Project Status Update for year 2022 month 06 date 22.pptx

SuriaRao2 7 views 1 slides Aug 26, 2024
Slide 1
Slide 1 of 1
Slide 1
1

About This Presentation

Project Status Update for users to understand and know where the current stop is at or the just involved in the existing process


Slide Content

Timeline Estimation 02-May-2022 CypherSign Web (Without eKYC ) Item Start Date End Date To finalize UAT Script 14-Apr 14-Apr UAT 19-Apr 20-Apr Patched update (Mobile view, signature history, gif signing introduction flow) 27-Apr 27-Apr Production Live (Soft Launch) 2-May 2-May Project signed-off stage 21-June 21-June