PPT, PIU Ratlam_8-lane Delhi-Mumbai Expressway

venkateswararaoPothi1 362 views 57 slides Jan 09, 2024
Slide 1
Slide 1 of 57
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47
Slide 48
48
Slide 49
49
Slide 50
50
Slide 51
51
Slide 52
52
Slide 53
53
Slide 54
54
Slide 55
55
Slide 56
56
Slide 57
57

About This Presentation

PPT for Delegation from MORTH


Slide Content

8-Lane Delhi-Mumbai
Expressway
WELCOME
Respected Guests
Delegation from MoRTH
Site Visit On 26
th
-27
th
August 2022
:-:
NHAI-PIU, Ratlam
1

Delhi Mumbai Expressway (NE 4)
Length = 1350 Km
Travel Time = 12 Hours
(Existing Route Travel Time = 22 Hours)
MP State Section (NE 4)
Length = 244.50 Km (9 Nos. Pkgs)
Travel Time of MP section = 2:15 Hours
Presently Constructing to 8 Lanes
Future Expansion upto12 Lanes
DM Expressway
2

Location MAP
3

Route Plan for visit of MoRT&H Delegates to
Delhi-Vadodara Expressway on 26 & 27-08-2022
4

5

6

Package Wise EPC Cost
7244.50 8204.438437.1135.097Total
P-17
P-23
P-24
P-25
21.05 GRIL 820.55 847.00
23.15 GRIL 952.33 996.27
Awarded
EPC Cost
(Rs. Crores)
Estimated
EPC Cost
(Rs. Crores)
EPC
Contractor
Length
Km
Cost/ Km
(Rs. Crores)
Pkg No.
32.00 MKC
25.30 GRIL 1010.21
973.78 1094.97
840.00
743.89
888.42
1047.00
884.00
880.62
736.67
919.63
1022.22
P-18
P-19
P-20
P-21
P-22
33.00
29.50
25.30
30.20
25.00 L&T
GRIL
MKC
GHV
GRIL 990.97
993.01
41.38
40.24
43.04
27.63
33.18
28.47
29.40
32.81
39.72

Package Wise Main Work
8Package
No.
Length
Km
Road
Length
(Km)
Structure
Length
(Km)
Major
Bridge
(Nos.)
Minor
Bridge
(Nos.)
ROB
(Nos.)
Inter
change
(Nos.)
Under
pass
(Nos.)
Overpass
(Nos.)
Culverts
Nos.)
Fee Plaza
(Nos.)
WSA
(LHS+RHS)
(Nos.)
Tree
Plantation
(Nos.)
Slope
Protection
(Km)
P-1732.030.81.26130 131 066 1 07400019.4
P-1833.031.41.67170 224 269 1 27000022.7
P-1929.528.21.34130 120 271 1 26880013.3
P-2025.323.41.98120 014 051 0 05900013.8
P-2130.228.91.31101 321 061 2 26700020.0
P-2225.023.21.94261 214 141 1 0620008.5
P-2325.322.03.39300 09 456 0 25100016.0
P-2421.118.72.415140 06 549 0 04400015.0
P-2523.220.82.311150 114 246 1 44900015.6
Total244.5227.317.2651502 1015316510 7 12544800144.4

Package Wise Progress
9
PkgNo.EPC
AD
Start Date
Orig.
Day
OSC
Date
EOT
Days
Revis
Date
2019 2020 2021 2022
Total
Length
Km
Length
Compltd
Fin.
%
Phy.
%
Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct Nov Dec Jan Feb Mar April May June July Aug Sept Oct Nov Dec
P-17MKC7.10.207307.10.220 31.12.22 32.0030.38286
P-18GRIL7.2.20730 5.2.2232831.12.22 33.0033.09095
P-19MKC5.11.207304.11.220 31.12.22 29.5027.67376
P-20GHV6.12.197304.12.21180 211.22 25.3022.78789
P-21GRIL10.12.197304.12.2128721.9.22 30.2030.29294
P-22L&T20.11.2073019.11.220 31.8.22 25.0024.99899
P-23GRIL29.5.2073028.5.2220621.12.22 25.3019.97475
P-24GRIL5.3.20730 4.3.2225414.11.22 21.0521.09293
P-25GRIL5.3.20730 4.3.2225414.11.22 23.1521.58688
Total 244.50231.18688
Original Period Extended Period Time Lapsed

MP Section Progress
10MP Section UnitScope Completed
% age
Completed
Road Length Km 227.3 218.1 96
Structure LengthKm 17.2 12.9 75
Total Km 244.5 231.1 94
Major Bridge Nos. 65 48 74
Minor Bridge Nos. 150 137 91
Interchange Nos. 10 10 100
ROB Nos. 2 2 100
Underpass Nos. 152 151 99
Overpass Nos. 16 11 69
Total Nos. 395 359 89
WSA Nos. 12 5 42
Fee Plaza Nos. 7 6 86
Total Nos. 19 11 64

MP Section Completion Schedule
Start Date –6 Dec 2019
Completion Date –31 Dec 2022
Dates from First Award to Last Completion
11

Unique Features
1. Perpetual Flexible Pavement
2. Latest ATMS
3. World Class WSA / Fee Plaza
4. Automatic Drip Irrigation System
5. Plantation Scheme
6. Proposed Art work on sidewall in hill cutting
7. Rainwater Harvesting
8. Slope Protection with Geo-Cell and Turfing
12

1. Perpetual Flexible Pavement
1.DesignandBuildPavementthatnotfailinfatigueandhavelonger
structurallife,thusattaining“Perpetuality”andhencereferredas
PerpetualPavement.
2.Designedon‘EnduranceLimit’(RepetitiveStress)andNoton
‘TrafficCalculation’(PCU)
13

Minimum Crust of Perpetual Pavement
Pavement Layer
Pavement
Type
Crust
Layer Thickness (mm)
SMA asWearing Course
Perpetual
50
Bituminous Base Course (DBM) 250
Non-Bituminous Base Course (WMM) 150
Sub-Base Course (GSB) 200
Subgrade 500
14

SMA Air Voids
15

Perpetual Vs Conventional Pavement
Technical
Properties
Perpetual Pavement Conventional Pavement
Design CriteriaMechanical design basically computes
and checks the sufficiency of the
mechanistic response in terms of
maximum horizontal tensile strains at
the bottom of the lowest HMA layer and
the maximum vertical compressive
strains on top of sub-grade.
Conventional pavement based
on the 1993 AASHTO pavement
design guide, thickness of the
pavement depends on the
increasing traffic resulting overly
conservative cross-section and
unnecessary added cost.
Deterioration
Rate
Deterioration rate is low w.r.t. age. High compared to perpetual
pavement.
Failure
Mechanism
Top down longitudinal cracking. Bottom up fatigue cracking.
ReconstructionOnly time to time rehabilitation required.Reconstruction required after a
certain period of time.
Use Delay CostLower due to shorter work zone periods
and off-peak period constructions.
Higher.
Layer
Specifications
Layer are well defined and each layer
has its own purpose.
Layer are not well defined.
16

SMA Vs BC
Properties SMA BC
Definition SMA is a gap graded mix which contains more
amount of coarse aggregates hardly bonded by
matrix consisting of filler, bitumen, fine
aggregate and stabilizing additives (Cellulose
Fiber).
BC consists of well graded coarse
and fine aggregate, filler and
bitumen.
Visual Surface Skelton Smooth
Prefer Uses Very Heavy Traffic Medium to Heavy Traffic
Pavement Name Long Life Perpetual Flexible Flexible
Mix Bitumen, Coarse Aggregate, Fine Aggregate,
Filler, Anti Stripping Agent, Stabilizing Additives
Bitumen, Coarse Aggregate, Fine
Aggregate, Filler, Anti Stripping
Agent
Type of Binder VG-30, VG-40, MB, PMB VG-30, VG-40, MB, PMB
Binder content by weight
of mix (%)
>5.8% >5.2%
Coarse Aggregate (%) 75% –80% 50%-60%
Fine Aggregate (%) 20% –25% 40% –50%
Filler Content (%) by
weight of aggregate
At least 2%
Hydrated Lime OR Rock Dust.
At least 2%
Cement/Hydrated Lime/Rock Dust
Stabilizing Additives by
weight of mix (%)
Minimum 0.3% Nil
Air Voids (%) 4% 3% –5%
Layer Thickness, mm 40mm –75mm 30mm –50mm
17

2. Latest ATMS –Equipped with Solar
1.TrafficMonitoringCameraSystem atSpacingof@1Km
2.VehicleSpeedDetectionSystemEquip.atSpacing@1Km
3.EmergencyCallBox atSpacing@1Km
4.VideoIncidentDetectionSystemEquip.atSpacingof@5Km
5.VariableMessageSigns atInterchange/FeePlaza
6.PortableVMS 1No.ineachPkg.
7.ControlCentreforall9Pkg.(P-17toP-25)1No.InP-21
18

Latest ATMS
Traffic Monitoring Camera
System at Spacing of @ 1 Km
Motion Détections surveillance
camera, hooter alarm with
beacon, and all-in-one solar street
light.
19

Latest ATMS
VideoIncidentDetection
SystemEquip.atSpacing
of@5Km
VIDSCamera-3perlocation
20

Latest ATMS
VehicleSpeedDetection
SystemEquip.atSpacing
@1Km
VehicleActuatedSpeed
Display(VASD)System(one
eachforeachlaneineach
direction+shoulder)with
Solar
21

Latest ATMS
VariableMessageSigns
neartoInterchange/Fee
Plaza
True Colour High Pitch
VMS Message Sign -M
Type) (5000mm x 2000m)
22

Latest ATMS
ControlCentreforall9
Pkg.(P-17toP-25)
1No.inP-21
VideoWallDisplay
23

3. World Class WSA
1. Dormitory
2. Motel
3. Travel Desk
4. Dhaba
5. Petrol Pump
6. Restaurant
7. Repair and
Maintenance
8. Trauma
Center
9. Helipad
10 Parking
11. Others
24

Toll Plaza –All Lane Hybrid ETC
Pkg-25
On Loop/
Ramp
Pkg-21
On Full
MCW
25

4. Drip Irrigation System
Solar Based Drip
Irrigation System
26

5. Plantation Scheme
27

Plantation Cross section
28

Plantation Scheme
29

Transplantation
30
Package-24

Transplantation
31
Package-24

32
Plantation Scheme

33
Plantation Scheme

Imli
Bargad
Mango
Mahua
Jamun
Neem
Arjun
Chirol
Peepal
34

6. Rain Water Harvesting
At every 500m
in the entire
length
35

Innovative Tech./ Method
1.Hydraulic Post Driver for MBCB
2.Shear Line Machine for TP Road Marking
3.Centeralized Bar Bending Cutting
4.Precast Segments for Box Culvert
5.Precast Girder, Beam, Plank
6.Slipform Paver for RCC Crash Barrier
7.Slope Protection with Geocell
8.SMA Density Checking By PQI
9.Expansion Joints Installation
36

1. Hydraulic Post Driver for MBCB
37

2. Shear Line Machine for TP Marking
38

3. Centeralized Bar Bending Cutting
39

4. Precast Segments for Box Culvert
40

5. Slipform Paver -RCC Crash Barrier
41

6. Precast Bridge Girder, Beam, Plank
42

7. Slope Protection with Geocell
Embankment Slope Protection –Geocell +Turfing
43

8. Expansion Joint Installation
1 2
5
3
6 7 8
4
44

Expansion Joint Installation
45

Field Tests
46

SMA Density Checking by PQI
47

Camber Checking
48

Side Slope Checking
49

Median Slope Checking
50

Ultrasonic Pulse Velocity Test
51

Rebound Hammer Test
52

Thermoplast Marking Test
53

Pile Load Test
54

Compressive Strength Test
55

Sign Board Reflectivity Test
56

Thanks
57
Hkkjrh; jk"Vªh; jktekxZizkf/kdj.k] jryke
Tags