Project Management, What are the Key Metrics

pmp02pmp02 6 views 47 slides Aug 29, 2025
Slide 1
Slide 1 of 47
Slide 1
1
Slide 2
2
Slide 3
3
Slide 4
4
Slide 5
5
Slide 6
6
Slide 7
7
Slide 8
8
Slide 9
9
Slide 10
10
Slide 11
11
Slide 12
12
Slide 13
13
Slide 14
14
Slide 15
15
Slide 16
16
Slide 17
17
Slide 18
18
Slide 19
19
Slide 20
20
Slide 21
21
Slide 22
22
Slide 23
23
Slide 24
24
Slide 25
25
Slide 26
26
Slide 27
27
Slide 28
28
Slide 29
29
Slide 30
30
Slide 31
31
Slide 32
32
Slide 33
33
Slide 34
34
Slide 35
35
Slide 36
36
Slide 37
37
Slide 38
38
Slide 39
39
Slide 40
40
Slide 41
41
Slide 42
42
Slide 43
43
Slide 44
44
Slide 45
45
Slide 46
46
Slide 47
47

About This Presentation

Na


Slide Content

McGraw-Hill/Irwin Copyright © 2007 by The McGraw-Hill Companies, Inc. All rights reserved.
1717
Project
Management

17-2
Learning ObjectivesLearning Objectives
Discuss the behavioral aspects of projects
in terms of project personnel and the
project manager.
Discuss the nature and importance of a
work breakdown structure in project
management.
Give a general description of PERT/CPM
techniques.
Construct simple network diagrams.

17-3
Learning ObjectivesLearning Objectives
List the kinds of information that a PERT or
CPM analysis can provide.
Analyze networks with deterministic times.
Analyze networks with probabilistic times.
Describe activity “crashing” and solve
typical problems.

17-4
Unique, one-time operations designed to Unique, one-time operations designed to
accomplish a specific set of objectives in a limited accomplish a specific set of objectives in a limited
time frame.time frame.
Build A
A Done
Build B
B Done
Build C
C Done
Build D
Ship
JANFEBMAR APRMAY JUN
On time!
ProjectsProjects

17-5
Project ManagementProject Management
How is it different?
Limited time frame
Narrow focus, specific objectives
Less bureaucratic
Why is it used?
Special needs
Pressures for new or improves products or
services

17-6
Project ManagementProject Management
What are the Key Metrics
Time
Cost
Performance objectives
What are the Key Success Factors?
Top-down commitment
Having a capable project manager
Having time to plan
Careful tracking and control
Good communications

17-7
Project ManagementProject Management
What are the Major Administrative
Issues?
Executive responsibilities
Project selection
Project manager selection
Organizational structure
Organizational alternatives
Manage within functional unit
Assign a coordinator
Use a matrix organization with a project leader

17-8
Project ManagementProject Management
What are the tools?
Work breakdown structure
Network diagram
Gantt charts
Risk management

17-9
Planning and SchedulingPlanning and Scheduling
MARAPRMAYJUNJULAUGSEPOCTNOVDEC
Locate new
facilities
Interview staff
Hire and train staff
Select and order
furniture
Remodel and install
phones
Move in/startup
Gantt Chart

17-10
Deciding which projects to implement
Selecting a project manager
Selecting a project team
Planning and designing the project
Managing and controlling project resources
Deciding if and when a project should be
terminated
Key DecisionsKey Decisions

17-11
Project ManagerProject Manager
Responsible for:
Work Quality
Human Resources Time
Communications Costs

17-12
Temptation to understate costs
Withhold information
Misleading status reports
Falsifying records
Comprising workers’ safety
Approving substandard work
Ethical IssuesEthical Issues

17-13
Project Life CycleProject Life Cycle
Concept
Feasibility
Planning
Execution
Termination
M
a
n
a
g
e
m
e
n
t

17-14
Work Breakdown StructureWork Breakdown Structure
Project X
Level 1
Level 2
Level 3
Level 4
Figure 17.2

17-15
PERT and CPMPERT and CPM
PERT: Program Evaluation and
Review Technique
CPM: Critical Path Method
Graphically displays project activities
Estimates how long the project will take
Indicates most critical activities
Show where delays will not affect project

17-16
The Network DiagramThe Network Diagram
Network (precedence) diagram – diagram of
project activities that shows sequential
relationships by the use of arrows and nodes.
Activity-on-arrow (AOA) – a network diagram
convention in which arrows designate activities.
Activity-on-node (AON) – a network diagram
convention in which nodes designate activities.
Activities – steps in the project that consume
resources and/or time.
Events – the starting and finishing of activities,
designated by nodes in the AOA convention.

17-17
The Network Diagram (cont’d)The Network Diagram (cont’d)
Path
Sequence of activities that leads from the starting
node to the finishing node
Critical path
The longest path; determines expected project
duration
Critical activities
Activities on the critical path
Slack
Allowable slippage for path; the difference the
length of path and the length of critical path

17-18
Project Network – Activity on Project Network – Activity on
ArrowArrow
1
2
3
4
5 6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Hire and
train
Remodel
Move
in
Figure 17.4
AOA

17-19
Project Network – Activity on Project Network – Activity on
NodeNode
1
2
3
5
6
Locate
facilities
Order
furniture
Furniture
setup
Interview
Remodel
Move
in
4
Hire and
train
7S
Figure 17.4
AON

17-20
Network ConventionsNetwork Conventions
a
b
c a
b
c
a
b
c
d
a
b
c
Dummy
activity

17-21
Time EstimatesTime Estimates
Deterministic
Time estimates that are fairly certain
Probabilistic
Estimates of times that allow for variation

17-22
Example 1Example 1
1
2
3
4
5 6
8 weeks
6 weeks
3 weeks
4 weeks
9 weeks
11 weeks
1 week
Locate
facilities
Order
furniture
F
u
r
n
i
t
u
r
e
s
e
t
u
p
I
n
t
e
r
v
i
e
w
H
ire and train
R
e
m
o
d
e
l
Move
in
DeterministicDeterministic
time estimatestime estimates
Figure 17.5

17-23
Example 1 SolutionExample 1 Solution
P a t h L e n g t h
( w e e k s )
S l a c k
1 - 2 - 3 - 4 - 5 - 6
1 - 2 - 5 - 6
1 - 3 - 5 - 6
1 8
2 0
1 4
2
0
6
Critical Path

17-24
Network activities
ES: early start
EF: early finish
LS: late start
LF: late finish
Used to determine
Expected project duration
Slack time
Critical path
Computing AlgorithmComputing Algorithm

17-25
Probabilistic Time EstimatesProbabilistic Time Estimates
Optimistic time
Time required under optimal conditions
Pessimistic time
Time required under worst conditions
Most likely time
Most probable length of time that will be
required

17-26
Probabilistic EstimatesProbabilistic Estimates
Activity
start
Optimistic
time
Most likely
time (mode)
Pessimistic
time
t
o t
pt
mt
e
Figure 17.8
Beta Distribution

17-27
Expected TimeExpected Time
t
e =
t
o
+ 4t
m
+t
p
6
t
e = expected time
t
o = optimistic time
t
m = most likely time
t
p = pessimistic time

17-28
VarianceVariance



(t
p – t
o)
2
36


= variance
t
o = optimistic time
t
p = pessimistic time

17-29
Example 5Example 5
1-3-4
a
3-4-5
d
3-5-7
e
5-7-9
f
2-4-6
b
4-6-8
h
2
-
3
-
6
g 3 - 4 - 6
i
2
-
3
-
5
c
Optimistic
time
Most likely
time
Pessimistic
time

17-30
Example 5 Time EstimatesExample 5 Time Estimates
2.83
a
4.00
d
5.0
e
7.0
f
4.00
b
6.0
h
3
.
3
3
g 4 . 1 7
i
3
.
1
7
c
T
abc
= 10.0
T
def
= 16.0
T
ghi
= 13.50

17-31
Path ProbabilitiesPath Probabilities
Z =
Specified time – Path mean
Path standard deviation
Z indicates how many standard deviations
of the path distribution the specified tine
is beyond the expected path duration.

17-32
17
Weeks
Weeks
Weeks
Weeks
10.0
16.0
13.5
1.00
1.00
a-b-c
d-e-f
g-h-i
Example 6Example 6

17-33
Time-cost Trade-offs: CrashingTime-cost Trade-offs: Crashing
Crash – shortening activity duration
Procedure for crashing
Crash the project one period at a time
Only an activity on the critical path
Crash the least expensive activity
Multiple critical paths: find the sum of
crashing the least expensive activity on
each critical path

17-34
Time-Cost Trade-Offs: CrashingTime-Cost Trade-Offs: Crashing
Total
cost
Shorten
Shorten
Cumulative
cost of
crashing
Expected indirect costs
Optimum
CRASH
Figure 17.11

17-35
6
a
4
d
5
c
1
0
b
9
e
2
f
Example 7Example 7

17-36
Advantages of PERTAdvantages of PERT
Forces managers to organize
Provides graphic display of activities
Identifies
Critical activities
Slack activities
1
2
3
4
5 6

17-37
Limitations of PERTLimitations of PERT
Important activities may be omitted
Precedence relationships may not be
correct
Estimates may include
a fudge factor
May focus solely
on critical path
1
2
3
4
5 6
142 weeks

17-38
Goldratt’s Critical ChainGoldratt’s Critical Chain
Goldratt’s insight on project management
Time estimates are often pessimistic
Activities finished ahead of schedule often go
unreported
With multiple projects, resources needed for one
project may be in use on another

17-39
Computer aided design (CAD)
Groupware (Lotus Notes)
CA Super Project
Harvard Total Manager
MS Project
Sure Track Project Manager
Time Line
Project Management SoftwareProject Management Software

17-40
Imposes a methodology
Provides logical planning structure
Enhances team communication
Flag constraint violations
Automatic report formats
Multiple levels of reports
Enables what-if scenarios
Generates various chart types
Advantages of PM SoftwareAdvantages of PM Software

17-41
Risk: occurrence of events that have
undesirable consequences
Delays
Increased costs
Inability to meet specifications
Project termination
Project Risk ManagementProject Risk Management

17-42
Identify potential risks
Analyze and assess risks
Work to minimize occurrence of risk
Establish contingency plans
Risk ManagementRisk Management

17-43
SummarySummary
Projects are a unique set of activities
Projects go through life cycles
PERT and CPM are two common
techniques
Network diagrams
Project management software available

17-44
Video: Work BreakdownVideo: Work Breakdown

17-45
Video: Project Materials/DelaysVideo: Project Materials/Delays

17-46
Video: Project SchedulingVideo: Project Scheduling

17-47
Video: PERT/CPMVideo: PERT/CPM
Tags