PUBLIC WORKS
Presented by:
Frank Orta
Public Works Director
STAFF REPORT
2026 STREET MAINTENANCE PROGRAM (SMP) PROJECTS
ITEM # 13
OCTOBER 27, 2025
SUMMARY
Council budgeted $1.2 million for street & sidewalk
improvements for the 2026 Street Maintenance
Program (SMP)
Agreement with Mendez Engineering for engineering
design & project management services
2026 SMP proposal of road rehabilitation consisting
of 9 project areas (5 streets and 4 Alleys)
BACKGROUND
SMP projects identified in conjunction with the 4x2 /
Water Main Relocation effort and new alley
maintenance program
Mendez Engineering proposal for bid and project
management accepted October 2025
Construction bid award for 2026 will be brought back
to council for consideration in March 2026
2026 SMP PROJECT LOCATIONS -STREETS
Claywell Dr. –Broadway to New
Braunfels Ave.
E. Oakview Pl. –Broadway to New
Braunfels Ave.
E. Edgewood Pl. –Broadway to
New Braunfels Ave.
E. Elmview Pl. –Broadway to New
Braunfels Ave.
*Add Alternate: Vanderhoeven Dr. –
Claywell Dr. to 50’ South of E.
Elmview Pl.
Claywell
Oakview
Edgewood Elmview
*Vanderhoeven
Broadway
New Braunfels
2026 SMP PROJECT LOCATIONS -ALLEYS
Between Blue Bonnet Blvd. and
Redwood St. –Henderson St. to
New Braunfels Ave.
Between Harrigan Ct. and
Katherine Ct. –Broadway to New
Braunfels Ave.
Between Katherine Ct. and Burr Rd.
–Broadway to New Braunfels Ave.
*Add Alternate: Between Albany St.
and Montclair St. –Broadway to
Ashcroft Ave.
Blue Bonnet/
Redwood
New Braunfels
*Albany/
Montclair
Harrigan/
KatherineKatherine/
Burr
Broadway
TIMELINE & NEXT STEPS
Plans, Specifications, and Estimates to be completed
by Mendez Engineering by end of December 2025.
Projected to be advertised in January with a bid
opening in February 2026.
Projected contract award March 2026.
Three-month estimated construction duration (April to
June 2026.)