Proyek 35 000 MW RUPTL 2014 - 2025

Sumatera

Rencana pembangunan PLTU No PLTU Kapasitas Tahun 1 Meulaboh 200 MW 2019-2020 2 Pangkalan Susu 200 MW 2018 3 Jambi 600 MW 2019 4 Sumsel 7 2 x 150 MW 2018 5 Bengkulu 2 x 100 MW 2019 5 Sumsel - 1 2 x 300 MW 2018 6 Sumsel-6 1 x 300 MW 2019 7 Sumbagsel 7 2 x 150 MW 2018 8 Sewa 2 x 30 MW 2019

Jawa

Rencana pembangunan PLTU No PLTU Kapasitas Tahun 1 Indramayu 2 x 1000 MW 2019-2020 2 Jawa 5 1 x 1000 MW 2018 3 Jawa 1 1 x 1000 MW 2019 4 Jawa 3 2 x 660 MW 2021 5 Jateng 2 x 1000 MW 2019 5 Jawa 10 2 x 600 MW 2019 6 Jawa 13 2 x 1000 MW 2024 7 Jawa 4 2 x 1000 MW 2019 8 Jawa 11 2 x 600 MW 2021

Kalimantan

Rencana pembangunan PLTU No PLTU Kapasitas Tahun 1 Kaltim (FTP 2) 1 x 200 MW 2018-2019 2 Kaltim (Mulut Tambang) 1 x 55 MW 2017 3 Kaltim 4 1 x 200 MW 2019/2020 4 Kaltim 3 1 x 400 MW 2022/2023 5 Kaltim 5 1 x 400 MW 2023/2024 5 Kalsel (FTP2) 1 x 200 MW 2017 6 Kalselteng 2 1 x 200 MW 2017 7 Kalteng 3 1 x 200 MW 2020/2021 8 Kalteng 1 1 x 200 MW 2019/2020 9 Ketapang FTP 2 20 MW 2016 10 Kalbar 3 1 x 400 MW 2023/2024 11 Kalbar 1 1 x 200 MW 2018 12 Kalbar 2 1 x 400 MW 2020/2021 13 Pulau Baru 1 x 110 MW 2017/2018

Sulawesi

Rencana pembangunan PLTU No PLTU Kapasitas Tahun 1 Sulut 3 1 x 100 MW 2019-2020 2 Sulbagut 1 x 200 MW 2022/2023 3 Amurang 1 x 50 MW 2017 4 Sulut 1 1 x 50 MW 2018 5 Sulbagut 1 1 x 100 MW 2019/2020 6 Gorontalo 1 x 30 MW 2017 7 Gorontalo 3 1 x 100 MW 2019/2020 8 Toli-Toli 1 x 50 MW 2020/2021 9 Palu 3 1 x 100 MW 2018 10 Tawaele 30 MW 2016 11 Kendari 3 1 x 100 MW 2018 12 Mampu 1 x 50 MW 2017 13 Sulsel 2 1 x 400 MW 2019/2020 14 Sulsel Baru 2 1 x 100 MW 2018 15 Punagaya 1 x 200 MW 2017/2018 16 Jeneponto 250 MW 2018/2019 17 Bau-Bau IPP 14 MW 2019 18 Wangi-Wangi 6 MW 2019

Nusa Tenggara Barat

Rencana pembangunan PLTU No PLTU Kapasitas Tahun 1 Lombok 3 1 x 100 MW 2023-2024 2 Sambaluh FTP 2 1 x 20 MW 2021 3 Lombok Timur 2 x 25 MW 2017 4 Lombok 2 x 50 MW 2018/2019 5 Lombok 2 2 x 50 MW 2019/2020