Project evaluation in project management

engrasjadshahzad 16 views 15 slides Jul 09, 2024
Slide 1
Slide 1 of 15
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15

About This Presentation

evaluation


Slide Content

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-1
Project Evaluation and Control
Chapter 13

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-2
The Project Control Cycle
1.Setting a Goal
4.Taking Action
and Recycling
the Process
2.Measuring
Progress
3.Comparing Actual
with Planned

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-3
The Project S-Curve
Elapsed Time (in weeks)
105 45403530252015 50
20
60
40
Cumulative Cost ($ in thousands)
Cumulative
Budgeted Cost
Cumulative
Actual Cost
$10,000 Negative Var

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-4
Milestone Analysis
Milestones are events or stagesof the project
that represent a significant accomplishment.
Milestones
…show completion of important steps
…signalthe team and suppliers
…can motivatethe team
…offer reevaluationpoints
…help coordinateschedules
…identifykey review gates
…delineatework packages

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-5
Tracking Gantt Chart
Project status is updated by
linking task completion to the
schedule baseline

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-6
Earned Value Management
Schedule
Cost
Performance
Tracking Control Charts
Cost
Performance Schedule
Earned
Value
Project
S-Curves
Cost
Performance Schedule

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-7
Earned Value Terms
Planned value (PV)
Earned value (EV)
Actual cost of work performed (AC)
Schedule performance index (SPI)
Cost performance index (CPI)
Budgeted cost at completion (BAC)

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-8
Steps in Earned Value Management
1.Clearly define each activityincluding its
resource needs and budget
2.Create usage schedulesfor activities and
resources
3.Develop a time-phased budget(PV)
4.Total the actual costsof doing each task (AC)
5.Calculateboth the budget variance (CV) and
schedule variance (SV)

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-9
Earned Value Milestones
PV EV
AC
Slip
Overspend
Schedule Performed
Actual
Budget
Schedule
Cost

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-10
Earned Value Example
ActivityJanFebMarAprilPlan%CValue
Staffing87 1510015
Blueprint 4 61080 8
Prototype 2 81060 6
Design 3 333 1
Mon Plan8761738∑ 30
Cmltv 8152138
Mon Act 811813
Cmltv Act8192740
Planned Value
38=15+10+10+3
Earned Value
30=15+8+6+1
Value
8=80%(10)
Cumulative
40=8+11+8+13

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-11
Earned Value Example
Schedule Variances
Planned Value (PV) = 38 = 15+10+10+3
Earned Value (EV) = 30 = 15+8+6+1
Schedule Performance Index = .79 = 30/38 = EV/PV
Estimated Time to Completion = (1/.79)x4=5
Cost Variances
Actual Cost of Work Performed (AC) = 40 = 8+11+8+13
Cost Performance Index = .75 = 30/40 = EV/AC
Estimated Cost to Completion = 50.7 = (1/.75)x38

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-12
Completion Values in EVM
Accurateand up-to-dateinformation is critical
in the use of EVM
0/100 Rule
50/50 Rule
Percentage Complete Rule

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-13
Human Factors in
Project Evaluation & Control
Optimistic progress reports
Level of detail
Process evaluation
Non-technical performance measurement

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-14
Critical Success Factors in the
Project Implementation Profile
1.Project mission
2.Top management support
3.Project plans & schedules
4.Client consultation
5.Personnel
6.Technical tasks
7.Client acceptance
8.Monitoring & feedback
9.Communication channels
10.Troubleshooting

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 13-15
Tags