aug-24
BUP 2 0 2 Aug-24
Minor Bridge 1 0 1 Aug-24
Toll Booths 22 0 0 Aug-24
Interchange 1 0 1 Aug-24
Progress of Major Structures