Project photos of Caliagua's new Telemark project for FivePoint.
jhines4
0 views
6 slides
Oct 14, 2025
Slide 1 of 6
1
2
3
4
5
6
About This Presentation
Caliagua is a heavy civil engineering general contractor working in the water and wastewater treatment industry. This presentation reviews a new project of ours for the FivePoint community. Project Photos from Caliagua's Telemark project.
Size: 9.92 MB
Language: en
Added: Oct 14, 2025
Slides: 6 pages
Slide Content
Aerial overview of the Telemark Booster Pump Station site showing
excavation limits, staging areas, and access routes. Layout and dig
operations for the recycled-water pump cans were in progress during
this period
Layout and excavation for RW pump cans; survey control verified and
excavation depths checked prior to setting cans
Preassembled pump cans with reinforcement cages staged for
placement. Cages fabricated and inspected for dimensional compliance
and proper spacing prior to lowering into excavations for encasement
Preassembled pump cans with reinforcement
cages staged for placement. Cages fabricated and
inspected for dimensional compliance and proper
spacing prior to lowering into excavations for
encasement.
Concrete encasement pour in progress at RW pump cans; crew placing
and consolidating per pre-pour inspection and approved submittals (
Installation of recycled-water suction and discharge header piping
through the pump station slab and into pump can assemblies. Crews
performing alignment and joint integrity checks prior to hydrostatic
testing.